Ozaukee County Distribution Interconnection Project

ATC is proposing an expansion and upgrade of our electric system that would include building new power lines, rebuilding existing power lines, constructing up to five new substations and maintenance work on sections of existing power lines. The project would include parts of Calumet, Fond du Lac, Sheboygan, Ozaukee and Washington counties in east central Wisconsin.  

The proposed project is needed to reliably serve a load interconnection request by We Energies to serve a new large load addition in the Port Washington area, and maintain the safe and reliable operation of ATC’s system.

The project is subject to approval by the Public Service Commission of Wisconsin.

Additional information about the proposed project can be found on the Public Service Commission of Wisconsin website, under docket number 137-CE-221.

Rebuilding and upgrading existing lines from the Forest Junction Substation east of Appleton to a new proposed Sheboygan River Substation east of Fond du Lac. 

  • The Preferred Route would involve a rebuild of an existing single circuit line to a dual-circuit line largely within the existing utility corridor. 
  • The Alternate Route would involve building a new line adjacent to an existing corridor, where possible, and in new corridors where it’s not possible. 

Rebuilding and upgrading existing lines to connect a new proposed Mullet River Junction Substation near Sheboygan Falls with a new proposed Cedar Creek Junction Substation west of Saukville. 

  • Preferred Route – Rebuild the existing single-circuit 345-kV line as a dual-circuit 345-kV line. 
  • Preferred Route – Construct a new dual-circuit 345-kV line from the town of Saukville to meet with existing power lines about 9 miles to the west. 
  • Alternate Route – Rebuild an existing dual-circuit 138/345-kV line to a dual-circuit 345-kV line. 
  • Alternate Route – Construct two new 138-kV power lines from the existing Holland Substation to a new proposed Adell Substation south of Adell. 

Constructing two new dual-circuit lines (four lines) between a new proposed Decker Substation in Port Washington to the existing transmission system 

Building up to 5 new substations and completing minor remote end substation work.

Maintenance work on sections of existing power lines through structure replacements, burial of distribution spans or amp-jacking structures.

Milestones

September 2025

The application was submitted to the PSCW.

Spring 2026

Anticipated timeframe for PSCW decision.

Spring 2026 (after approval)

Project construction is anticipated to begin.

Late 2027

Project is anticipated to be in service.

September 2025

The application was submitted to the PSCW.

*Dates are anticipated and subject to changes
Spring 2026

Anticipated timeframe for PSCW decision.

*Dates are anticipated and subject to changes
Spring 2026 (after approval)

Project construction is anticipated to begin.

*Dates are anticipated and subject to changes
Late 2027

Project is anticipated to be in service.

*Dates are anticipated and subject to changes

Project FAQ's

A:

The proposed project is needed to address proposed load increases in the Port Washington area and maintain the safe and reliable operation of ATC’s system. 

A:

The Public Service Commission of Wisconsin  is the regulatory agency with the authority to approve or deny the proposed project and select the final route.

A:

Yes. Now that ATC’s application has been submitted to the PSCW, in the coming months they will put in place a process for collecting public comments and receiving testimony during public hearings.

A:

As part of the routing and siting process, ATC follows the power line routing priorities established by state law, which favor colocation with existing facilities and infrastructure – like existing power lines and pipelines, highways, and railroads – where it is feasible. This is intended to reduce the impact on local areas and communities. 

A:

If you have additional questions about the project or would like to discuss it in more detail, please contact Zac Tretow with ATC Local Relations at (262) 506-6901 or ztretow@atcllc.com.