Northern Adams County Area Network Improvement Project

  • Colburn Substation – Planned by Adams-Columbia Electric Cooperative as a separate project, this new substation in Adams County will serve area load growth and electric reliability. 
  • New ATC Facilities – ATC is building and installing facilities to interconnect the new, planned ACEC Colburn Substation to the regional electric grid to improve the networking and reliability of existing electric infrastructure in the region.  

ATC is making system upgrades to connect the new, planned ACEC Colburn Substation to the regional electric grid. The Colburn Substation is planned for a site near the intersection of Bighorn Avenue and 7th Avenue in the town of Big Flats. The project will also provide an additional source to the existing 69-kilovolt, Y-302 circuit which will bring greater reliability to three existing local distribution substations.

This ATC project includes:

  • Building approximately 4.5 miles of new, 69-kV power line from the ACEC Cottonville Substation to the new ACEC Colburn Substation. This new power line will be an extension to the existing ATC 69-kV, Y-302 power line in the town of Big Flats. The extended line will run on the south side of Bighorn Avenue from 7th Avenue to 11th Avenue.
  • Building approximately 5.1 miles of new, 69-kV power line from the ACEC Badger West Substation to State Highway 13. This new power line will be built in the towns of Rome and Monroe. It will also be an extension to the existing ATC 69-kV, Y-302 power line.
  • Improving networking service to three ACEC substations. 
  • Expanding the ACEC Badger West Substation to create a new 138-kV to 69-kV connection point on the system. 

The project supports the connection of the proposed ACEC Colburn Substation to the regional electric grid to ensure electric reliability and address current and future energy needs in the surrounding area. It will provide a second source for the new and existing loads served by the power line, and help relieve constraints on the current electric delivery system, improve reliability and support local energy demand. 

The ATC project was approved by the Public Service Commission of Wisconsin in May 2026. 

Additional information about the ATC project can be found on the PSCW website, under docket number 137-CE-213

Milestones

January 2025

The application was submitted to the PSCW.

May 2026

The project received a final, written approval order from the PSCW.

2Q 2026

Project construction is anticipated to begin.

3Q 2027

Project is anticipated to be in service.

January 2025

The application was submitted to the PSCW.

*Dates are anticipated and subject to changes
May 2026

The project received a final, written approval order from the PSCW.

*Dates are anticipated and subject to changes
2Q 2026

Project construction is anticipated to begin.

*Dates are anticipated and subject to changes
3Q 2027

Project is anticipated to be in service.

*Dates are anticipated and subject to changes

Project FAQ's

A:

The project is necessary to interconnect to the regional electric grid a new, Adams-Columbia Electric Cooperative substation. The planned location for the new ACEC Colburn Substation is near the intersection of Bighorn Avenue and 7th Avenue in the town of Big Flats in Adams County.

A:

The Public Service Commission of Wisconsin (PSCW) is the regulatory agency with the authority to approve or deny a project. The PSCW gave final approval to the project in May 2026.

A:

If you have additional questions about the power line project or would like to discuss it in more detail, please contact Kurt Hendrickson, ATC Local Relations: (920) 338-6515 or khendrickson@atcllc.com.

A:

If you have additional questions about the planned Colburn Substation project or would like to discuss it in more detail, please contact Mark LaMore, Adams-Columbia Electric Cooperative: (800) 831-8629 or mlamore@acecwi.com.