Plymouth Reliability Project

Plymouth 5 Substation – Built by Plymouth Utilities as a separate project, this new substation serves area electric reliability and load needs.

ATC Power Line – A new, approximately 7-mile, double-circuit 138-kilovolt power line connects the Plymouth 5 Substation to an existing ATC 138-kV line.

The new power line that connects to the Plymouth 5 Substation was needed to ensure electric reliability and address current and future energy needs in the community and the surrounding area. The substation and power line relieve constraints on the current electric delivery system, improve reliability and support local energy demand.

Additional information about the ATC power line can be found on the PSCW website, under docket number 137-CE-205. Additional information about the Plymouth 5 Substation can be found on the  PSCW website, under docket number 4740-CE-106.

Project Contacts

ATC power line

Kurt Hendrickson
(920) 338-6515

ATC real estate

Perri Petropoulos
(866) 899-3204 , ext. 6738

Plymouth Utilities

Tim Blakeslee
(920) 893-3745

Media Contact
(877) 506-6117

Milestones

January 2024

The application was submitted to the PSCW.

January 2025

The project received a final, written approval order from the PSCW.

Fall 2025

Project construction began.

May 2026

Project was placed in service.

Summer 2026

Project restoration is ongoing.

January 2024

The application was submitted to the PSCW.

*Dates are anticipated and subject to changes
January 2025

The project received a final, written approval order from the PSCW.

*Dates are anticipated and subject to changes
Fall 2025

Project construction began.

*Dates are anticipated and subject to changes
May 2026

Project was placed in service.

*Dates are anticipated and subject to changes
Summer 2026

Project restoration is ongoing.

*Dates are anticipated and subject to changes

Structures to be used

An angle structure pole

Angle structure poles will connect the Plymouth 5 Substation to an existing ATC 138-kV line.

Tangent Pole

Tangent poles will also be used to connect the Plymouth 5 Substation to an existing ATC 138-kV line.

Angle structure poles will connect the Plymouth 5 Substation to an existing ATC 138-kV line.

Tangent poles will also be used to connect the Plymouth 5 Substation to an existing ATC 138-kV line.

Project FAQ's

A:

The new power line connects to the Plymouth 5 Substation that is needed to ensure electric reliability and address current and future energy needs in the community and the surrounding area. The substation and power line relieve constraints on the current electric delivery system, improve reliability and support local energy demand.

The southwestern portion of the Plymouth Utilities service territory had reached near capacity in recent years. A new substation was necessary to improve service reliability for local utility customers.

A:

The Public Service Commission of Wisconsin is the regulatory agency with the authority to approve or deny a project, as well as choose the final route, in the event of approval. In this case, ATC proposed two routes, the power line project was approved by the PSCW, and the PSCW selected the Ordered Route that is shown on the PDF map.

A:

If you have additional questions about the power line project or would like to discuss it in more detail, please contact Kurt Hendrickson with ATC Local Relations at (920) 338-6515 or khendrickson@atcllc.com.

A:

If you have additional questions about the Plymouth 5 Substation project or would like to discuss it in more detail, please contact Tim Blakeslee, city administrator and utilities manager with the City of Plymouth at (920) 893-3745 or tblakeslee@plymouthwi.gov.