Elm Road – Racine Project

ATC will connect the existing Elm Road Substation in Oak Creek to the Racine Substation in Racine. This includes constructing approximately 3.7 miles of new power line and reconfiguring approximately nine miles of existing power line to 345 kilovolts.  

The key elements of the project include:  

  • Build a new 3.7-mile, 345-kV line that would generally run south and west out of the Elm Road Substation and into the village of Caledonia. 
    • About 1.5 miles of the new 345-kV line would run along a route out of the Elm Road Substation. 
    • Nearly 2.2 miles of the new 345-kV line would run along the approved route. Some adjustments may be required to existing lines in areas where the new lines would cross. 
  • Upgrade an existing, approximately 9-mile line to 345-kV using the structures and conductor wire that are already in place. Some construction may be required to connect the existing line to the new line on the north end and to the substation on the south end. 

The estimated project cost is approximately $64 million. The project was identified and approved by the Midcontinent Independent System Operator. Because it provides regional benefits the cost will be shared with energy consumers from multiple states – not just Wisconsin. 

The project is needed to reduce constraints on the electric grid, maintain reliability, support increasing demand for energy and provide access to lower-cost energy including renewable generation. 

The project received final approval by the Public Service Commission of Wisconsin.  

Additional information about the project can be found on the Public Service Commission of Wisconsin website, under docket number 137-CE-215. 

Milestones

August 2025

The application was submitted to the PSCW.

September 2026

Project received final approval from the PSCW.

Q2 2028

Project construction is anticipated to begin.

Q1 2029

Project is anticipated to be in service.

August 2025

The application was submitted to the PSCW.

*Dates are anticipated and subject to changes
September 2026

Project received final approval from the PSCW.

*Dates are anticipated and subject to changes
Q2 2028

Project construction is anticipated to begin.

*Dates are anticipated and subject to changes
Q1 2029

Project is anticipated to be in service.

*Dates are anticipated and subject to changes

Project FAQ's

A:

The project is needed to reduce constraints on the electric grid, increase reliability, address generator and load interconnection needs, and provide access to lower-cost energy including renewable generation. 

A:

The Public Service Commission of Wisconsin approved the project and selected the final route.  

A:

The estimated cost of the project will be approximately $64 million.

A:

This project was identified and approved by MISO and it provides regional benefits so the cost will be shared with energy consumers from multiple states – not just Wisconsin. Given the cost of the project will be shared, Wisconsin energy consumers have typically shouldered 13 to 16 percent of the total cost for these types of projects. This makes regional grid projects an exceptional value for Wisconsin’s energy consumers.