Stevens Point-Appleton Rebuild Project

  • ATC is proposing the Stevens Point-Appleton 345-kilovolt Rebuild Project in Portage, Waupaca, and Outagamie counties. 
  • The project includes rebuilding and upgrading an existing 345-kV power line between the Stevens Point and Appleton areas. ATC is currently evaluating alternative routes as part of the routing and siting process. 
  • The project is subject to review and approval by the Public Service Commission of Wisconsin.
  • The project was identified through the Midcontinent Independent System Operator’s long-range transmission planning process and is classified as a Multi-Value Project designed to support reliability and future energy needs throughout the region.

The proposed project is needed to address aging infrastructure, improve reliability and support growing demand on the power grid. It will help address increasing demand on the transmission system and reduce system constraints to support current and future energy needs.

We will be hosting a live online open house. Registration is required to participate.

Live online open house – Aug. 20, 2026 at 5:30 p.m.
To register, click on the register button at the top of the page.

ATC will also hold two in-person open house sessions. These do not require registration. There will not be a formal presentation, so please feel free to attend any of the sessions. You will have the opportunity to submit a comment. All written comments we receive are included in our application to the PSCW.

In-person open house – Wednesday, Aug. 26, 2026In-person open house – Thursday, Aug. 27, 2026
Session One: 12:30 – 2:30 p.m. 
Session Two: 4 – 6 p.m. 
Best Western Premier Bridgewood Resort Hotel 
1000 Cameron Way, Neenah, WI 54956
Session One: 12:30 – 2:30 p.m. 
Session Two: 4 – 6 p.m. 
Foxfire Golf Club at Par4 Resort 
201 Foxfire Dr., Waupaca, WI 54981 

Milestones

Q3 2026
Q3 2027

Anticipated timeframe for application submittal to the PSCW.

Q3 2028

Anticipated timeframe for PSCW decision.

Q2 2030

(if approved) Project construction is anticipated to begin.

Q3 2032

Project is anticipated to be in service.

Q3 2026
*Dates are anticipated and subject to changes
Q3 2027

Anticipated timeframe for application submittal to the PSCW.

*Dates are anticipated and subject to changes
Q3 2028

Anticipated timeframe for PSCW decision.

*Dates are anticipated and subject to changes
Q2 2030

(if approved) Project construction is anticipated to begin.

*Dates are anticipated and subject to changes
Q3 2032

Project is anticipated to be in service.

*Dates are anticipated and subject to changes

Project FAQ's

A:

The existing transmission system in the area is experiencing increasing demand and system constraints. 

The Stevens Point-Appleton 345-kV Rebuild Project is intended to improve transmission system performance, increase transmission capacity, and maintain reliable electric service in the region. The project will help address increasing demand on the transmission system and reduce system constraints to support current and future energy needs. 

A:

The PSCW is the regulatory agency with the authority to approve or deny major utility projects in Wisconsin. 

As part of the routing and siting process, ATC will develop and evaluate route alternatives for the project. If the project is approved, the PSCW will select the final route for construction.

A:

Yes. Public engagement opportunities will occur throughout the routing and siting process, including public open houses and opportunities to provide input on route alternatives. 

When ATC submits an application to the PSCW, the commission will establish a process for collecting public comments and receiving testimony during the regulatory review process. 

A:

If you have additional questions about the Project or would like to discuss it in more detail, please contact Devin Renner with ATC Local Relations at (608) 877-3581 or drenner@atcllc.com.