American Transmission Co. http://www.atcllc.com Helping to keep the lights on, businesses running and communities strong. ® Thu, 26 Mar 2015 19:46:03 +0000 en-US hourly 1 PSC signals approval for Badger Coulee Transmission Line Project http://www.atcllc.com/whats-current/psc-signals-approval-for-badger-coulee-transmission-line-project/ http://www.atcllc.com/whats-current/psc-signals-approval-for-badger-coulee-transmission-line-project/#comments Thu, 26 Mar 2015 19:46:03 +0000 http://www.atcllc.com/?p=5210 PSC commissioners verbally approve Northern Route at open meeting; final order will be issued by April 24, 2015

MADISON, Wis. – Following more than four years of public involvement and regulatory review, the merits of the 345,000-volt Badger Coulee Transmission Line Project were discussed today by the Public Service Commission of Wisconsin. At an open meeting, the PSC commissioners agreed with the project’s need and benefits outlined by American Transmission Co. and Xcel Energy for the approximately 180-mile line, which will electrically connect the La Crosse area to northern Dane County. The next step is for the Commissioners’ discussion to be documented in a written order and then approved by the Commissioners at an open meeting before April 24, 2015.

“We appreciate the public’s active involvement throughout our public outreach and the regulatory review process,” said ATC Manager of Environmental and Local Relations Greg Levesque. “Public input helps identify ways to avoid and minimize environmental and community impacts. We will continue to communicate with affected property owners and communities in the years to come to ensure the safe construction of the line.”

During the meeting, PSC commissioners selected the Northern Route, which was one of the two options submitted by the applicants. More than 90 percent of the Northern Route uses existing utility and Interstate or U.S. highway corridors. The project’s end points are Xcel Energy’s new Briggs Road Substation near Holmen and ATC’s North Madison Substation in the Town of Vienna, continuing to ATC’s Cardinal Substation in the Town of Middleton. The PSC’s order for the project, including any minor route adjustments or conditions ATC and Xcel Energy must meet to construct the project, will be issued by April 24, 2015.

This project has been designated a Multi-Value Project by the Midcontinent Independent System Operator because it will enable the delivery of energy in support of reliability, economic and public policy benefits. The $580 million estimated project cost will be shared among all electric users in MISO’s footprint, which includes 15 Midwestern states and the Canadian province of Manitoba.

“We are pleased that the PSC has recognized the need for and benefits of this project.” said Xcel Energy Manager, Regional Transmission Initiatives Kyle Neidermire. “This project will help ensure electric reliability and provide access to lower-cost power and renewable energy for all electric users in the region.”

ATC and Xcel Energy will begin reaching out to impacted property owners along the selected route this year. Project construction is expected to begin in 2016 to meet an in-service date of 2018.

Note to editors:

A map of the proposed route options and additional project information are available at http://www.badgercoulee.com/.

ATC and Xcel Energy’s application and documents associated with the regulatory review process are available at http://www.psc.wi.gov/ under Docket No. 5-CE-142.

About ATC
American Transmission Co. is a Wisconsin-based company that owns and operates the electric transmission system in portions of the Upper Midwest. Formed in 2001 as the nation’s first multi-state transmission-only utility, ATC has invested $3.5 billion to improve the adequacy and reliability of its infrastructure. ATC now has $3.8 billion in assets, including more than 9,530 miles of transmission lines and 530 substations. The company is a member of the MISO regional transmission organization, and provides nondiscriminatory service to all customers, supporting effective competition in energy markets without favoring any market participant. For more information, visit our website at www.atcllc.com.

About Xcel Energy
Xcel Energy is a major U.S. electricity and natural gas company, with retail operations in eight Western and Midwestern states, including Wisconsin. Xcel Energy provides a comprehensive portfolio of energy-related products and services to 3.4 million electricity customers and 1.9 million natural gas customers through its regulated operating companies. Company headquarters are located in Minneapolis, and Wisconsin-Michigan operating company headquarters are located in Eau Claire, Wis. For more information about Xcel Energy visit www.xcelenergy.com.

]]>
http://www.atcllc.com/whats-current/psc-signals-approval-for-badger-coulee-transmission-line-project/feed/ 0
2014 annual report features best-in-class operations, community involvement, environmental stewardship http://www.atcllc.com/blog/2014-annual-report-features-best-in-class-operations-community-involvement-environmental-stewardship/ http://www.atcllc.com/blog/2014-annual-report-features-best-in-class-operations-community-involvement-environmental-stewardship/#comments Fri, 20 Mar 2015 17:53:29 +0000 http://www.atcllc.com/?p=5187 AnnualReport-2014Each year, American Transmission Co. issues an Annual Report that highlights construction and operations, project updates, financial information and more.

2014 highlights include:

Operational excellence: We earned a “best in class” performance rating for 100- to 161-kilovolt circuits in a longitudinal industry study and ranked in the top 10 percent for 345- to 500-kV circuits.

Improved electric reliability, innovative technology: A project near St. Ignace, Mich., to better manage the flow of electricity between Upper and Lower Michigan. The flow-control device, one of only three such facilities in the country, began providing geographically widespread reliability benefits soon after it began commercial operation.

Environmental activities above and beyond the lines: Stewardship efforts and work this year included a study of bee habitat and behavior in transmission line corridors, projects to curb the spread of invasive species and the company’s Avian Protection Program.

Giving back: Employees are at the heart of the company’s community relations; more than 100 employees participated in United Way Days of Caring activities around the state. ATC connects with communities in other ways, including sponsorships benefiting Children’s Hospital of Wisconsin, Big Brothers Big Sisters, Junior Achievement, the Urban League and the YMCA. The company contributed $600,000 to more than 500 charitable and community programs in the area it serves.

 

]]>
http://www.atcllc.com/blog/2014-annual-report-features-best-in-class-operations-community-involvement-environmental-stewardship/feed/ 0
ATC releases 2014 annual report http://www.atcllc.com/whats-current/atc-releases-2014-annual-report/ http://www.atcllc.com/whats-current/atc-releases-2014-annual-report/#comments Fri, 20 Mar 2015 17:49:04 +0000 http://www.atcllc.com/?p=5185 Features best-in-class operations, community involvement, environmental stewardship

PEWAUKEE, Wis. – Innovation and excellence are the themes highlighted in American Transmission Co.’s 2014 annual report, available at the company’s website, www.atcllc.com, today.

The transmission-only electric utility earned a “best in class” performance rating for 100- to 161-kilovolt circuits in a longitudinal industry study and ranked in the top 10 percent for 345- to 500-kV circuits. Company investments in its construction program included an innovative project near St. Ignace, Mich., to better manage the flow of electricity between Upper and Lower Michigan. The flow-control device, one of only three such facilities in the country, began providing geographically widespread reliability benefits soon after it began commercial operation.

Also featured in the report are a number of environmental stewardship activities that “go above and beyond the lines,” including a study of bee habitat and behavior in transmission line corridors, projects to curb the spread of invasive species and the company’s Avian Protection Program.

Employees are at the heart of the company’s community relations; more than 100 employees participated in United Way Days of Caring activities around the state. ATC connects with communities in other ways, including sponsorships benefiting Children’s Hospital of Wisconsin, Big Brothers Big Sisters, Junior Achievement, the Urban League and the YMCA. The company contributed $600,000 to more than 500 charitable and community programs in the area it serves.

]]>
http://www.atcllc.com/whats-current/atc-releases-2014-annual-report/feed/ 0
ATC receives award for supporting programs at Milwaukee County Zoo http://www.atcllc.com/blog/atc-receives-award-for-supporting-programs-at-milwaukee-county-zoo/ http://www.atcllc.com/blog/atc-receives-award-for-supporting-programs-at-milwaukee-county-zoo/#comments Mon, 16 Mar 2015 15:21:16 +0000 http://www.atcllc.com/?p=5172 Now we know how big an elephant’s footprint really is. 2015_ZooAward_group-web The award even has a real African elephant footprint. We’re proud to support the important education and conservation work the Zoological Society of Milwaukee provides to the community.

Over the past decade, ATC has sponsored Party for the Planet, a two-day event that celebrates Earth Day and Migratory Bird Day. The event helps educate zoo visitors about environmental stewardship with fun, interactive activities. Our exhibit allows visitors to compare their wingspan to those of a bald eagle, whooping crane, osprey and black crow. ATC strives to minimize the impact that transmission line construction and operation have on wildlife throughout our service area with our Avian Protection program.2015_ZooAward_wingspan

Last year, a local Cub Scout troop helped Milwaukee County Zoo Forester Alex Krutsch and other volunteers plant more than 100 native trees and shrubs representing 13 different species on the zoo grounds. ATC provided the zoo with assistance for removing damaged vegetation and invasive species and replacing them with native trees and shrubs. Restoration of this area was done to help to diversify plant and animal species, improve air quality, reduce the zoo’s carbon footprint and enhance the beauty of the zoo. ATC supports the planting of trees and vegetation a safe distance from transmission lines to help ensure public safety and ensure electric system reliability. You can learn more about it by checking out our Grow Smart program.2015_ZooAward_CubScouts

Watch a short video to see the fun we had at the Zoo during Party for the Planet last year.

]]>
http://www.atcllc.com/blog/atc-receives-award-for-supporting-programs-at-milwaukee-county-zoo/feed/ 0
Paris-Albers transmission line placed into service http://www.atcllc.com/whats-current/paris-albers-transmission-line-placed-into-service/ http://www.atcllc.com/whats-current/paris-albers-transmission-line-placed-into-service/#comments Fri, 13 Mar 2015 19:13:38 +0000 http://www.atcllc.com/?p=5162 Project enhances safety, reliability

PEWAUKEE, Wis. – American Transmission Co. today energized the Paris-Albers Rebuild Project in Kenosha County. The 138,000-volt, 12.5-mile line, which runs from the Paris Substation in Paris to the Albers Substation in Kenosha, will enhance electric reliability for southeastern Wisconsin.

Seventy-seven aging, wood transmission poles were replaced with new wood and steel structures and the old wires were replaced with new wires. No new right-of-way was needed for the project, and the new poles were placed within a few feet of the existing poles.

“This project will help ensure safe and reliable transmission operations in the future and adequate clearances between the wires and the ground,” said Mary Carpenter, senior local relations representative for ATC.

ATC received approval for the project from the Public Service Commission of Wisconsin in spring 2014, and construction began in fall 2014. The project was completed on time and is projected to come in under the PSC-approved budget of $11.5 million.

A map of the project and additional information can be found at atc-projects.com.

]]>
http://www.atcllc.com/whats-current/paris-albers-transmission-line-placed-into-service/feed/ 0
Celebrating National Engineers Week http://www.atcllc.com/blog/celebrating-national-engineers-week/ http://www.atcllc.com/blog/celebrating-national-engineers-week/#comments Tue, 24 Feb 2015 17:15:57 +0000 http://www.atcllc.com/?p=5138 Brian and John enjoy collaborating on a project.

Brian and John, design engineering, enjoy collaborating on a project.

It’s National Engineers Week and we’re proud to employ a pretty exceptional amount of engineers per capita at American Transmission Co.

If you’re walking the floors of our offices, about one in every four employees is an electrical, civil, industrial or other type of engineer. And while the rest of the world may think of gym class when you say PE, we instantly envision the Professional Engineer designation.

Our engineers help manage construction projects, operate the grid, plan for future transmission upgrades and more.

If you’re an engineer looking for a Great Place to Work®, join our talent network and check out some of our current openings:

]]>
http://www.atcllc.com/blog/celebrating-national-engineers-week/feed/ 0
New electrical facilities approved for Brillion Iron Works http://www.atcllc.com/whats-current/new-electrical-facilities-approved-for-brillion-iron-works/ http://www.atcllc.com/whats-current/new-electrical-facilities-approved-for-brillion-iron-works/#comments Fri, 13 Feb 2015 19:25:42 +0000 http://www.atcllc.com/?p=5130 American Transmission Co. to build new substation, short power lines for local reliability

DE PERE, Wis. – The Public Service Commission of Wisconsin has approved plans for $14 million in electrical transmission improvements in the area of Brillion Iron Works to support the local distribution system owned and operated by Wisconsin Public Service Corp.

The project will involve building a new substation on BIW property, a new 0.3-mile 69,000 volt line to connect the foundry to the new substation, along with an extension of a double-circuit 138,000/69,000 volt line to the new substation. Additional work also will be required at the Glenview Substation in Brillion.

The ATC project is part of an asset renewal process being undertaken by WPS to address load growth at BIW. Currently, BIW is served by a single electrical line; the new project will supply the foundry with additional lines, greatly improving reliability for this large regional employer.

Construction on the ATC facilities will begin in summer 2015 and the project is expected to be placed into service in August 2016.

]]>
http://www.atcllc.com/whats-current/new-electrical-facilities-approved-for-brillion-iron-works/feed/ 0
ATC receives Innovations in Urban Forestry Award http://www.atcllc.com/whats-current/atc-receives-innovations-in-urban-forestry-award/ http://www.atcllc.com/whats-current/atc-receives-innovations-in-urban-forestry-award/#comments Thu, 05 Feb 2015 19:31:18 +0000 http://www.atcllc.com/?p=5121 Community Planting Program helps beautify communities

PEWAUKEE, Wis. – The Wisconsin Urban Forestry Council, advisory council to the Department of Natural Resources, has selected American Transmission Co. to receive its annual Innovations in Urban Forestry Award. The award was presented to ATC for its Grow Smart Community Planting Program, which over the past two years has awarded $130,000 to more than 90 communities for planting projects.

“Our Community Planting Program connects us with the communities that we serve,” said Mark Davis, ATC vice president of asset management. “It helps to beautify the communities within our service area and supports our obligation to ensure the reliability of the electric transmission system by encouraging plantings that are compatible with the safe operation of the electric transmission system.”

Now in its second year, ATC’s Community Planting Program provides eligible municipalities and counties in its service area with funding for planting projects on public property. To qualify, applicant communities must commit to complying with ATC’s maintenance standards for all current and future planting plans and urban forestry activities near high-voltage electric transmission lines.

The Community Planting Program is part of ATC’s Grow Smart initiative – a program that promotes planting a safe distance from transmission lines to help ensure public safety and electric system reliability. The Community Planting Program reinforces this initiative by encouraging the planting of tall-growing trees and other vegetation outside transmission line rights-of-way.

About the Wisconsin Urban Forestry Council
The Wisconsin Urban Forestry Council is an appointed group of urban forestry experts who advise the Wisconsin Department of Natural Resources on the best ways to preserve, protect, expand and improve Wisconsin’s urban and community forest resources. More information about the council can be found here.

]]>
http://www.atcllc.com/whats-current/atc-receives-innovations-in-urban-forestry-award/feed/ 0
ATC named one of the nation’s top workplaces http://www.atcllc.com/whats-current/atc-named-one-of-the-nations-top-workplaces/ http://www.atcllc.com/whats-current/atc-named-one-of-the-nations-top-workplaces/#comments Thu, 22 Jan 2015 14:29:52 +0000 http://www.atcllc.com/?p=5105 Great Place to Work® and FORTUNE magazine-published list ranks top 15 manufacturing & production workplaces in the country

PEWAUKEE, WIS. — American Transmission Co. ranks as one of the nation’s top workplaces, having been chosen as one of the People’s Picks: 15 Great Workplaces in Manufacturing & Production by Great Place to Work®’s Great Rated!™. This honor comes after ATC last fall was named one of the top 25 workplaces in the United States on FORTUNE magazine’s 2014 Best Small & Medium Workplaces list.

The 15 Great Workplaces in Manufacturing & Production is a “best of the best” ranking. Of the 600 companies surveyed by Great Place to Work®, 44 were in the Manufacturing & Production category. ATC and the other 14 winning companies in this category were selected based on the evaluations of nearly 34,000 employees from companies across the country who were surveyed to get their assessment of their workplaces and employers. Employers were evaluated through Great Place to Work®’s Trust Index© survey, and the companies with the highest levels of trust, camaraderie and pride among their employees are the ones that rank on this list.

“We are honored to again be named among the best places to work in the country,” said ATC President and CEO John Procario. “We strive to be the employer of choice for talented and dedicated people.”

The full category in which ATC participated was the Manufacturing & Production/Energy Distribution, as it was the established category that came closest to encompassing ATC’s unique business model as a transmission-only utility. Pewaukee, Wis.-based ATC, with 650 employees, was formed in 2001 as the first multi-state, transmission-only utility in the country.

FORTUNE Magazine published the complete list of People’s Picks: 15 Great Workplaces in Manufacturing & Production. Click here for the entire list and here for ATC’s company profile.

]]>
http://www.atcllc.com/whats-current/atc-named-one-of-the-nations-top-workplaces/feed/ 0
Final route options for power line project to be presented at ATC public open house http://www.atcllc.com/whats-current/final-route-options-for-power-line-project-to-be-presented-at-atc-public-open-house/ http://www.atcllc.com/whats-current/final-route-options-for-power-line-project-to-be-presented-at-atc-public-open-house/#comments Tue, 13 Jan 2015 16:06:14 +0000 http://www.atcllc.com/?p=5103 Proposed project will be submitted in April to state regulators for review

PEWAUKEE, Wis. – American Transmission Co. is hosting a final public open house on Tuesday, Jan. 27 for the proposed Spring Valley-North Lake Geneva Electric Reliability Project. The open house gives area residents and other stakeholders the opportunity to review the proposed substation location and preferred and alternate routes for the 25-mile, 138-kilovolt transmission line from southern Walworth County to western Kenosha County, Wis. ATC plans to submit its application to the Public Service Commission of Wisconsin in April 2015 for permission to build the line and substation. If approved, the PSC will select one route to be built.

The public is invited to attend the open house on Tuesday, Jan. 27, any time between 4 and 7:30 p.m. at the Wheatland Center Elementary School Cafeteria, located at 6606 368th Ave. in Burlington.

“The two proposed routes represent the options the project team members believe best meet state routing and siting criteria based on impacts, costs, constructability, operation and maintenance,” said Mary Carpenter, senior local relations representative.

The electric transmission system in the area is vulnerable to low voltages and power outages and can no longer adequately support the lower-voltage distribution system. ATC studies indicate that the project would strengthen the electric transmission system to meet the growing use of electricity. This estimated $72 million to $92 million project would provide system redundancy and allow for maintenance outages when repairs are needed.

The Spring Valley-North Lake Geneva Electric Reliability Project was introduced to the public in early 2013. Since then, the ATC project team has been gathering field data and public input and evaluating community and environmental impacts to determine the most suitable route options for a proposed transmission line and substation. Preliminary transmission line corridors and routes were presented to the public during open houses in January 2013, and again in March 2014. If state regulators approve the project, construction would begin in 2017 to meet an in-service date of 2019.

Note to editors: A map showing the two proposed route options can be found here. Additional information about the project is available at www.atc-projects.com.

]]>
http://www.atcllc.com/whats-current/final-route-options-for-power-line-project-to-be-presented-at-atc-public-open-house/feed/ 0
ATC awards $55,000 to communities for vegetation plantings http://www.atcllc.com/whats-current/atc-awards-55000-to-communities-for-vegetation-plantings/ http://www.atcllc.com/whats-current/atc-awards-55000-to-communities-for-vegetation-plantings/#comments Mon, 05 Jan 2015 21:04:12 +0000 http://www.atcllc.com/?p=5101 Program continues to support beautification efforts, electric reliability

PEWAUKEE, Wis. – American Transmission Co. has awarded $55,000 to 33 communities in its service area to plant trees and other vegetation. The Community Planting Program, now in its second year, supports the reliability of the electric transmission system and helps to beautify communities by promoting plantings located outside of transmission line rights-of-way.

“It’s ATC’s responsibility to keep trees and brush out of the transmission line rights-of-way for public safety and electric system reliability,” said ATC Environmental and Local Relations Manager Greg Levesque. “Collaborating with communities in our service territory to educate them about vegetation growth in the rights-of-way helps ATC maintain the safety and electric reliability of the grid.”

Municipalities and counties received funding ranging from $500 to $4,000 for planting projects on public property where ATC facilities exist. To qualify, community recipients committed to complying with ATC’s maintenance standards for all current and future planting plans and urban forestry activities near high-voltage electric transmission lines.

The Community Planting Program is part of ATC’s Grow Smart initiative – a program that promotes planting native, low-growing vegetation near transmission line rights-of-way. Trees and other vegetation purchased by communities through the Community Planting Program reinforces this initiative by encouraging the planting of tall-growing trees and other vegetation outside the transmission line rights-of-way.

The 2014 Community Planting Program funding recipients include:

Algoma, Wis. Lisbon, Wis. Rib Mountain, Wis.
Amherst, Wis. Manitowoc, Wis. Rhinelander, Wis.
Bayside, Wis. Menasha, Wis. Spencer, Wis.
Bellevue, Wis. Mequon, Wis. Stevens Point, Wis.
Bristol, Wis. Merrill, Wis. Waterford, Wis.
Brooklyn, Wis. Oakdale, Wis. Waukesha, Wis.
Cambridge, Wis. Oconto, Wis. Waupaca, Wis.
Fond du Lac, Wis. Ozaukee County, Wis. Wescott, Wis.
Fort Atkinson, Wis. Pittsville, Wis. Wilson, Wis.
Gilman, Wis. Prairie du Chien, Wis. Winnebago County, Wis.
Kenosha County, Wis. Princeton, Wis. Wisconsin Rapids, Wis.
]]>
http://www.atcllc.com/whats-current/atc-awards-55000-to-communities-for-vegetation-plantings/feed/ 0
The power of giving http://www.atcllc.com/blog/the-power-of-giving/ http://www.atcllc.com/blog/the-power-of-giving/#comments Tue, 23 Dec 2014 16:30:00 +0000 http://www.atcllc.com/uncategorized/the-power-of-giving/ It’s no secret that our employees love to give. As a company and individuals we support local organizations with our time, funds and in-kind donations. And while the first thing you think of when an electric utility comes to mind may not be fun, we like to weave it in whenever we can. Here’s how some employees are having a good time while giving back.

Banana phones and white elephants

Our real estate team raised a whopping $730 with its second annual White Elephant Auction at their holiday lunch. Manager of Real Estate Sarah Justus started the tradition last year; buying a number of wacky and wild items and encouraging her team to bid on them white elephant-style for charity.

“The generosity of my colleagues is amazing. It was very fun and personally gratifying to support such an inspirational organization,” said Justus.

This year’s beneficiary was Make-A-Wish®. Which item garnered the highest bid this time around? A banana phone secured by Real Estate Manager David Hollenberger for a generous donation.

Betting with baked goods

Three Madison, Wis., employees made the annual Second Harvest Foodbank Share Your Holidays food and fund drive a little more interesting by making a friendly baked goods wager. Each team captain bet their team would collect the most meals, with the winning team receiving baked goods from the second and third place team leaders. More than 1,850 meals were raised during the campaign.

]]>
http://www.atcllc.com/blog/the-power-of-giving/feed/ 0
ATC files regulatory application for Branch River Substation http://www.atcllc.com/whats-current/atc-files-regulatory-application-for-branch-river-substation/ http://www.atcllc.com/whats-current/atc-files-regulatory-application-for-branch-river-substation/#comments Wed, 10 Dec 2014 17:41:34 +0000 http://www.atcllc.com/?p=4787 Transmission facilities in Manitowoc County will improve local electric reliability

PEWAUKEE, Wis. – American Transmission Co. is requesting approval from the Public Service Commission of Wisconsin to build a new substation and connecting transmission lines in the Manitowoc County Town of Franklin. The facilities will support the reliable operation of the high-voltage transmission system that provides electric service to eastern Wisconsin.

If approved, construction would begin in August 2016 and the project would be placed into service in late 2018. The estimated cost of the project ranges from $41 million to $46 million, depending on routing and site selection.

The application and other documents to be used in the regulatory review can be found at the PSC’s website, http://psc.wi.gov. Enter docket number 137-CE-176.

]]>
http://www.atcllc.com/whats-current/atc-files-regulatory-application-for-branch-river-substation/feed/ 0
ATC project recycling efforts really pay off http://www.atcllc.com/blog/atc-project-recycling-efforts-really-pay-off/ http://www.atcllc.com/blog/atc-project-recycling-efforts-really-pay-off/#comments Mon, 24 Nov 2014 22:32:00 +0000 http://www.atcllc.com/uncategorized/atc-project-recycling-efforts-really-pay-off/ Metal from this disassembled, 60-year-old transmission structure and glass from its insulators will be recycled.

Environmental stewardship is a core value at American Transmission Co. that saves valuable resources and helps protect the environment. Last year, ATC and its contractors achieved an incredible rate of re-using or recycling 99 percent of non-hazardous construction waste. This included more than 4,864 tons of various metals, glass, wood, concrete and cardboard. This year to date, ATC and its contractors have recycled more than 3,476 tons of material and collected $667,363 through construction project recycling efforts.

 Wood decking used during construction, as seen in the above photo of the Milwaukee Zoo Interchange Project, is an example of ATC project material that is re-used or recycled.

Learn more about ATC’s environmental commitment.


]]>
http://www.atcllc.com/blog/atc-project-recycling-efforts-really-pay-off/feed/ 0
Preparations underway for ATC power line construction http://www.atcllc.com/whats-current/preparations-underway-for-atc-power-line-construction/ http://www.atcllc.com/whats-current/preparations-underway-for-atc-power-line-construction/#comments Mon, 17 Nov 2014 17:35:59 +0000 http://www.atcllc.com/?p=4762 Holmes-Old Mead Road project set for Menominee, Delta counties

DE PERE, Wis. – Real estate and tree clearing activities are underway along the 58-mile corridor of American Transmission Co.’s 138,000-volt transmission line project in Menominee and Delta counties in Michigan.

“About 60 percent of the easements we need for the new transmission line have been acquired,” said Brett French, senior external relations manager for ATC. “A major milestone was achieved when we acquired the easement rights of about 20 miles of the corridor from the state of Michigan. This portion of the new line will be built in an abandoned railroad corridor and will be transformed into a recreational trail after the power line is built.”

Surveying, staking, and brush and tree clearing are underway in the corridor where ATC holds easement rights in preparation for the start of construction in January 2015. Contract crews from AECOM, Asplundh Tree Expert Co. and MJ Electric are performing the work. Activities in the corridor will be limited during the gun deer hunting season through Nov. 30.

The new line is needed to improve electric reliability in the area. The project was first announced as part of ATC’s Bay Lake Project in spring 2012. The new line will run between the Holmes Substation along the Menominee River and the Old Mead Road Substation near the New Page mill in Escanaba. The project was approved by the Michigan Public Service Commission in January 2014.

]]>
http://www.atcllc.com/whats-current/preparations-underway-for-atc-power-line-construction/feed/ 0
ATC wraps up electric work in Milwaukee’s Zoo Interchange http://www.atcllc.com/whats-current/atc-wraps-up-electric-work-in-milwaukees-zoo-interchange/ http://www.atcllc.com/whats-current/atc-wraps-up-electric-work-in-milwaukees-zoo-interchange/#comments Thu, 13 Nov 2014 17:49:22 +0000 http://www.atcllc.com/?p=4751 Transmission line and substation work completed two months ahead of schedule

PEWAUKEE, Wis. – American Transmission Co. has completed its work in the Zoo Interchange to relocate and erect new electric transmission infrastructure to accommodate the Wisconsin Department of Transportation’s interchange expansion plans.

ATC began the transmission line portion of the project in June 2013 to relocate seven overhead 138-kilovolt transmission lines and erect 59 single pole structures to replace 58 lattice towers. Just over 11 miles of new wire were strung from south of Greenfield Avenue along the east side of USH 45/I-894 in West Allis, north to the Zoo Interchange and then west along I-94 to ATC’s Bluemound Substation.

The project also involved modifications at two nearby substations and expansion of the 96th Street Substation, which supports both the new lines for the Zoo Interchange project and ATC’s Western Milwaukee County Electric Reliability Project, which is slated to be complete in spring 2015.

“Residents and commuters were able to watch the transformation over the past year and a half while we removed the old structures, installed the new poles and strung wire across six lanes of traffic – all while the interchange was kept open to motorists,” said Barbara Mikolajczyk, ATC major project manager. “We were able to complete our work more than two months ahead of schedule because there was great communication and collaboration among the DOT and the multiple utilities involved.”

ATC’s restoration work may continue through spring 2015 – removing the former lattice towers and construction mats, and completing final grading of the area.

“Because ATC completed its portion of the project ahead of schedule, that helps our scheduling with other contractors this winter and next spring,” said DOT Construction Project Manager Mike Burns.

The cost of ATC’s Zoo Interchange project work totaled $50 million.

]]>
http://www.atcllc.com/whats-current/atc-wraps-up-electric-work-in-milwaukees-zoo-interchange/feed/ 0
ATC wraps up electric work in Zoo Interchange http://www.atcllc.com/blog/atc-wraps-up-electric-work-in-zoo-interchange/ http://www.atcllc.com/blog/atc-wraps-up-electric-work-in-zoo-interchange/#comments Thu, 13 Nov 2014 17:44:00 +0000 http://www.atcllc.com/uncategorized/atc-wraps-up-electric-work-in-zoo-interchange/
American Transmission Co. has just completed its work in the Milwaukee Zoo Interchange to relocate and erect new electric transmission infrastructure to accommodate the Wisconsin Department of Transportation’s interchange expansion plans.

ATC began the transmission line portion of the project in June 2013 to relocate seven overhead 138-kilovolt transmission lines and erect 59 single pole structures to replace 58 lattice towers. 
“Residents and commuters were able to watch the transformation over the past year and a half while we removed the old structures, installed the new poles and strung wire across six lanes of traffic – all while the interchange was kept open to motorists,” said Barbara Mikolajczyk, ATC major project manager. “We were able to complete our work more than two months ahead of schedule because there was great communication and collaboration among the DOT and the multiple utilities involved.”

“Because ATC completed its portion of the project ahead of schedule, that helps our scheduling with other contractors this winter and next spring,” said DOT Construction Project Manager Mike Burns.

Project highlights include:

  • Line energized and project complete: November 2014 – two-and-half months ahead of schedule
  • Line length: approximately 11 miles 
  • Voltage: 138,000 volts
  • 58 lattice structures removed (circa 1954); equals 1.24 million pounds of steel removed
  • 59 new single-pole structures erected; equals 2.3 million pounds of steel installed
  • 40.5 miles of wire removed and new wires installed
  • Transmission pole height: 115 to 180 feet; new poles are 50-60 feet taller than the lattice structures
  • Tallest transmission pole: 180 feet with five sections, nine feet in diameter at the base and weight of 130,000 pounds
  • Longest span between two transmission poles: 1,000 feet
  • Project cost: approximately $50 million
]]>
http://www.atcllc.com/blog/atc-wraps-up-electric-work-in-zoo-interchange/feed/ 0
ATC employees volunteer during United Way Days of Caring http://www.atcllc.com/blog/atc-employees-volunteer-during-united-way-days-of-caring/ http://www.atcllc.com/blog/atc-employees-volunteer-during-united-way-days-of-caring/#comments Fri, 24 Oct 2014 20:36:00 +0000 http://www.atcllc.com/uncategorized/atc-employees-volunteer-during-united-way-days-of-caring/
During American Transmission Co.’s United Way Days of Caring this year, more than 100 employees volunteered for projects at various agencies. In the span of a few short days, employees helped United Way organizations accomplish a great deal, while at the same time learning how much help is needed in the community each day.

Day of Caring volunteers were busy at Feeding America

ATC’s Day of Caring volunteers from the Pewaukee office were very busy sorting and labeling food for the hungry at Feeding America Eastern Wisconsin in Milwaukee.
Feeding America Eastern Wisconsin is a food bank that distributes more than 22 million pounds of food a year to 1,000 pantries, meal programs and other nonprofit agencies that serve 330,000 people in eastern Wisconsin. The Milwaukee distribution center provides food to nearly 800 nonprofit programs in nine counties. Representatives at the center shared that they could have a group like ATC’s help out every day.
 
Employees help Interfaith clean up gardens before winter
You would have thought that an army went in to clean up the gardens at Interfaith’s Washington Park Senior Center in Milwaukee, Wis. However, it was a powerful group of 10 ATC employees who pulled weeds, trimmed bushes, transplanted and cut down perennials to make the gardens look beautiful.
Since 1975, Interfaith has established many programs focused on quality services, social opportunities and valuable resources to enhance the welfare of older adults and family caregivers who support them. The community center offers a warm place to gather for older adults to enjoy the company of friends, take exercise classes, use computers and enjoy many other group activities along with the wonderful gardens ATC’s volunteers helped spruce up.
 

Volunteers at LifeStriders help with stables and horse riding lessons

It was rainy, but LifeStriders Therapeutic Riding Center, located on a farm in Waukesha County, Wis., had plenty of indoor work for our volunteers to do. ATC employees helped with cleanup in the horse stables, organized equipment, created teaching tools for use during riding lessons and later assisted LifeStriders staff and other volunteers with riding lessons.

LifeStriders provides fun and interactive sessions to help children and adults with special needs experience the physical and mental benefits achieved through working with horses. They currently have 104 students enrolled in the program, which requires more than 300 volunteer hours each week, so the help of all volunteers is greatly appreciated.


Area was full of leaves at Bay Beach Wildlife Sanctuary

ATC’s employees did a lot of raking during a fall clean up at Bay Beach Wildlife Sanctuary in Green Bay, Wis. Everyone enjoyed the opportunity to give back to the community while they worked in the fresh air.

The Bay Beach Wildlife Sanctuary is a beautiful 700 acre urban wildlife refuge featuring live animal exhibits, educational displays, miles of hiking/skiing trails and various wildlife viewing opportunities. It is home to the second largest wildlife rehabilitation program in Wisconsin, caring for more than 4,500 orphaned and injured animals annually.

 
Employees help build a brighter future for a Waukesha family 
Two groups of employees helped with siding, building a porch and constructing shelving for a Habitat for Humanity home in Waukesha, Wis.
Through volunteer labor and tax-deductible donations of money, land and materials, Habitat for Humanity of Waukesha County builds or rehabilitates houses in partnership with families who need an affordable home.
Group works through icy conditions to sort food
Working in a cold room, ATC volunteers from Madison and Cottage Grove, Wis., sorted 28,500 pounds of frozen food at the Second Harvest Foodbank of Southern Wisconsin.
In one year, Second Harvest and its partners provide more than 12 million meals to those facing hunger.


 Many cats will have a cozy place to sleep thanks to ATC volunteers
 

Volunteers at the Dane County Humane Society had fun while they made more than 45 cat beds. The group received a tour of the facility and donated needed supplies to the organization.
 
DCHS is an open admission shelter that accepts animals that need assistance no matter their age, health status or temperament. DCHS places all healthy or treatable cats and dogs in new homes.
 
ATC employees had a great time during the Days of Caring for the United Way and truly enjoyed giving back to the communities where they live and work.

Watch a video to learn why ATC employees volunteered for the United Way.

]]>
http://www.atcllc.com/blog/atc-employees-volunteer-during-united-way-days-of-caring/feed/ 0
ATC Transmission System Assessment describes changing landscape http://www.atcllc.com/whats-current/atc-transmission-system-assessment-describes-changing-landscape/ http://www.atcllc.com/whats-current/atc-transmission-system-assessment-describes-changing-landscape/#comments Wed, 08 Oct 2014 18:33:58 +0000 http://www.atcllc.com/?p=4697 Plans address generation changes, reliability requirements, industry dynamics

PEWAUKEE, Wis. – American Transmission Co.’s 2014 10-Year Transmission System Assessment is now available and describes the need for continued investment to address not only reliability needs, but also to respond to an evolving regional energy market and changes in public policy concerning air quality rules and renewable energy standards.

“The energy landscape in which we operate today looks vastly different than it did when we began operations in 2001,” said Ron Snead, vice president of system planning. “The grid is being asked to perform in ways it was not originally intended. We continue to work with our interconnected customers to meet their reliability needs and to share information about how changes in their operations impact our system.”

The planning analysis calls for $3.3 billion to $3.9 billion in infrastructure investment, including $1.4 billion in specific network projects, $1.2 billion in maintenance, $500 million in regional Multi-Value Projects, and $200 million to $800 million in other capital projects.

“Transmission remains a good value for electricity consumers,” Snead said, noting that transmission costs within the ATC service territory remain about 8 to 9 percent of a retail customer’s electric bill.

To read the full report, go to www.atc10yearplan.com.

 

]]>
http://www.atcllc.com/whats-current/atc-transmission-system-assessment-describes-changing-landscape/feed/ 0
ATC completes two grid projects in eastern Upper Peninsula http://www.atcllc.com/whats-current/atc-completes-two-grid-projects-in-eastern-upper-peninsula/ http://www.atcllc.com/whats-current/atc-completes-two-grid-projects-in-eastern-upper-peninsula/#comments Wed, 08 Oct 2014 15:15:02 +0000 http://www.atcllc.com/?p=4693 High-voltage direct-current device, rebuilt lines improve reliability, operations

DE PERE, Wis. – American Transmission Co. has improved the reliability of the electrical grid in the Upper Peninsula with the completion of two projects in the St. Ignace, Michigan, area.

A new high voltage, direct-current flow control device and associated substation also were placed into commercial operation in late summer. The innovative device allows operators to better manage the flow of power into and out of the Upper Peninsula, strengthening local-area electric reliability. The project was built by ABB, an international power and technology group. The facilities are located in Moran Township, just north of U.S. Highway 2 west of St. Ignace. The project also was completed slightly under budget at a cost of $125 million.

“The HVDC device helped us avoid two near-certain outages since it began operation,” said Paul Roehr, director of operations for ATC. Previously, the transmission facilities in the eastern U.P. were tied to Lower Michigan, and the western U.P. facilities to northern Wisconsin. The U.P. facilities were separated at a substation near Engadine because the system could not support the flow of power across the width of the peninsula. The HVDC device now provides the support to connect the two regions.

“An unplanned outage on transmission facilities in northern Wisconsin almost surely would have caused customers in the U.P. to lose service, but the HVDC device provided system support, maintaining reliability by allowing a continuous flow of power,” Roehr said. “In one of those instances, some customers in northern Wisconsin also would have been affected.”

Two 69,000-volt transmission lines that were built in the 1930s between St. Ignace and Rudyard also have been upgraded in a construction project that began in late 2012. The new lines are built to 138,000-volt standards, but continue to be operated at 69-kV. They operate more efficiently, reducing energy losses on the system and lowering operating and maintenance costs. They also provide more flexibility in routing power in the area. The project was completed slightly under budget at a cost of $43 million.

 

]]>
http://www.atcllc.com/whats-current/atc-completes-two-grid-projects-in-eastern-upper-peninsula/feed/ 0
ATC to discuss proposed transmission line in Fond du Lac County http://www.atcllc.com/whats-current/atc-to-discuss-proposed-transmission-line-in-fond-du-lac-county/ http://www.atcllc.com/whats-current/atc-to-discuss-proposed-transmission-line-in-fond-du-lac-county/#comments Tue, 07 Oct 2014 16:11:49 +0000 http://www.atcllc.com/?p=4682 Final open house regarding the project will be Oct. 21 at the Eden Community Center

PEWAUKEE, Wis. – An informational open house will provide an opportunity for area landowners and members of the public to comment on American Transmission Co.’s proposal for a new 138,000-volt transmission line to connect to a new We Energies substation. ATC and We Energies held the first round of open houses in April 2014, after announcing the Creekview Interconnection Project to the public.

ATC staff, along with representatives from We Energies, will be at the Eden Community Center, located at 104 Pine St. in Eden, Wis., between 4 p.m. and 7 p.m. on Tuesday, Oct. 21, to discuss the project plans – including proposed route options for the transmission line and a substation location.

The proposed We Energies substation, located approximately one mile southeast of the Village of Eden along County Highway F, is needed to support the low-voltage electric distribution system and improve overall electric system reliability in the region. To connect this new substation to the regional transmission system, ATC would build a transmission line either to the west, which would be 6.5 miles in length, or to the north of the proposed substation site, which would be 9.3 miles in length.

ATC will file an application in early 2015 with the Public Service Commission of Wisconsin for permission to build the transmission line. If approved, the PSC will determine the route of the transmission line, and construction would begin in fall 2016. If the west route is approved, the in-service date is expected to be June 2017. If the north route is approved, the in-service date is expected to be June 2018.

Mary Carpenter, senior local relations representative for ATC, said, “Additional power is needed in the area to serve We Energies customers. With a total estimated cost of $23 million, this project will provide system redundancy and allow equipment and facilities to be taken out of service when repairs are needed.”

“We look to the public, particularly people who may be impacted, to participate in the process by providing comments and input,” said Carpenter. “This information helps us finalize the proposed routes in alignment with our routing and siting criteria – including impacts, costs, operation, maintenance and overall constructability.”

Note to editors: A map and additional information about the Creekview Interconnection Project is available at www.atc-projects.com.

###

 American Transmission Co. is a Wisconsin-based company that owns and operates the electric transmission system in portions of the Upper Midwest. Formed in 2001 as the nation’s first multi-state transmission-only utility, ATC has invested $3.2 billion to improve the adequacy and reliability of its infrastructure. ATC now is a $3.6 billion company with 9,530 miles of transmission lines and 530 substations. The company is a member of the MISO regional transmission organization, and provides nondiscriminatory service to all customers, supporting effective competition in energy markets without favoring any market participant. For more information, visit our website at www.atcllc.com.

]]>
http://www.atcllc.com/whats-current/atc-to-discuss-proposed-transmission-line-in-fond-du-lac-county/feed/ 0
ATC named on Great Place to Work® 2014 Best Small & Medium Workplaces List http://www.atcllc.com/whats-current/atc-named-on-great-place-to-work-2014-best-small-medium-workplaces-list/ http://www.atcllc.com/whats-current/atc-named-on-great-place-to-work-2014-best-small-medium-workplaces-list/#comments Thu, 18 Sep 2014 14:14:09 +0000 http://www.atcllc.com/?p=4656 FORTUNE magazine-published list names the best workplaces in the countryGPTW

PEWAUKEE, WIS. — American Transmission Co. was named by Great Place to Work® as one of the best small and medium workplaces in the United States on their annual 2014 Best Small & Medium Workplaces list, published today in FORTUNE magazine.

ATC competed against hundreds of companies across the country to receive this honor. This is the first time ATC has been named to the list, a recognition that comes on the heels of being named as one of the 2014 Milwaukee Journal Sentinel Top Workplaces in southeastern Wisconsin.

ATC participated in a rigorous selection process, which included an employee survey and an in-depth questionnaire about benefits programs and company practices. Great Place to Work® evaluated each application based on five dimensions of a great workplace: credibility, respect, fairness, pride and camaraderie.

As ATC strives to become the premier national energy delivery company, surveys such as this help highlight how practices in place at ATC are experienced by employees.

“Every day, we strive to be a company where engaged and productive employees enjoy working. The best way to measure how we are doing is to ask employees for feedback,” said ATC President and CEO John Procario. “We are honored to be named among the best places to work in the country, most importantly because it is our employees’ assessment that put us there.”

Divided into two categories, small (25-250 employees) and medium (251-999 employees), the Best Small & Medium Workplaces list has recognized companies with exceptional workplace cultures for the past 11 years. Great Place to Work® has found that employees believe they work for great organizations when they consistently trust the people with whom they work, have pride in what they do and enjoy their coworkers.

FORTUNE Magazine published the complete list of Best Small & Medium Workplaces. Click here for the entire list of medium workplaces and here for ATC’s company profile.

]]>
http://www.atcllc.com/whats-current/atc-named-on-great-place-to-work-2014-best-small-medium-workplaces-list/feed/ 0
ATC named one of the best medium-sized companies in the U.S. http://www.atcllc.com/blog/atc-named-one-of-the-best-medium-sized-companies-in-the-u-s/ http://www.atcllc.com/blog/atc-named-one-of-the-best-medium-sized-companies-in-the-u-s/#comments Thu, 18 Sep 2014 13:51:00 +0000 http://www.atcllc.com/uncategorized/atc-named-one-of-the-best-medium-sized-companies-in-the-u-s/
American Transmission Co. has been named one of the best medium workplaces on the 2014 Great
Place to Work® Best Small & Medium Workplaces list, published in FORTUNE magazine.
We competed against hundreds of companies across the country to receive this honor to rank in the 25 top medium-sized workplaces. This is the first time we have applied for and received this honor in our 13-year history.
 
The rigorous selection process included a written application, but the bulk of the weight of the application came from an employee survey about benefits programs and company practices. Seventy-one percent of ATC employees participated in the survey and their responses placed ATC in the 95 percentile for positive marks in the five dimensions of a great workplace: credibility, respect, fairness, pride and camaraderie.
“Every day, we strive to be a company where engaged and productive employees enjoy working. The best way to measure how we are doing is to ask employees for feedback,” said ATC President and CEO John Procario. “We are honored to be named among the best places to work in the country, most importantly because it is our employees’ assessment that put us there.”

Here are a few things that employees had to say which helped get ATC in the top 25:

  • “ATC puts a high emphasis on safety and is a steward of the environment.”
  • “I really enjoy the autonomy of my job. I am given all the resources, the time and the encouragement to function at a very high level. I feel I align well with ATC’s decisions and values, and that the company wants me to excel. Everybody is respected here.”
  • “The corporate culture is exceptionally supportive. People go out of their way to help one another. People are also polite and considerate. There are no organizational barriers to cooperation, so people easily work in informal teams across functional areas to get things done.”
  • “Ensuring electricity is reliable and affordable plays a huge part in our jobs and everyone in our service territory’s lives.”

Check out the 2014 Great Place to Work® Best Small & Medium Workplaces list, as published in FORTUNE magazine here.
Learn more about why ATC made the list in the Great Place to Work® Great Rated! Review.

Interested in working at ATC? Visit our careers page here.

ABOUT GREAT PLACE TO WORK: Great Place to Work® is the global authority on high-trust, high-performance workplace cultures. Through proprietary assessment tools, advisory services, and employer branding programs, including Best Companies lists and workplace reviews, Great Place to Work® provides the benchmarks, framework, and expertise needed to create, sustain, and recognize outstanding workplace cultures.
In the United States, Great Place to Work® produces the annual FORTUNE 100 Best Companies to Work For® list and the Great Place to Work® Best Small & Medium Workplaces list.Follow Great Place to Work® online at www.greatplacetowork.com and on Twitter at @GPTW_US. For information about global operations at Great Place to Work®, visit www.greatplacetowork.net.

ABOUT GREAT RATED!: The Great Place to Work® Model forms the basis of Great Rated!’s methodology, and is relied on internationally as the premiere assessment of employer culture. Great Rated!™ tells the story of workplace culture to job seekers from the viewpoint of a company’s own employees. Great Rated!™ reviews go well beyond a list of benefits or a handful of employee comments, to provide a comprehensive picture of what makes a company great. The site offers both ratings and reviews so that job seekers can easily compare the strengths and benefits across multiple organizations. Great Rated!™ works with a number of strategic partners including Simply Hired, and Digital First Media.

ABOUT FORTUNE: Fortune is a global business magazine that has been revered in its content and credibility since 1930. Published biweekly, every issue is completely saturated with profoundly deep and extensively detailed analyses of the entire field of business, including specific companies, tendencies, prominent people, and new ideas that are characterizing the modern world. Fortune magazine is particularly well-known for its exceptionally reliable annual rankings of companies. Examples of these highly researched features are the “Fortune 500,” which ranks the world’s companies by gross revenue, and the “Best Companies to Work For,” both of which have become industry benchmarks. This publication furthers understanding of the economy, provides implementable business strategy, and maximizes ability to make objective decisions. Fortune magazine is prized in its category of magazines and has been proven a reliable source of integral knowledge.



]]>
http://www.atcllc.com/blog/atc-named-one-of-the-best-medium-sized-companies-in-the-u-s/feed/ 0
ATC team takes on Briggs & Al’s Run & Walk for the kids http://www.atcllc.com/blog/atc-team-takes-on-briggs-als-run-walk-for-the-kids/ http://www.atcllc.com/blog/atc-team-takes-on-briggs-als-run-walk-for-the-kids/#comments Mon, 15 Sep 2014 21:49:00 +0000 http://www.atcllc.com/uncategorized/atc-team-takes-on-briggs-als-run-walk-for-the-kids/ ATC’s All for The Children team lined up for Briggs & Al’s Run & Walk for Children’s Hospital of Wisconsin on Saturday, Sept. 13, 2014, to help kids receive care and services they need to improve their lives. Employees and family members had fun and raised almost $3,000 in addition to ATC’s bib sponsorship.
  It was chilly as ATC’s team warmed up for the event.

  Family members sporting their team T-shirts.

There was something for everyone, including an 8K run and a 5-mile or 3-mile walk through downtown Milwaukee. Live performers pumped up the crowd with a Radio Disney sing-a-long at the starting line on the Marquette University campus. Various musicians, cheerleaders and local residents were there to encourage the runners and walkers along the way. Afterwards, participants enjoyed music from Mat Kearney and other activities on the Summerfest grounds.


  Walkers take a moment to huddle up and smile.
ATC is proud to support Children’s Hospital of Wisconsin and has been a sponsor of this event since 2011. The organization provides many services throughout Wisconsin, including health care, counseling, family resource centers and treatment foster care. Click here to see a map of communities in Wisconsin with CHW services. 

]]>
http://www.atcllc.com/blog/atc-team-takes-on-briggs-als-run-walk-for-the-kids/feed/ 0
ATC, ITC announce public open houses for Wisconsin portion of Cardinal-Hickory Creek Transmission Line Project http://www.atcllc.com/whats-current/atc-itc-announce-public-open-houses-for-wisconsin-portion-of-cardinal-hickory-creek-transmission-line-project/ http://www.atcllc.com/whats-current/atc-itc-announce-public-open-houses-for-wisconsin-portion-of-cardinal-hickory-creek-transmission-line-project/#comments Mon, 15 Sep 2014 12:51:53 +0000 http://www.atcllc.com/?p=4623 New transmission line from Iowa to Wisconsin will provide reliability, economic and public policy benefits

MADISON, WIS. ─ American Transmission Co. and ITC Midwest LLC will host open houses to introduce to the public their plans for a new electric transmission line that would connect Dane County, Wisconsin, and Dubuque County, Iowa.

The Cardinal-Hickory Creek Project, previously called Cardinal Bluffs, would connect ATC’s Cardinal Substation in the Town of Middleton, Wisconsin,, with ITC’s proposed Hickory Creek Substation in Dubuque County, Iowa. The Midcontinent Independent System Operator, Inc., the regional electric transmission organization, approved the need for the approximately 125-mile, 345,000-volt Cardinal-Hickory Creek project as part of a portfolio of 17 transmission line projects that were identified as Multi-Value Projects. These projects are expected to deliver multiple benefits to electric consumers across the Midwest region by improving electric system reliability, providing economic benefits to utilities and electric consumers, and expanding electric infrastructure to support public policy for greater use of renewable energy.

The open houses are the first step in a multi-year process required to seek regulatory approval for the line.

Dates and locations for open houses are listed below. Open houses are scheduled from 4 to 7 p.m. at all locations. Attendees are encouraged to come at any time to speak with subject matter experts and learn more about the project; there will be no formal presentation.

Monday, Oct. 6
Grant County Fairgrounds-UW Extension Youth & Agriculture Center
916 East Elm St., Lancaster

Tuesday, Oct. 7
Belmont Convention Center & Banquet Hall
102 West Mound View Ave., Belmont

Wednesday, Oct. 8
Dodger Bowl Banquet Hall
318 King St., Dodgeville

Thursday, Oct. 9
Marriott Madison West – Ballroom-Salon D
1313 John Q. Hammons Drive, Middleton

“A route for the new power line has not yet been determined.  We look forward to meeting with the public and talking about their involvement in the routing and Wisconsin regulatory processes,” said Jon Callaway, ATC senior local relations representative. “ATC and ITC are beginning outreach in Wisconsin well ahead of filing an application with the Public Service Commission of Wisconsin.”

“Landowners and local officials have an important role to play in this process,” said Angela Jordan, ITC area manager for local government and community affairs. “These open houses are the first step in a long process of communications and dialogue with local landowners, citizens and other stakeholders about this important project.”

The project will require state regulatory approvals from Wisconsin and Iowa agencies as well as federal approvals from the U.S. Fish and Wildlife Service and the Army Corps of Engineers. ATC and ITC anticipate filing an application for the Wisconsin portion of the project with the PSCW in 2016. If the project is approved, construction in Wisconsin is expected to start in 2019 to meet an in-service date of 2020.

The total project is estimated to cost approximately $450 million at this time, although detailed engineering design cannot be performed until a specific route is determined. Because this project is designated by MISO as a Multi-Value Project that provides benefits across the Midwest, its costs will be spread across the MISO 11-state footprint in the Midwest. For more information, including a study area map, visit www.cardinal-hickorycreek.com.

# # #

About ATC
American Transmission Co. is a Wisconsin-based company that owns and operates the electric transmission system in portions of the Upper Midwest. Formed in 2001 as the nation’s first multi-state transmission-only utility, ATC has invested $3.2 billion to improve the adequacy and reliability of its infrastructure. ATC now is a $3.6 billion company with more than 9,500 miles of transmission lines and 530 substations. The company is a member of the MISO regional transmission organization, and provides nondiscriminatory service to all customers, supporting effective competition in energy markets without favoring any market participant. For more information, visit our website at www.atcllc.com.

About ITC Midwest
ITC Midwest LLC is a wholly-owned subsidiary of ITC Holdings Corp., the nation’s largest independent electricity transmission company. Through its regulated subsidiaries, ITC owns and operates high-voltage transmission lines in seven states, serving a combined peak load exceeding 26,000 megawatts along 15,000 circuit miles of transmission line. ITC Midwest operates more than 6,600 circuit miles of transmission lines in Iowa, Minnesota, Illinois and Missouri, and holds utility status in Wisconsin. ITC Midwest maintains regional offices in Cedar Rapids, Dubuque, Iowa City and Perry, Iowa; and Albert Lea and Lakefield, Minnesota. ITC’s focus on transmission and grid development drives operational excellence and delivers superior value for customers, communities and other stakeholders. For more information, please visit www.itctransco.com.

]]>
http://www.atcllc.com/whats-current/atc-itc-announce-public-open-houses-for-wisconsin-portion-of-cardinal-hickory-creek-transmission-line-project/feed/ 0
Reconstruction to begin on Paris-Albers transmission line http://www.atcllc.com/whats-current/reconstruction-to-begin-on-paris-albers-transmission-line/ http://www.atcllc.com/whats-current/reconstruction-to-begin-on-paris-albers-transmission-line/#comments Thu, 04 Sep 2014 19:53:09 +0000 http://www.atcllc.com/?p=4610 PEWAUKEE, Wis. – American Transmission Co. this month will begin the reconstruction of approximately 12.5 miles of 138,000-volt transmission lines in Kenosha County. The Paris-Albers Rebuild Project runs from the Paris Substation, located in the towns of Paris and Somers, Wisconsin, to the Albers substation in the City of Kenosha, Wisconsin. The existing transmission line was originally built in 1947, and this rebuild will allow the system to meet current and future electricity loads.

The construction is expected to be complete in early 2015, with an estimated cost of $11.5 million. Landowners along the right-of-way have been informed of the project, and ATC is working with them to access the right-of-way through their property if necessary.

Additional details are available on the PSC’s website under Docket No. 137-CE-174. A map of the proposed project and additional information can be found at www.atc-projects.com.

]]>
http://www.atcllc.com/whats-current/reconstruction-to-begin-on-paris-albers-transmission-line/feed/ 0
A bird’s eye view of construction on the Zoo Interchange, Western Milwaukee County Electric Reliability projects http://www.atcllc.com/blog/a-birds-eye-view-of-construction-on-the-zoo-interchange-western-milwaukee-county-electric-reliability-projects/ http://www.atcllc.com/blog/a-birds-eye-view-of-construction-on-the-zoo-interchange-western-milwaukee-county-electric-reliability-projects/#comments Tue, 02 Sep 2014 18:36:00 +0000 http://www.atcllc.com/uncategorized/a-birds-eye-view-of-construction-on-the-zoo-interchange-western-milwaukee-county-electric-reliability-projects/ We’re continuing to make progress on the Zoo Interchange Project, a project to relocate seven overhead 138-kilovolt transmission lines to accommodate expansion and realignment of the interchange. Lattice structures are being replaced with 50 single pole structures, many of which have already been swapped out. The transmission lines west of the interchange were completed and placed into service in May.

Crews were hard at work in late August installing conductor (wires) on the transmission structures on the southern portion of the project. Construction on the lines south of the Zoo Interchange will continue through this fall and winter and will be placed into service this winter.
On the Western Milwaukee County Electric Reliability Project, crews are using wooden construction mats to protect the ground and wetlands from damage by heavy machinery as they work to install transmission foundations and structures along the portion of the line that runs along Underwood Creek Parkway.
Duct instillation work for the underground portion of the line should be completed in September. Foundation work and pole setting for the overhead portion of the project will continue this fall, with wire stringing occurring in late fall. The project is on track to be placed into service in spring 2015.

 

 

 

 
]]>
http://www.atcllc.com/blog/a-birds-eye-view-of-construction-on-the-zoo-interchange-western-milwaukee-county-electric-reliability-projects/feed/ 0
ATC receives approval to rebuild transmission line in Rock, Walworth counties http://www.atcllc.com/whats-current/atc-receives-approval-to-rebuild-transmission-line-in-rock-walworth-counties/ http://www.atcllc.com/whats-current/atc-receives-approval-to-rebuild-transmission-line-in-rock-walworth-counties/#comments Thu, 28 Aug 2014 17:12:42 +0000 http://www.atcllc.com/?p=4601 Aging 69,000-volt line needs upgrading

PEWAUKEE, Wis. – American Transmission Co. on Tuesday gained approval from the Public Service Commission of Wisconsin to rebuild a 20-mile, 69,000-volt transmission line in Rock and Walworth counties. The Colley Road-Brick Church Rebuild Project will run from the Colley Road Substation in Beloit to the Brick Church Substation in Walworth. The project also involves construction of the new Tiger Substation near Clinton.

“Much of the line is more than 60 years old and needs improvements to ensure electric reliability in the area,” said Jon Callaway, ATC senior local relations representative.

The project will involve stringing new wires and replacing aging wood transmission poles with new steel poles. The new substation will be constructed on approximately 10 acres of land owned by ATC near Clinton.

Construction is planned to begin during the second half of 2015 to meet an in-service date of spring 2018. The estimated cost of the project is $38.5 million.

Note to editors: Additional information including a map is available at atc-projects.com and on the PSC’s website (psc.wi.gov) under docket number 137-CE-171.

]]>
http://www.atcllc.com/whats-current/atc-receives-approval-to-rebuild-transmission-line-in-rock-walworth-counties/feed/ 0
Osprey have a view from the top on ATC nest platforms http://www.atcllc.com/blog/osprey-have-a-view-from-the-top-on-atc-nest-platforms/ http://www.atcllc.com/blog/osprey-have-a-view-from-the-top-on-atc-nest-platforms/#comments Thu, 07 Aug 2014 15:15:00 +0000 http://www.atcllc.com/uncategorized/osprey-have-a-view-from-the-top-on-atc-nest-platforms/
ATC is committed to environmental leadership in all aspects of our business. One of the ways we demonstrate this commitment is through our avian stewardship.

According to the Department of Natural Resources, about 87 percent of Wisconsin’s breeding osprey population nest on platforms. There are more than 100 nesting platforms located on or adjacent to transmission lines in ATC’s service area, and these platforms support successful breeding of this once declining species.

These platforms protect the birds, enhance electric reliability and promote continued recovery of the species. Learn more about how we protect our feathered friends.

We recently spotted two osprey families nesting along our Clear Lake-Woodmin line in northern Wisconsin.
An osprey gets comfy on a nesting platform near our Woodmin Substation.

There are more than 100 nesting platforms located on or near ATC facilities


Madison, Wis., employees and their families also have taken office mascots, toy osprey couple Ozzie and Harriet, out and about “Flat Stanley” style over the years. 

Riding along for Bike to Work Week.
Enjoying the lake breeze on Cana Island, Door County, Wis.

Tagging along for Pesto Fest at Vermont Valley Community Farm.







]]>
http://www.atcllc.com/blog/osprey-have-a-view-from-the-top-on-atc-nest-platforms/feed/ 0
STIHL Tour des Trees, Day 7 – Aug. 2: Port Washington to Milwaukee http://www.atcllc.com/blog/stihl-tour-des-trees-day-7-aug-2-port-washington-to-milwaukee/ http://www.atcllc.com/blog/stihl-tour-des-trees-day-7-aug-2-port-washington-to-milwaukee/#comments Mon, 04 Aug 2014 20:13:00 +0000 http://www.atcllc.com/uncategorized/stihl-tour-des-trees-day-7-aug-2-port-washington-to-milwaukee/
“Hey, it’s Ben Gura again – and I am so happy to say I am writing the final day’s blog while sitting comfortably on my couch at home! I made it safe and sound with only a couple of mechanical issues on the bike. My legs are sore but in a good way – and the rest of my body is happy to be off the bike. 

The last ride day, Saturday, was bittersweet. Everyone was excited to be finished and to ride into the closing ceremony, but also disappointed that we would have to leave all of these new friends we made. The 40 miles went way too fast. I spent the first 20 miles with the fast guys just to see what it was like to put the hammer down and it felt great! The last 20 was a slow processional with a lot of chatter. It presented a great opportunity to say thank you to all of those I had ridden with throughout the week.

At the very last mile, the Team Wisconsin riders moved to the front of the pack to lead the way to Mount Mary College. This is where all of our friends and family had gathered and where the international tree climbing championships were being held. As we turned into the college entrance, the entire road was filled with people cheering and clapping for us. It was a really nice moment to see how happy everyone was to see us. Among those cheering was my family…now that made me smile!!
After hugs and kisses from the family and a quick round of pictures we had the final presentation. The TREE Fund thanked the sponsors and identified the 10 ten individual fund raisers. Team Wisconsin was the top fund raising team which was our goal! The Tour des Trees raised over $500,000 for The TREE Fund this year. I didn’t hit my goal but I am so happy at how close I came. I want to take an opportunity to say a big THANK YOU to everyone who donated to The TREE Fund! It really means a lot to me and your support really does help the trees.
A highlight from this year’s Tour was witnessing the dedication of over 23 trees, and a record number of educational events featuring Professor Elwood Pricklethorn. As riders, we tend to focus on the miles and occasionally we forget about the trees. But every tree that the Tour dedicates is a benefit to the community, environment and ecosystem. Every tree will provide oxygen to a cyclist, a shady spot to rest and a break from the wind. The trees are the reason we ride!  
My favorite part of the Tour was the educational events for the kids. Tour rider Warren Hoselton – aka “Professor Elwood Pricklethorn” does an outstanding job engaging the children and helping them understand the importance of trees. I heard that the Tour entertained over 300 kids during this year’s events. That’s 300 kids who now have an appreciation for “planting the right tree in the right place,” understanding what trees give to the community and hopefully having a desire to do more with trees as they get older. Who knows… maybe one or two of those kids will be foresters when they grow up!
The final tree dedication was at the Mount Mary College grounds, following the presentations. This tree dedication was particularly special because my family was there and my daughter, Morgan, and son, Jake, got to see how silly a group of adults could be. What a great way to end the week! Thank you again to ATC for sponsoring the lunch and educational event in New London. The Tour des Trees really matches our corporate values and I hope that ATC will become a long-term sponsor of this great event.
And thanks to all of you for letting me share my experiences with you during the past week. I’m now fairly certain: this Tour will not be my last…”
]]>
http://www.atcllc.com/blog/stihl-tour-des-trees-day-7-aug-2-port-washington-to-milwaukee/feed/ 0
STIHL Tour des Trees, Days 5 & 6 – July 31 & Aug. 1: Green Bay to Sturgeon Bay to Port Washington http://www.atcllc.com/blog/stihl-tour-des-trees-days-5-6-july-31-aug-1-green-bay-to-sturgeon-bay-to-port-washington/ http://www.atcllc.com/blog/stihl-tour-des-trees-days-5-6-july-31-aug-1-green-bay-to-sturgeon-bay-to-port-washington/#comments Mon, 04 Aug 2014 01:02:00 +0000 http://www.atcllc.com/uncategorized/stihl-tour-des-trees-days-5-6-july-31-aug-1-green-bay-to-sturgeon-bay-to-port-washington/
“Hey everyone – it’s Ben Gura checking in again from the STIHL Tour des Trees. We wrapped up this amazing ride on Saturday (which I’ll have another update on), but I wanted to catch you up from the days prior. Talk about a great pedaling – lovely weather and scenic riding. 
 
Day five was a blast. It was a short 57 miles from Green Bay to Sturgeon Bay. The day started with a once-in-a-lifetime tree dedication. The City of Green Bay and Bartlett Tree Company had acquired a very special tree. What made this tree so special? Well, it actually derived from the only surviving tree from ground zero. While cleaning up the rubble at the World Trade Center in New York after 9/11, the workers found a pear tree that was still alive. It was the only tree that survived the attack. Only a few trees have been grown from the cuttings of the tree and it is very special for a city to receive it. The dedication in Green Bay took place at a park near the Fox River and the library. The City had commissioned a beautiful memorial for the people from Wisconsin who died in the 9/11 attacks. It really was something to see and will be a great place to visit. 
The day’s riding was uneventful – a few nice rolling hills and a view of Green Bay. We had an early stop in Brussels and then a stop at the home of a Tour rider’s friend, for a nice ice cold beer. Lunch was served at a park right of Green Bay just north of Sturgeon Bay. We got into the hotel so early my room wasn’t ready. But I took advantage of the time by doing some laundry. We only get two jerseys so we need to wash them every couple of days. Some people wash their clothes in the sink while others wear them in the shower to wash them. I’m a fan of the guest washing machine that the hotels have. I also had time for a soak in the hot tub, a trip to McDonald’s for a cheeseburger and ice cream cone, and some more carb loading. We had a tasty outdoor dinner and enjoyed a polka band while we relaxed a bit. The evening’s activities capped off a wonderful day.
Of course, after a short day you have to make up some miles and day six did not disappoint us on that; it was a short 120 miles to Port Washington. I knew this was going to be a long day so I made sure to be up early and ready to roll. A taco truck feed us breakfast burritos, which was a welcome change from our standard breakfast before we rolled out at 7 a.m. The day started with some long climbs out of Door County but as we made it to Lake Michigan things leveled out. We had a slight headwind but I had a good group of riders that I worked with for the whole day. When you get a group of cyclists together that are willing to share the work of the ride, they can cover miles quickly. Our group ranged from 5 to 10 riders throughout the day. We would each take a turns “pulling” the other cyclists for a few miles then drop back into the pace line. 
Sorry for getting my cycling nerd out but there are a few terms that you learn when pack riding. A pace line is a group of cyclists riding in a line. They ride about 3 inches to 3 feet behind the rider in front of them – and obviously, the closer the better. “Taking a turn” or “pulling” is when you are the lead cyclist in the group. The lead rider splits the wind for everyone else. This helps the other riders rest while the lead is pulling. A good “pull” will set a pace that is comfortable for the group and they stick to it without speeding up or slowing down. In our case it was 17 mph. After the leader pulls, they move to the left and fall to the back of the pace line. When you are not in the front you work about 30% less than the lead rider. It’s the best way to get a lot of miles done quickly.
Our day ended around 3 p.m., with 8 hours in the saddle, just before a severe rainstorm with hail hit the hotel! At dinner we had presentations from The TREE Fund, and the rider awards were handed out. After dinner I had to stop for a slice of pizza. For some reason I have been hungry all week…could be the 500 plus miles on a bike?
All for now, and I’ll catch you up on the finale soon!”
]]>
http://www.atcllc.com/blog/stihl-tour-des-trees-days-5-6-july-31-aug-1-green-bay-to-sturgeon-bay-to-port-washington/feed/ 0
STIHL Tour des Trees, Day 4 – July 30: Stevens Point to Green Bay http://www.atcllc.com/blog/stihl-tour-des-trees-day-4-july-30-stevens-point-to-green-bay/ http://www.atcllc.com/blog/stihl-tour-des-trees-day-4-july-30-stevens-point-to-green-bay/#comments Thu, 31 Jul 2014 14:50:00 +0000 http://www.atcllc.com/uncategorized/stihl-tour-des-trees-day-4-july-30-stevens-point-to-green-bay/

“Hey – it’s Ben Gura again from the Tour des Trees. Days like today are the ones I love! The weather was perfect and the roads were scenic and rolling. We started our day early and managed to have gelato by 9 a.m. I had 47 miles to lunch and was excited to see all of my peers in New London from ATC. During those miles, I reflected on why I signed up for the Tour a second time.
 
Simply put – it’s the impact that the Tour has on the communities it touches. Each of these towns opens their arms to the Tour when we ride through. It seems that community members love seeing all of the riders decked out in their matching kits – plus they’re happy to feed and hydrate us! The message that the Tour sends about the value and importance trees on the environment and community is always heard by the residents who attend the tree dedications and the educational presentations.
When we made it to lunch all of my peers had the ATC Grow Smart tent set up and were assembling the giveaway bags that the kids got to bring home. They received books about trees, purple coneflower seed packets, a kid’s activity guide and other goodies too. Melinda Myers was there to greet the kids, talk about Grow Smart and answer any gardening questions that the guests had. We had some other special guest as well including the mayor of New London.
There were about 50 kids present who got to hear “Professor Elwood Prickethorn” give his tree presentation. It was great to see the kids getting involved and learning about trees and planting “the right tree in the right place.” After the presentation, the kids dedicated a tree in a very special Tour des Trees way.

The dedication starts with a clap of the hands above your head. Then we
rub our hands together to make energy. Next the energy is transferred to the trees roots by pointing our hands at the roots, wiggling our fingers and saying “the roots, the roots are on fire.” Then it ends in a loving rendition of John Lennon’s “Give Peace a Chance” but instead the lyrics go: ‘All we are saying…is give treesa chance.’ Some of the kids get embarrassed about doing this but most think it’s really fun. It was great to see my ATC friends and the kids that get to hear the ATC and Tour des Trees message.

The day ended 53 miles later with a tree dedication to a special kid who’s life was impacted by a car crash, followed by a lovely dinner at Lambeau Field in Green Bay.
Now, just three days of riding remain and my legs are getting stronger. We’re heading to Sturgeon Bay on Thursday, but cross your fingers for a strong north wind on Friday as we had 120 miles to ride down to Port Washington.”

]]>
http://www.atcllc.com/blog/stihl-tour-des-trees-day-4-july-30-stevens-point-to-green-bay/feed/ 0
STIHL Tour des Trees, Day 3 – July 29: Ride recap / Wisconsin Dells to Stevens Point http://www.atcllc.com/blog/stihl-tour-des-trees-day-3-july-29-ride-recap-wisconsin-dells-to-stevens-point/ http://www.atcllc.com/blog/stihl-tour-des-trees-day-3-july-29-ride-recap-wisconsin-dells-to-stevens-point/#comments Wed, 30 Jul 2014 02:16:00 +0000 http://www.atcllc.com/uncategorized/stihl-tour-des-trees-day-3-july-29-ride-recap-wisconsin-dells-to-stevens-point/

“Greetings again, from Ben Gura at the Tour des Trees! Three days are in the books and it has been an amazing journey so far. Day one started with lots of excitement and energy as 80-plus cyclists gathered at German Fest (Summerfest fair grounds) for the official kickoff. A tree was dedicated and the riders used their energy to help the tree get a good start in a very fun ceremony. The opening banner was cut by a STIHL chainsaw and we were on our way to Madison. We took over the streets of Milwaukee with all of the riders were clad in matching jerseys and helmets representing the Tour des Trees – overall, an impressive sight. As the ride passed Oconomowoc it was clear that this was going to be a difficult day. There was a constant 25 mph headwind with gusts into the upper thirties. I’m a decent cyclist but this proved to be very difficult. There were times where I would be climbing hills and the wind would almost bring my bike to a standstill. Then when I would need to rest on the downhill portions, I had to pedal instead of coasting. It was the most difficult day I’ve had on the bicycle.
Day two had no wind but plenty of hills. We headed west from Madison to Blue Mound State Park and up the hill to dedicate another tree. On the climb up I broke a spoke and my rim constantly rubbed on my brake making the climb even more challenging. The great support group fixed it and I was able to continue the day. We finished a very long 106 miles at 6:30 p.m. that evening. The total footage climbed was over 6,000 feet which doesn’t seem like much until you do it on a bike.
Day three was a great recovery day; a short 86 miles from Wisconsin Dells to Stevens Point. After two very difficult days and over 16 hours on a bicycle your whole body aches, especially your seat…Even though I knew today would be easier it was very difficult to wake up and put on my cycling shorts, jersey, helmet, gloves and cycling shoes. My gloves were still wet from yesterday’s sweat which made them even more pleasant to put on. Overall, day three went well. There was a minor accident in a group in front of me that left a couple riders off their bikes for the rest of the day; fatigue from the previous two days and close riding to one another are to blame. I finished the day’s ride a little after 3 p.m. and I feel great.
Another cyclist told me that their fitness tracker said they burned over 6,000 calories on day two, but this seemed low to me. On a normal training ride I burn close to 1,000 calories in an hour! The Tour does a great job keeping everyone feed and hydrated. Each day starts with a great breakfast that it is typically high on protein and carbohydrates. Once the day’s ride has started we have a rest stop before and after lunch where we can get snacks and water. These stops are short and typically include shoving as much salty food and bananas as you can get in your face before you’re off riding. Along the way, the riders also track down some of their own favorite stops. For me it has been for ice cream – twice on day two and once on day three. Lunch is catered in and again, it’s high in protein and carbs, lots of chicken, potatoes, rice, and fish. 
Dinners typically are the best meal of the day and I always have an appetite. On day one we had a pasta bar ready for us at the hotel as soon as we arrived. This is perfect for a cyclist to help their bodies recover. After the pasta bar we had our official dinner at the UW Arboretum. Most of the cyclists go back for seconds or thirds on dinner just to help recover the calories they are burning. I am averaging two to four chicken breasts per meal.
Four more days and about 290 miles left. Stay tuned…”
]]>
http://www.atcllc.com/blog/stihl-tour-des-trees-day-3-july-29-ride-recap-wisconsin-dells-to-stevens-point/feed/ 0
STIHL Tour des Trees, Day 1 – July 27: Milwaukee to Madison http://www.atcllc.com/blog/stihl-tour-des-trees-day-1-july-27-milwaukee-to-madison/ http://www.atcllc.com/blog/stihl-tour-des-trees-day-1-july-27-milwaukee-to-madison/#comments Mon, 28 Jul 2014 13:51:00 +0000 http://www.atcllc.com/uncategorized/stihl-tour-des-trees-day-1-july-27-milwaukee-to-madison/ “Hi, I’m Ben Gura, vegetation management specialist at ATC. I’ve worked in utility vegetation management for over 15 years and have made a career of keeping trees out of utility rights-of-way to maintain safe and reliable electricity to help ‘keep the lights on.’ When I found out the STIHL Tour des Trees was returning to Milwaukee this summer I knew this would be a great opportunity for me to give something back to the trees.

The STIHL Tour des Trees is a week-long, 583-mile bicycle ride. The Tour is also America’s largest fundraiser for tree research, which benefits The TREE Fund. Since 1992, The TREE Fund has raised over $6.6 million dollars for tree research and educational programs. Some of the money raised also goes to grants that help sustain urban forests, which is part of my role at ATC. In Wisconsin, forests are under attack from a variety of pests including the Emerald Ash Borer. The TREE Fund provides grants that are helping protect Wisconsin ash trees and by identifying new varieties of ash trees that may be EAB resistant.

During the Tour, we will dedicate trees to communities, provide books about trees to local libraries, and present educational events to children about the importance and care of trees. The Tour spreads the word about how trees are an important part of the urban landscape and a necessary part of the ecosystem. The Tour benefits people, trees and the environment. Recognizing that these traits align with ATC’s Tree Line USA award and ATC’s environmental stewardship, ATC is sponsoring the 2014 STIHL Tour des Trees lunch stop in New London on July 30. This should be a great event that will include presentations from the Tour’s “Professor Elwood Pricklethorn” and nationally renowned horticulturist, author and radio/TV host, Melinda Myers.

Going all in on a seven-day 583-mile bike ride isn’t something that one takes lightly. Besides having to spend a lot of time on a bicycle training for the event, each rider is required to raise $3,500 for The TREE Fund. It’s a commitment that I’m happy to take on for the trees. Please help me reach my goal by donating below.

http://www.crowdrise.com/stdtteamwisconsin/fundraiser/bengura

The Tour’s first day from Milwaukee to Madison was tough because we had a 25 mph headwind and got caught in two downpours. Monday’s weather looks better though! Thanks for reading and be sure to check back in the coming days for more updates and photos as I pedal through Wisconsin – all for the benefit of trees.”

]]>
http://www.atcllc.com/blog/stihl-tour-des-trees-day-1-july-27-milwaukee-to-madison/feed/ 0
ATC to sponsor STIHL Tour des Trees stop in New London http://www.atcllc.com/news/american-transmission-co-to-sponsor-stihl-tour-des-trees-stop-in-new-london/ http://www.atcllc.com/news/american-transmission-co-to-sponsor-stihl-tour-des-trees-stop-in-new-london/#comments Fri, 25 Jul 2014 16:13:47 +0000 http://www.atcllc.com/?p=4567 Event will feature Melinda Myers, tree dedication, awareness program and giveaways for children

PEWAUKEE, Wis. – On Wednesday, July 30, some 100 bicyclists will pedal into Hatten Park in New London, Wis., where American Transmission Co. and the New London Parks and Recreation department will host an event for kids and families. The bicyclists will be making a lunch stop on the fourth day of the nearly 600-mile STIHL Tour des Trees, which originates in Milwaukee and tours through Wisconsin to raise awareness and contributions to benefit the TREE Fund. Since 1992, the STIHL Tour des Trees has raised more than $6.6 million to fund research, education grants and scholarships administered by the TREE Fund.

At 11 a.m. in Hatton Park on July 30, Toronto arborist and veteran Tour cyclist Warren Hoselton, also known as “Professor Elwood Pricklethorn,” will present a kid-friendly short course in tree science. The Professor will be joined by renowned Wisconsin gardening expert, TV/radio host and author Melinda Myers, who will talk about the importance of trees and how to Grow Smart – by planting them a safe distance from high-voltage transmission lines. The 45-minute interactive program will focus on how trees grow, where and how to plant trees to increase their longevity and what kids can do to care for the trees in their world. The program is free, and the public is invited.

New London Public School fifth graders, assisted by Ranger Services Inc., planted a tree in Hatten Park on Arbor Day in anticipation of the Tour’s visit. On July 30, the Professor and Melinda Myers will lead the Tour cyclists and audience members in a special dedication of the new tree, and every child in attendance will take home books, seeds and other materials contributed by ATC, Bartlett Tree Experts, Wisconsin Arborist Association and the Wisconsin Dept. of Natural Resources. The New London Public Library also will receive a set of books about trees and a donation from the TREE Fund, for inclusion in its children’s collection.

Note to editors: A video about the STIHL Tour des Trees can be found on YouTube by clicking here.

]]>
http://www.atcllc.com/news/american-transmission-co-to-sponsor-stihl-tour-des-trees-stop-in-new-london/feed/ 0
Just imagine…riding 583 miles all for the benefit of trees http://www.atcllc.com/blog/just-imagineriding-583-miles-all-for-the-benefit-of-trees/ http://www.atcllc.com/blog/just-imagineriding-583-miles-all-for-the-benefit-of-trees/#comments Thu, 24 Jul 2014 19:27:00 +0000 http://www.atcllc.com/uncategorized/just-imagineriding-583-miles-all-for-the-benefit-of-trees/ On Sunday, July 27, American Transmission Co. Vegetation Management Specialist Ben Gura will join nearly 100 other cyclists as they kick off the STIHL Tour des Trees. Since 1992, riders have generated nearly $7 million for The TREE Fund. This will be Gura’s second Tour.

“I’ve made a living removing and pruning trees, so when I see an opportunity to give something back to the trees I jump on it,” said Gura.

The STIHL Tour des Trees rolls out from Milwaukee and includes stops throughout central and southeast Wisconsin. ATC is sponsoring the Tour’s July 30 stop in New London. At 11 a.m. in Hatton Park, Toronto arborist and veteran Tour cyclist Warren Hoselton, also known as “Professor Elwood Pricklethorn,” will present a free kid-friendly short course in tree science. The professor will be joined by renowned Wisconsin gardening expert Melinda Myers, who will talk about the importance of trees and how to Grow Smart by planting them a safe distance from high-voltage transmission lines. The 45-minute program will focus on how trees grow, where and how to plant trees to increase their longevity and what kids can do to care for the trees. The TREE Fund mission aligns with ATC’s environmental policy ─ benefitting people, trees and the environment.

ATC is a Tree Line USA utility with environmental designations from the Wisconsin Department of Natural Resources and Michigan’s Department of Environmental Quality. Subscribe to our blog for event updates and photos in the days to come.

]]>
http://www.atcllc.com/blog/just-imagineriding-583-miles-all-for-the-benefit-of-trees/feed/ 0
ATC partners with Western Wisconsin American Red Cross to provide disaster relief http://www.atcllc.com/blog/atc-partners-with-western-wisconsin-american-red-cross-to-provide-disaster-relief/ http://www.atcllc.com/blog/atc-partners-with-western-wisconsin-american-red-cross-to-provide-disaster-relief/#comments Wed, 09 Jul 2014 21:41:00 +0000 http://www.atcllc.com/uncategorized/atc-partners-with-western-wisconsin-american-red-cross-to-provide-disaster-relief/ Tornadoes, severe storms, floods and fires have impacted many people and communities in our service area. June was a particularly volatile month, with storms and tornadoes causing significant damage throughout western Wisconsin.

American Transmission Co. system operators monitor the grid and watch the weather very carefully. We also have a Transmission Emergency Response Plan that helps employees effectively prepare for and manage emergencies that impact the transmission system.

In addition to a plan for responding to electric transmission emergencies, ATC has committed significant support to the communities it serves as a Red Cross Disaster Partner. The Disaster Partners program provides funds to local Red Cross chapters, which enables them to immediately assist people impacted by disasters such as hurricanes, wildfires, house fires or tornadoes. This support includes shelter, food, clothing, medications and health services.

According to the American Red Cross, every nine minutes emergencies that never make the news leave families without shelter, disconnected from loved ones and in need of lifesaving blood.

The Western Wisconsin Region American Red Cross has produced a handy checklist for disaster planning and emergency kits. Key highlights of the checklist include:

• Create and practice a family disaster plan.

• Assemble an emergency-preparedness kit.

• Have at least one household member trained in first aid and CPR/AED.

• Choose two places to meet if separated by an emergency: Right outside of your home in case of a sudden emergency and outside of your neighborhood, in case you cannot return home or are asked to evacuate.

Visit the Western Wisconsin Region American Red Cross website for more information on preparing for an emergency or disaster.

]]>
http://www.atcllc.com/blog/atc-partners-with-western-wisconsin-american-red-cross-to-provide-disaster-relief/feed/ 0
ATC places new transmission line in service http://www.atcllc.com/whats-current/atc-places-new-transmission-line-in-service-2/ http://www.atcllc.com/whats-current/atc-places-new-transmission-line-in-service-2/#comments Tue, 08 Jul 2014 20:45:08 +0000 http://www.atcllc.com/?p=4556 Chandler-Old Mead Road improves electric reliability in Escanaba area

DE PERE, Wis. – A new six-mile electric transmission line and a new substation have been placed in service in the Escanaba, Michigan, area.

The 138,000-volt transmission line runs from the Chandler Substation northwest of the city to the new Old Mead Road Substation located near the NewPage mill.

“The new line will help improve electric reliability,” said David Hovde, local relations consultant at American Transmission Co. “Previously, transmission facilities in the area were often overloaded; they also were so critical to maintaining service to customers that it was difficult to take an outage to perform maintenance on the system.”

Construction on the $25 million project began in summer 2013.

]]>
http://www.atcllc.com/whats-current/atc-places-new-transmission-line-in-service-2/feed/ 0
This weekend: Tosa Garden Tour http://www.atcllc.com/blog/this-weekend-tosa-garden-tour/ http://www.atcllc.com/blog/this-weekend-tosa-garden-tour/#comments Mon, 07 Jul 2014 19:17:00 +0000 http://www.atcllc.com/uncategorized/this-weekend-tosa-garden-tour/ It seems hard to believe, but July is here and summer is finally upon us. For the gardeners and landscapers out there, the warm weather is a welcome relief from this slow growing season. Getting the appropriate grasses, flowers and plants to come up at the right time — much less thrive — has been a challenge, but there’s still hope!

Melinda Myers
If you’re still working on cultivating that perfect space in your yard and need some inspiration, check out what a few others have accomplished at the Tosa Garden Tour, this Saturday, July 12. If you have specific gardening or landscaping questions, renowned Wisconsin gardening expert, TV/radio host and author Melinda Myers will be on site to provide tips at the Kanavas Landscape Management booth from 10 a.m. to 1 p.m.

While you’re there, take home some purple coneflower seed packets, courtesy of American Transmission Co. Once these hearty perennials bloom, they’ll have no problem attracting birds and butterflies. The little gardener in your life will appreciate the “Growing Gardeners” activity booklet too, including information about the purple coneflowers, so make sure to pick up one of those as well.

Rain or shine, the garden tour is on. Sign up here and we’ll see you this weekend in Wauwatosa!

]]>
http://www.atcllc.com/blog/this-weekend-tosa-garden-tour/feed/ 0
ATC named one of the top workplaces in southeast Wisconsin http://www.atcllc.com/blog/atc-named-one-of-the-top-workplaces-in-southeast-wisconsin/ http://www.atcllc.com/blog/atc-named-one-of-the-top-workplaces-in-southeast-wisconsin/#comments Mon, 09 Jun 2014 12:59:00 +0000 http://www.atcllc.com/uncategorized/atc-named-one-of-the-top-workplaces-in-southeast-wisconsin/
It’s time to celebrate! On Sunday, June 8, the Milwaukee Journal Sentinel published the 2014 list of Top Workplaces in southeast Wisconsin, and we’re on it! The list recognizes area businesses and organizations whose employees find their jobs most rewarding and meaningful. 
The evaluation was based on employee responses to a survey about ATC’s values, execution, leadership, culture, job satisfaction and overall feelings about working at the company. ATC was nominated for consideration last fall, and 90 percent of ATC’s Pewaukee-based employees responded to the survey.
This is the fifth year the Journal has published the list. ATC has been nominated twice, and we’ve won twice – this year and in 2011.
As ATC aims to be the premier national energy delivery company, these opportunities help us evaluate what we are doing right, and how we can improve upon making employees’ experience at ATC a great one.
We are honored to have been selected for the award, particularly as the judges are our employees.
Click here to check out ATC’s company profile and herefor the full list of top southeast Wisconsin workplaces.
]]>
http://www.atcllc.com/blog/atc-named-one-of-the-top-workplaces-in-southeast-wisconsin/feed/ 0
ATC named one of the top workplaces in southeastern Wisconsin http://www.atcllc.com/blog/atc-named-one-of-the-top-workplaces-in-southeastern-wisconsin/ http://www.atcllc.com/blog/atc-named-one-of-the-top-workplaces-in-southeastern-wisconsin/#comments Mon, 09 Jun 2014 12:54:19 +0000 http://www.atcllc.com/?p=4474 Milwaukee Journal Sentinel Top Workplaces list names 150 best area employers

PEWAUKEE, WIS. — American Transmission Co. has been selected as one of the 2014 Milwaukee Journal Sentinel Top Workplaces in southeastern Wisconsin.

The Top Workplaces are determined based on feedback from an employee survey, conducted by WorkplaceDynamics, LLP, an organizational health and employee engagement research firm. This is the fifth year the Milwaukee Journal Sentinel has worked with Workplace Dynamics, LLP to develop and publish the list of top area workplaces, and this is the second time ATC has been nominated and named to the list.

Approximately 90 percent of ATC’s Milwaukee-area employees responded to the survey, which asked questions about ATC’s values, execution, leadership, culture, job satisfaction and overall feelings about working at the company. As ATC strives to become the premier national energy delivery company, surveys such as this help highlight how practices in place at ATC are experienced by employees.

“Every day, we strive to be a company where employees enjoy their work. The best way to gauge how we are doing is to ask our employees for feedback,” said ATC President and CEO John Procario. “It is very gratifying to be recognized as a top workplace, especially since the judges are our employees.”

The Milwaukee Journal Sentinel published the complete list over the weekend. Click here for the entire list and here for ATC’s company profile.

]]>
http://www.atcllc.com/blog/atc-named-one-of-the-top-workplaces-in-southeastern-wisconsin/feed/ 0
ATC transmission line application determined to be complete http://www.atcllc.com/whats-current/atc-transmission-line-application-determined-to-be-complete/ http://www.atcllc.com/whats-current/atc-transmission-line-application-determined-to-be-complete/#comments Tue, 03 Jun 2014 15:04:58 +0000 http://www.atcllc.com/?p=4466 New power lines proposed for northeastern Wisconsin

DE PERE, Wis. – The Public Service Commission of Wisconsin has deemed complete American Transmission Co.’s application to build new 345,000- and 138,000-volt transmission lines in northeastern Wisconsin. The North Appleton-Morgan transmission line project, part of ATC’s Bay Lake Project, includes facilities in Outagamie, Brown, Shawano, Oconto and Marinette counties. The project is needed to address reliability concerns, changes in generation and demand in the region, and the evolution of a wholesale electricity market.

“Without these reinforcements, areas of northeastern Wisconsin, including Green Bay and the Upper Peninsula of Michigan, would be vulnerable to widespread outages,” said David Hovde, ATC local relations consultant.

The completeness determination begins an extensive regulatory review by the PSC, the Wisconsin Department of Natural Resources and Department of Agriculture. The review will include public and technical hearings as well as an environmental impact statement.

Estimated cost of the project is $307 million to $327 million, depending on the route and substation alternatives. If approved, construction would begin in 2017 and the line would be placed in service in 2019.

]]>
http://www.atcllc.com/whats-current/atc-transmission-line-application-determined-to-be-complete/feed/ 0
ATC to rebuild transmission line in western Kenosha County http://www.atcllc.com/whats-current/atc-to-rebuild-transmission-line-in-western-kenosha-county/ http://www.atcllc.com/whats-current/atc-to-rebuild-transmission-line-in-western-kenosha-county/#comments Tue, 27 May 2014 17:38:59 +0000 http://www.atcllc.com/?p=4445 PEWAUKEE, WIS. – American Transmission Co. has received approval from the Public Service Commission of Wisconsin to reconstruct approximately 12.5 miles of 138,000-volt transmission lines in western Kenosha County. The Paris – Albers Rebuild Project will run from the Paris Substation, located in the towns of Paris and Somers, Wisconsin, to the Albers substation in the City of Kenosha, Wisconsin.

“This project will help maintain reliability of the electric transmission system,” said Mary Carpenter, senior local relations representative. “The existing transmission line was originally built in 1947, and this rebuild will allow the system to meet current and future electricity loads.”

This project involves replacing the aging H-frame wooden poles with new H-frame wooden poles. The existing wires strung between the poles also will be replaced with larger wires to increase the line capacity. No new right-of-way is needed, and the new poles will be placed within a few feet of the existing poles. ATC will work with landowners to access the right-of-way through their property if necessary.

Construction is expected to begin in fall 2014, with completion in early 2015. The estimated cost of the project is $11.5 million. Landowners along the right-of-way have been informed of the project and will continue to be kept apprised as the project proceeds.

Additional details are available on the PSC’s website under Docket No. 137-CE-174. A map of the proposed project and additional information can be found at www.atc-projects.com.

]]>
http://www.atcllc.com/whats-current/atc-to-rebuild-transmission-line-in-western-kenosha-county/feed/ 0
PSC announces dates for Badger Coulee scoping sessions http://www.atcllc.com/blog/psc-announces-dates-for-badger-coulee-scoping-sessions/ http://www.atcllc.com/blog/psc-announces-dates-for-badger-coulee-scoping-sessions/#comments Fri, 16 May 2014 19:54:00 +0000 http://www.atcllc.com/uncategorized/psc-announces-dates-for-badger-coulee-scoping-sessions/ The Public Service Commission of Wisconsin this week released the dates, times and locations of six scoping sessions to solicit input from the public to help determine the scope of the Environmental Impact Statement that must be prepared regarding the proposed Badger Coulee Transmission Project. The PSC also mailed notifications to potentially affected property owners.
American Transmission Co. and Xcel Energy jointly filed an application with the Public Service Commission to construct a 345,000-volt electric transmission line from north of La Crosse to northern Dane County, Wisconsin.
A flowchart of the PSC’s comprehensive regulatory review process is available here.

More than 90 percent of the approximately 182-mile northern route uses existing utility and Interstate or U.S. Highway corridors, and about 60 percent of the approximately 159-mile southern route uses shared corridors. Both route options have the same end points: Xcel Energy’s new Briggs Road Substation near Holmen and ATC’s North Madison Substation in the Town of Vienna, continuing to ATC’s Cardinal Substation in the Town of Middleton. If the project is approved, the PSC will select the final route. The estimated cost is $540 million to $580 million, depending on the route.
ATC and Xcel Energy anticipate receiving a decision on the project by April 2015.
Anyone interested in this project is invited to attend the PSC’s meetings. The sessions will run from 3 p.m. to 8:30 p.m.
Dates and locations
Wednesday, May 28, 2014 — Waunakee Village Community Center, 333 S. Madison St., Waunakee
Monday, June 2, 2014 — Town of Holland Town Hall, W7937 County Road MH, Holland
Tuesday, June 3, 2014 — Cashton Community Hall, 811 Main St., Cashton
Thursday, June 5, 2014 — Kalahari Resorts, 1305 Kalahari Dr., Wisconsin Dells
Monday, June 9, 2014 — Comfort Inn and Suites, W10170 Holiday Dr., Black River Falls
Tuesday, June 10, 2014 — Best Western, 1017 East McCoy Blvd., Tomah
]]>
http://www.atcllc.com/blog/psc-announces-dates-for-badger-coulee-scoping-sessions/feed/ 0
ATC plans to rebuild aging transmission line in Rock, Walworth counties http://www.atcllc.com/whats-current/atc-plans-to-rebuild-aging-transmission-line-in-rock-walworth-counties/ http://www.atcllc.com/whats-current/atc-plans-to-rebuild-aging-transmission-line-in-rock-walworth-counties/#comments Thu, 15 May 2014 17:24:51 +0000 http://www.atcllc.com/?p=4424 Project will improve aging infrastructure, enhance area electric reliability

PEWAUKEE, WIS. – American Transmission Co. today filed an application with the Public Service Commission of Wisconsin to rebuild a 20-mile, 69,000-volt transmission line in Rock and Walworth counties. The proposed Colley Road-Brick Church Rebuild Project will run from the Colley Road Substation in Beloit, Wisconsin, to the Brick Church Substation in Walworth, Wisconsin. The project also involves construction of the new Tiger Substation near Clinton, Wisconsin.

The project will involve stringing new wires and replacing aging wood transmission poles with new steel poles. The current route will generally be maintained, though minor adjustments are planned to improve design efficiency.  Spans will be increased where possible to minimize the total number of structures. The new substation will be constructed on approximately 10 acres of land owned by ATC near Clinton.

“The project is needed to replace aging infrastructure, as much of the existing line is more than 60 years old,” said Jon Callaway, senior local relations representative for ATC. “It also will help ensure electric reliability in the area by relieving potential system constraints due to projected load growth.”

If the estimated $40 million project is approved, construction would begin in mid to late 2015 to meet an in-service date of 2018.

Additional details are available on the PSC website under Docket No. 137-CE-171. A map of the proposed project and additional information can be found at www.atc-projects.com.

]]>
http://www.atcllc.com/whats-current/atc-plans-to-rebuild-aging-transmission-line-in-rock-walworth-counties/feed/ 0
Lorenz promoted to VP of human resources, safety and facilities http://www.atcllc.com/whats-current/lorenz-promoted-to-vp-of-human-resources-safety-and-facilities/ http://www.atcllc.com/whats-current/lorenz-promoted-to-vp-of-human-resources-safety-and-facilities/#comments Tue, 13 May 2014 15:48:29 +0000 http://www.atcllc.com/?p=4413 PEWAUKEE, WIS. – American Transmission Co. has promoted Lori Lorenz to vice president of human capital. In this role, Lorenz oversees human resources, safety and facilities.

Lori LorenzLorenz brings years of experience and a wealth of human resources knowledge to the position. She joined ATC in 2013 as director of human resources, and prior to that served as vice president, human resources at Aurora Health Care in Milwaukee. She also was managing director of human capital at Robert W. Baird & Co. While at Baird, the organization achieved Fortune’s “100 Best Companies to Work For” recognition for nine consecutive years.

Lorenz is an active member of several local and national human resources organizations, including Society for Human Resource Management, Milwaukee Area Compensation Association, FUEL Milwaukee’s Employer Council, MRA’s HR Executive Forum, Waukesha Tempo and Waukesha County Business Alliance. She also serves on the personnel committee of the Roger’s Memorial Hospital board of directors and is a board member of Carmen High School of Science & Technology in Milwaukee. Lorenz was recognized in 2008 as one of The Business Journal’s “Forty Under 40” list of young business and community leaders in the Milwaukee metro area.

Lorenz holds a bachelor’s degree in human resources management from UW-Whitewater, and also holds certifications as Senior Professional in Human Resources, Global Professional in Human Resources and Certified Compensation Professional.

]]>
http://www.atcllc.com/whats-current/lorenz-promoted-to-vp-of-human-resources-safety-and-facilities/feed/ 0
Satterfield named EVP of business development, planning, policy, communications http://www.atcllc.com/whats-current/satterfield-named-evp-of-business-development-planning-policy-communications/ http://www.atcllc.com/whats-current/satterfield-named-evp-of-business-development-planning-policy-communications/#comments Wed, 07 May 2014 17:54:02 +0000 http://www.atcllc.com/?p=4394 Randy SatterfieldPEWAUKEE, WIS. – American Transmission Co. has named Randy Satterfield executive vice president of strategic planning and project development. In his new role at ATC, Satterfield oversees business development, strategic planning, regulatory policy and communications.

Satterfield joined ATC in 2003 as director of communications. In 2006, he became director of regulatory and governmental relations. He was named vice president of public affairs in 2008 and was promoted to executive vice president of public affairs and human resources in 2012, overseeing government relations, real estate, environmental, local relations, communications, customer relations, human resources and facilities.

Prior to joining ATC, Satterfield provided strategic communications, government affairs and political consulting services to a variety of corporations and organizations in Wisconsin. Before relocating to Wisconsin, Satterfield served as an assistant director in the Bureau of Consumer Protection at the Federal Trade Commission. In his 13 years in Washington, D.C., he also provided strategic communications, international corporate relations and political consulting services to a variety of organizations and corporations.

Satterfield holds bachelor’s degrees in philosophy and political science from Marquette University.

]]>
http://www.atcllc.com/whats-current/satterfield-named-evp-of-business-development-planning-policy-communications/feed/ 0
ATC files application for new 345- and 138-kV transmission lines http://www.atcllc.com/whats-current/atc-files-application-for-new-345-and-138-kv-transmission-lines/ http://www.atcllc.com/whats-current/atc-files-application-for-new-345-and-138-kv-transmission-lines/#comments Thu, 01 May 2014 16:53:16 +0000 http://www.atcllc.com/?p=4379 North Appleton-Morgan line is part of Bay Lake Project

PEWAUKEE, Wis. – American Transmission Co. has submitted a regulatory application to the Public Service Commission of Wisconsin, seeking permission to build new power lines and substation facilities in Outagamie, Brown, Shawano, Oconto and Marinette counties.

“The North Appleton-Morgan Project is needed to address reliability concerns, changes in generation and demand in the region, and the evolution of a wholesale electricity market,” said David Hovde, ATC local relations consultant. “Without these reinforcements, areas of northeastern Wisconsin, including Green Bay and the Upper Peninsula of Michigan, would be vulnerable to widespread outages.”

As part of ATC’s Bay Lake Project announced in 2012, North Appleton-Morgan includes:

 A new 345-kV line and a new 138-kV line between the North Appleton Substation on French Road in the Town of Freedom in Outagamie County and the Morgan Substation in Oconto County (about 40 to 48 miles depending on route),

  • Expanded facilities at North Appleton and Morgan substations,
  • A new Benson Lake Substation at the site of the Amberg Substation in Marinette County to accommodate a large voltage-control device and
  • Additional work at 11 substations in northern Wisconsin and Michigan’s Upper Peninsula.

ATC met with landowners, local officials and other interested stakeholders for nearly two years to develop route alternatives for the new transmission lines. A number of different route section options are identified in the application that generally form an east or west alternative within three routing areas.

When proposing route options to the PSC, ATC will sometimes state a preference for an option that would balance landowner, environmental, construction and cost impacts.

ATC has expressed a preference for the east option in the south routing area, the west option in the central routing area and no preference in the north routing area.

  • ATC has stated a preference for the east option in the south routing area because the west option travels through densely developed residential areas and would impact more residences than the east option.
  • The west option in the central routing area has been designated as the preferred option because it shares more right-of-way with existing facilities.
  • No preference has been expressed for the north routing area; the west option provides more opportunity for shared right-of-way and fewer environmental impacts, but could impact more properties. The east option, while shorter and straighter, could have more environmental impacts.

“While we have expressed preferences in certain areas, it is important for all stakeholders to remain involved in the process because the Public Service Commission ultimately chooses the route if the project is approved,” Hovde explained.

Single-circuit, self-supporting steel monopole structures would be used in most locations. The typical height of the structures would be 85 feet on the 138-kV line and 120 feet on the 345-kV line.

Estimated cost of the project is $307 to $327 million, depending on the route and substation alternatives. If approved, construction would begin in 2017 and the line would be placed in service in 2019.

# # #

NOTE TO EDITORS:  Maps, fact sheets and additional information is available at www.BayLakeProject.com

]]>
http://www.atcllc.com/whats-current/atc-files-application-for-new-345-and-138-kv-transmission-lines/feed/ 0
PSC deems Badger Coulee Transmission Line Project application complete http://www.atcllc.com/whats-current/psc-deems-badger-coulee-transmission-line-project-application-complete/ http://www.atcllc.com/whats-current/psc-deems-badger-coulee-transmission-line-project-application-complete/#comments Wed, 30 Apr 2014 18:16:41 +0000 http://www.atcllc.com/?p=4377 Extensive regulatory review process officially begins

MADISON, Wis. – The Public Service Commission of Wisconsin has determined complete the joint application of American Transmission Co. and Xcel Energy to build an approximately 160- to 180-mile, 345,000-volt transmission line from the La Crosse area to northern Dane County, Wisconsin. The next step is an extensive regulatory review by the PSC, Wisconsin Department of Natural Resources and Department of Agriculture, including public notification, scoping meetings, an Environmental Impact Statement, and public and technical hearings.

The project partners in October 2013 filed an application with the PSC. The PSC requires applicants to propose two route options for a new 345-kV transmission line. More than 90 percent of the approximately 182-mile northern route uses existing utility and Interstate or U.S. Highway corridors, and about 60 percent of the approximately 159-mile southern route uses shared corridors. Both route options have the same end points: Xcel Energy’s new Briggs Road Substation near Holmen and ATC’s North Madison Substation in the Town of Vienna, continuing to ATC’s Cardinal Substation in the Town of Middleton. If the project is approved, the PSC will select the final route. The estimated cost is $540 million to $580 million, depending on the route.

“We appreciate the public’s active involvement over the past several years in helping us evaluate possible routes,” said ATC Manager of Environmental and Local Relations Greg Levesque. “The PSC’s regulatory review phase allows further opportunity for stakeholders to submit comments directly to the PSC and be part of the process.”

The Badger Coulee Transmission Line Project has been designated a Multi-Value Project by the Midcontinent Independent System Operator because it will enable the delivery of energy in support of reliability, economic and public policy benefits. Studies indicate that a new transmission line will offset the need for about $160 million to $180 million in lower voltage transmission system upgrades in western Wisconsin, provide local utilities with increased access to the wholesale energy market and could provide $118 million to $700 million in net economic benefits to electric consumers over the life of the line. The new transmission line also would establish another pathway for renewable energy into Wisconsin with a connection to key load centers.

“Today’s decision is another step forward in a very comprehensive and inclusive regulatory process,” said Xcel Energy Project Manager Dave Rockwell. “We strongly encourage all interested stakeholders to stay involved as the review process may take up to 12 months.”

If the project is approved, construction of the new transmission line would begin in 2016 to meet an in-service date of 2018.

Note to editors:
A map of the final route options and additional project information are available at www.BadgerCoulee.com.

ATC and Xcel Energy’s application with the PSC can be found by visiting www.psc.wi.gov and entering Docket No. 5-CE-142 (current docket number) or 137-CE-160 (previous docket number).

# # # 

About ATC
ATC is a Wisconsin-based utility that owns, operates, builds and maintains the high-voltage electric transmission system serving portions of the Upper Midwest. Formed in 2001 as the nation’s first multi-state transmission-only utility, ATC has invested $3.2 billion to improve the adequacy and reliability of its infrastructure. ATC now is a $3.6 billion company with 9,480 miles of transmission lines and 529 substations. The company is a member of the MISO regional transmission organization, and provides nondiscriminatory service to all customers, supporting effective competition in energy markets without favoring any market participant. For more information, visit www.atcllc.com. 

About Xcel Energy
Xcel Energy is a major U.S. electricity and natural gas company, with retail operations in eight Western and Midwestern states, including Wisconsin. Xcel Energy provides a comprehensive portfolio of energy-related products and services to 3.4 million electricity customers and 1.9 million natural gas customers through its regulated operating companies. Company headquarters are located in Minneapolis, and Wisconsin-Michigan operating company headquarters are located in Eau Claire, Wisconsin. For more information about Xcel Energy visit www.xcelenergy.com.

]]>
http://www.atcllc.com/whats-current/psc-deems-badger-coulee-transmission-line-project-application-complete/feed/ 0
Helicopter, air saw to be used for tree trimming along transmission lines in Columbia, Dane and Rock counties http://www.atcllc.com/whats-current/helicopter-air-saw-to-be-used-for-tree-trimming-along-transmission-lines-in-columbia-dane-and-rock-counties/ http://www.atcllc.com/whats-current/helicopter-air-saw-to-be-used-for-tree-trimming-along-transmission-lines-in-columbia-dane-and-rock-counties/#comments Wed, 12 Mar 2014 16:11:51 +0000 http://www.atcllc.com/?p=4272 Aerial work scheduled to start mid-March

MADISON, Wis. – A helicopter and heavy-duty air saw are scheduled to be used beginning this week to trim trees along two transmission lines in Columbia, Dane and Rock counties.

American Transmission Co. has contracted with Aerial Solutions, Inc., a company that specializes in aerial tree management along transmission line corridors. The helicopters are equipped with heavy-duty air saws with rotary blades suspended on a 90-foot vertical boom. In some areas, ground crews will be performing additional vegetation removal work this year.

“The helicopter and air saw will be used to side trim trees at the edge of the right-of-way,” said Adam Helminiak, ATC senior vegetation management specialist. “This work will help us ensure the safe and reliable operation of the electric transmission system.”

Tree trimming will occur along portions of a 345,000-volt line that runs from the Columbia Substation near Portage, Wis., to the Rockdale Substation in the Town of Christiana, Wis. Trimming also will be done on portions of a 345-kV line that runs from the Rockdale Substation to the Paddock Substation near Beloit, Wis. Because the work is weather-dependent, flight schedules will vary and may extend into late March.

Managing the growth of trees and other vegetation is key to helping ensure public safety and electric system reliability. ATC performs routine vegetation management on its 9,480 miles of transmission lines in five-year cycles.

Note to editors: A video of similar aerial vegetation management work is available on our YouTube channel.

]]>
http://www.atcllc.com/whats-current/helicopter-air-saw-to-be-used-for-tree-trimming-along-transmission-lines-in-columbia-dane-and-rock-counties/feed/ 0
ATC employees power through American Birkebeiner race http://www.atcllc.com/blog/atc-employees-power-through-american-birkebeiner-race/ http://www.atcllc.com/blog/atc-employees-power-through-american-birkebeiner-race/#comments Tue, 04 Mar 2014 21:55:00 +0000 http://www.atcllc.com/uncategorized/atc-employees-power-through-american-birkebeiner-race/

Each year, more than 13,000 skiers descend upon Cable, Wis., to participate in the storied American Birkebeiner, or Birkie. The 50-kilometer cross-country ski event began in 1973, but the tradition goes back to Norway and the 1200s. Birkebeiners were charged with carrying the young  son of King Sverresson and Inga of Vartieg to safety. They donned birch bark leggings and traversed the mountains and forests of the Osterdalen valley in Norway during the Norwegian Civil War. The child transported to safety by the Birkebeiners was King Haakon Haakonsson IV. Thousands of skiers commemorate this event across the globe each year. Norwegian skiers often will carry a pack that symbolizes the weight of an 18-month-old child. 

Hagman at the end of the race.
Three American Transmission Co. employees joined in the tradition this year and powered through bitter cold to finish the race.
Transmission Planning Engineer Chris Hagman had a warm-up race in sub-zero temperatures weeks prior in the Upper Peninsula of Michigan, so when the mercury rose above freezing, it was a pleasant surprise for this tough racer.
“Of my seven Birkies, this was definitely the hardest and the slowest,” Hagman said. His girlfriend, Marianne, helped make the race a little more entertaining by organizing a group to provide comic relief and encouragement at a very steep hill just before the end of the race.
Construction Coordinator Paul Roltgen also agreed about the difficulty this year, calling his sixth Birkie the hardest one to date.
“Thursday night prior to the event, the Hayward area had 16-plus inches of snow. The new snow combined with the cold and the strong west wind certainly made it a challenge,” Roltgen said. “To put it into context, I finished 45 minutes slower than my fastest time. I still loved being in the winter wonderland surrounded by woods and upbeat competitors, many who keep coming back year after year.”
And what might a Professional Engineer who works at an electric utility call out as one of the highlights of the race?
“At a certain point after about 9 kilometers, racers travel below a 138-kilovolt circuit. There are hundreds of skate skiers on one side of the right-of-way going up and down the rolling hills right below the lines, while the classic skiers are on the other side doing the same,” said Project Manager Andy Ehlert.
Another highlight for Ehlert is an elaborate drumming display that takes place at the top of a hill.
“At one point at the top of a hill climb we pass by about 50 people from the local Lac Courte Oreilles tribe as they bang loudly on huge drums,” said Ehlert. “The skiers march up the steep hill in rhythm and it is awesome! It gives me goose bumps each time I pass by and really brings home the spirit of the race in that region of Wisconsin.”  

Roltgen warms up by getting into Viking garb and participating in a ‘Giant Ski Race,’ where teams strap themselves onto a set of giant skis and race down main street in Hayward, Wis.








]]>
http://www.atcllc.com/blog/atc-employees-power-through-american-birkebeiner-race/feed/ 0
ATC announces second round of public open houses for Spring Valley-North Lake Geneva project http://www.atcllc.com/whats-current/atc-announces-second-round-of-public-open-houses-for-spring-valley-north-lake-geneva-project/ http://www.atcllc.com/whats-current/atc-announces-second-round-of-public-open-houses-for-spring-valley-north-lake-geneva-project/#comments Wed, 26 Feb 2014 22:30:30 +0000 http://www.atcllc.com/?p=4256 New transmission line and substation proposed to improve electric reliability

PEWAUKEE, Wis. – American Transmission Co. is holding a second round of public open houses for the proposed Spring Valley-North Lake Geneva Electric Reliability Project. Informational open houses will be held in mid-March for residents and other stakeholders to review the routes and substation site options for the proposed 25-mile, 138-kilovolt transmission line from southern Walworth County to western Kenosha County, Wis.

“We’ve been working with Alliant Energy and We Energies for several years to identify a suitable long-term electric solution for this growing area,” said Mary Carpenter, local relations representative. “The communities and residents have been helpful in developing the project and the proposed routes.”

The electric transmission system in the area is vulnerable to low voltages and power outages and can no longer adequately support the lower-voltage distribution system. ATC studies indicate that the project would strengthen the electric transmission system to meet the growing use of electricity. This estimated $80 million to $95 million project would provide system redundancy and allow for maintenance outages when repairs are needed.

The public is invited to attend either of the following open houses any time between3 and 7 p.m.:

Tuesday, March 11, Marino’s Country Aire Banquet Hall, 34816 Geneva Rd., Burlington

Wednesday, March 12, Hawks View Golf Club, 7377 Krueger Rd., Lake Geneva

Following these open houses, ATC will evaluate public comments on the proposed route options to determine if modifications are needed. A final round of open houses will be held in early 2015 to present the route options that will be included in ATC’s application to the Public Service Commission of Wisconsin for permission to build the line and substation. If approved, the PSC will select the route to be built. Construction would begin in 2017 to meet an in-service date of 2019.

Note to editors: A map showing the proposed route options along with additional information about the project is available at www.atc-projects.com.

]]>
http://www.atcllc.com/whats-current/atc-announces-second-round-of-public-open-houses-for-spring-valley-north-lake-geneva-project/feed/ 0
Helicopter, air saw to be used for tree trimming in Manitowoc, Brown, Sheboygan, Fond du Lac counties http://www.atcllc.com/whats-current/helicopter-air-saw-to-be-used-for-tree-trimming-in-manitowoc-brown-sheboygan-fond-du-lac-counties/ http://www.atcllc.com/whats-current/helicopter-air-saw-to-be-used-for-tree-trimming-in-manitowoc-brown-sheboygan-fond-du-lac-counties/#comments Fri, 21 Feb 2014 16:11:30 +0000 http://www.atcllc.com/?p=4247 Aerial work scheduled to begin late February or early March 

PEWAUKEE, Wis. – A helicopter and heavy-duty air saw will be used beginning the last week of February or early March to trim trees along transmission lines in eastern Wisconsin.

American Transmission Co. has contracted with Aerial Solutions, Inc., a company that specializes in aerial tree management along transmission line corridors. The helicopters are equipped with heavy-duty air saws with rotary blades suspended on a 90-foot vertical boom. In some areas, ground crews will be performing additional vegetation removal work this year.

“We’ll be using the helicopter and air saw to side trim trees at the edge of the right-of-way,” said Ben Gura, ATC senior vegetation management specialist. “This work will help us ensure the safe and reliable operation of the electric system.” 

Tree trimming will occur along a 345,000-volt line that runs from the Point Beach Nuclear Plant in northeastern Manitowoc County, Wis., west across southern Brown County to west of Wrightstown, Wis. Trees also will be trimmed along a 345-kV line that extends from Sheboygan, Wis., southwest of Fond du Lac, Wis. Because the work is weather-dependent, flight schedules will vary and may extend later into March.

Managing the growth of trees and other vegetation is crucial to helping ensure public safety and electric system reliability. ATC performs routine vegetation management on its 9,480 miles of transmission lines in five-year cycles.

Note to editors: A video of similar aerial vegetation management work is available on our YouTube channel.

]]>
http://www.atcllc.com/whats-current/helicopter-air-saw-to-be-used-for-tree-trimming-in-manitowoc-brown-sheboygan-fond-du-lac-counties/feed/ 0
American Transmission Co. opposes legislation that would reduce coordinated regulatory reviews and permitting for utility projects http://www.atcllc.com/whats-current/american-transmission-co-opposes-legislation-that-would-reduce-coordinated-regulatory-reviews-and-permitting-for-utility-projects/ http://www.atcllc.com/whats-current/american-transmission-co-opposes-legislation-that-would-reduce-coordinated-regulatory-reviews-and-permitting-for-utility-projects/#comments Wed, 19 Feb 2014 15:44:49 +0000 http://www.atcllc.com/?p=4245 Proposed legislation could increase costs, eliminate coordinated environmental oversight

PEWAUKEE, Wis. – American Transmission Co. opposes Assembly Bill 774, which would impair the efficient coordination that currently exists between the Wisconsin Department of Natural Resources and the Wisconsin Public Service Commission for reviewing and permitting utility projects.

Over the last decade, ATC has successfully permitted nearly $3 billion in transmission reliability improvements under the current process, which provides for a streamlined and thorough examination of environmental impacts and protections. This legislation would undo the successful coordination that occurs among the DNR, the PSC, applicants and the public brought about through 2003 Act 89. In addition, it would negate the improvements to laws governing development and siting of transmission lines that were enacted in 2013 through Act 10.

The bill is being justified on the grounds that it will eliminate bureaucracy and reduce costs. In fact, the bill could increase the costs by eliminating the coordination among agencies, creating opportunities for duplicate or unnecessary work, and introducing the potential for more disputes.

 

]]>
http://www.atcllc.com/whats-current/american-transmission-co-opposes-legislation-that-would-reduce-coordinated-regulatory-reviews-and-permitting-for-utility-projects/feed/ 0
ATC plans to rebuild aging transmission line in Kenosha County http://www.atcllc.com/whats-current/atc-plans-to-rebuild-aging-transmission-line-in-kenosha-county/ http://www.atcllc.com/whats-current/atc-plans-to-rebuild-aging-transmission-line-in-kenosha-county/#comments Tue, 18 Feb 2014 19:29:52 +0000 http://www.atcllc.com/?p=4243 Project will enhance electric reliability for southeastern Wisconsin

Pewaukee, Wis. – American Transmission Co. today filed an application with the Public Service Commission of Wisconsin to rebuild a 12.5 mile, 138,000-volt transmission line in western Kenosha County. The proposed Paris-Albers Rebuild Project will run from the Paris Substation in Paris, Wis., to the Albers substation in Kenosha, Wis.

The project will involve stringing new wires and replacing aging wood transmission poles with new wood and steel poles. No new right-of-way is needed and the new poles will be placed within a few feet of the existing poles.

“The project is estimated to cost $12.2 million and is needed to help ensure safe and reliable transmission operations in the future and adequate clearances to the ground,” said Mary Carpenter, senior local relations representative for ATC.

If the project is approved, construction will begin in late 2014 to meet an in-service date of early 2015.

Additional details will be available on the PSC’s website under Docket No. 137-CE-174. A map of the proposed project and additional information can be found at www.atc-projects.com.

]]>
http://www.atcllc.com/whats-current/atc-plans-to-rebuild-aging-transmission-line-in-kenosha-county/feed/ 0
Calling all interns! http://www.atcllc.com/blog/calling-all-interns/ http://www.atcllc.com/blog/calling-all-interns/#comments Tue, 18 Feb 2014 14:50:00 +0000 http://www.atcllc.com/uncategorized/calling-all-interns/


Intern Elliot Nelson shows his team spirit with ATC
substation engineer and former intern Justin Nettesheim
during ATC’s 2014 Office Olympics at ATC’s
Madison office, Friday, Feb. 7.



Although it’s hard to imagine after the recent polar vortex, summer is just around the corner. For college students everywhere (and their parents) the impending change in season brings to mind one particular question: What am I going to do over summer break? 
How about a paid internship at American Transmission Co.? ATC has 33 internship positions to fill for summer 2014 in our Madison, Cottage Grove, Pewaukee and De Pere, Wis., offices. Many of the internships are for civil or electrical engineering students and others are in human resources, information technology and corporate security. 
ATC interns don’t make coffee. They do anything that full-time employees do. (So technically yes, that includes making coffee if they emptied the pot.) But in all seriousness, ATC interns do real work, and work right alongside professionals in their field. Interns learn invaluable career skills, processes technologies and programs—skills that give them a leg up both in their college coursework and when it’s time to find a job after graduation. 
Interested? We’re accepting applications now, so check out our open internship positions and apply today!

The basics

  • Length: May – August, with a possibility to extend into the fall or winter
  • Hours: 40 hours per week during the summer, 15-20 hours per week during the school year
  • College credit: Some schools give credit for internships
  • When to apply: NOW!
]]>
http://www.atcllc.com/blog/calling-all-interns/feed/ 0
ATC Tree Planting Program grant helps add fruit trees to DeForest http://www.atcllc.com/blog/atc-tree-planting-program-grant-helps-add-fruit-trees-to-deforest/ http://www.atcllc.com/blog/atc-tree-planting-program-grant-helps-add-fruit-trees-to-deforest/#comments Thu, 30 Jan 2014 20:10:00 +0000 http://www.atcllc.com/uncategorized/atc-tree-planting-program-grant-helps-add-fruit-trees-to-deforest/

We’re happy to read that the Village of DeForest, Wis., plans to help add to Dane County’s burgeoning edible landscape with apple and pear trees at Liberty Land Park.

In honor of the home of the Norskies, here are a few Nordic-inspired apple and pear desserts:

Stetke epler (fried apples)

Pear coffee cake
The Capital Times also reports that remaining grant money will be used to offer shade for the Fidos and Spots of the world at a local dog park.

Read more about our Tree Planting Program and how it’s helping local communities become more beautiful and sustainable.

]]>
http://www.atcllc.com/blog/atc-tree-planting-program-grant-helps-add-fruit-trees-to-deforest/feed/ 0
An Idol connection: ATC employees’ son takes a step toward the big time http://www.atcllc.com/blog/an-idol-connection-atc-employees-son-takes-a-step-toward-the-big-time/ http://www.atcllc.com/blog/an-idol-connection-atc-employees-son-takes-a-step-toward-the-big-time/#comments Tue, 28 Jan 2014 16:22:00 +0000 http://www.atcllc.com/uncategorized/an-idol-connection-atc-employees-son-takes-a-step-toward-the-big-time/ 
Joe Janowicz headshot

There’s a bit of a buzz going around American Transmission Co.’s De Pere, Wis., office that has nothing to do with the electric grid. ATC employees, Joe and Maria Janowicz, are the proud parents of talented singer/actor Jack Janowicz, who may just make it to the big stage at Hollywood Week on American Idol.

“It’s been a wild ride,” said Joe. “We were driving in the car one day when Jack said, ‘hey, I got an email from Idol. I made the cut!’” The family hadn’t known that Jack sent a video audition, let alone that it was good enough to avoid the cattle call and proceed to audition directly in front of the show’s executive producers in Omaha, Neb. After getting through two rounds with the producers, it was on to the celebrity judges.

Joe says Jack has displayed an unexpected talent for the arts all his life.

“We have videos of him dancing in-beat to music on the radio while wearing his diaper. He’s been singing as long as he could talk,” said Joe. “I’m not sure where he got it from, but we do know he is our kid. My dad likes to joke he had talent as a kid.”

Maria says it’s an experience he’ll never forget, topped off with high praise from star and Idol judge Jennifer Lopez. “When JLo met Jack, she told him some people don’t look the way they sound, but that Jack sounds exactly the way he looks. She said, ‘You have the whole package and I like it,’ while making a little box with her fingers. I told Jack if he ever has a bad day, JLo’s feedback should bring a smile to his face!”

While he can’t reveal his status on the show, fans online are buzzing with rave reviews of Jack’s singing and charisma, showcased on his YouTube channel. The Omaha auditions are scheduled to air Thursday, Jan. 30, from 7 to 8 p.m. We’ll be rooting for a powerful performance from Jack.

]]>
http://www.atcllc.com/blog/an-idol-connection-atc-employees-son-takes-a-step-toward-the-big-time/feed/ 0
ATC files application for Dyckesville-Sawyer project http://www.atcllc.com/whats-current/atc-files-application-for-dyckesville-sawyer-project/ http://www.atcllc.com/whats-current/atc-files-application-for-dyckesville-sawyer-project/#comments Fri, 24 Jan 2014 15:34:11 +0000 http://www.atcllc.com/?p=4214 Aging transmission line in Brown, Kewaunee and Door counties needs to be rebuilt

DE PERE, Wis. – American Transmission Co. has filed a regulatory application with the Public Service Commission of Wisconsin to rebuild a 69,000-volt transmission line between Dyckesville, Wis. and Sturgeon Bay, Wis.

“The line was built in the 1930s and needs to be improved for assured electric reliability in the area,” said David Hovde, ATC local relations representative. “H-frame structures along the 25-mile line will be replaced with single-pole structures in the same locations.”

If approved, construction would begin in September 2015 and the line should be placed in service in summer 2016. Cost of the project is estimated to be about $23 million.

To view a copy of the application, visit the PSC’s website, http://psc.wi.gov/, and enter docket number 137-CE-172.

]]>
http://www.atcllc.com/whats-current/atc-files-application-for-dyckesville-sawyer-project/feed/ 0
Michigan PSC approves Holmes-Old Mead Road project http://www.atcllc.com/blog/michigan-psc-approves-holmes-old-mead-road-project/ http://www.atcllc.com/blog/michigan-psc-approves-holmes-old-mead-road-project/#comments Thu, 23 Jan 2014 22:15:00 +0000 http://www.atcllc.com/uncategorized/michigan-psc-approves-holmes-old-mead-road-project/ The Michigan Public Service Commission today granted a certificate of public convenience and necessity for a 138-kilovolt transmission line from the Holmes Substation in Menominee County to the Old Mead Substation in Delta County. This is ATC’s first CPCN application and approval in Michigan.

In issuing its order, the MPSC selected ATC’s proposed route. The 58-mile line will make maximum use of co-location opportunities, placing the new facilities on existing transmission line or other rights-of-way. The western half will share a corridor with an existing transmission line; the eastern half will share an abandoned railroad corridor currently owned by the Michigan Department of Transportation and managed by the Department of Natural Resources. In exchange for sharing the corridor, ATC proposes to develop a 10-foot-wide multi-purpose recreational trail.

“The new transmission line is intended to improve electric reliability significantly in the Upper Peninsula,” said MPSC Chairman John D. Quackenbush. “The settlement agreement approved today enabled the MPSC to decide this case nine months in advance of the one-year statutory deadline, enhancing ATC’s ability to bring needed improvements to the Upper Peninsula.”

]]>
http://www.atcllc.com/blog/michigan-psc-approves-holmes-old-mead-road-project/feed/ 0
ATC names Bill Marsan as general counsel http://www.atcllc.com/whats-current/atc-names-bill-marsan-as-general-counsel/ http://www.atcllc.com/whats-current/atc-names-bill-marsan-as-general-counsel/#comments Tue, 07 Jan 2014 21:09:14 +0000 http://www.atcllc.com/?p=4206 PEWAUKEE, Wis. – William P. Marsan has been named executive vice president, general counsel and corporate secretary of American Transmission Co. effective Jan. 22, 2014. He will have responsibility for legal and state regulatory staffs at ATC.

Marsan has been with Indianapolis Power & Light Company since 2005, where he served as general counsel and corporate secretary, and led the federal regulatory, environmental, government affairs, security and project development teams. Prior to joining IPL, Marsan was a partner in the energy and public law practice at Troutman Sanders LLP in Washington, DC. He also has served as counsel and legislative director on Capitol Hill and as a litigator with Campbell & Associates in Boston.  

Marsan began his legal career in the Navy Judge Advocate General’s Corps, where he served as trial counsel in more than 200 courts-martial. While on active duty, Marsan was awarded the Navy Achievement Medal and Navy Commendation. He was honorably discharged from the Naval Reserve as a lieutenant commander in 2001.

Marsan earned a Bachelor of Arts degree from Boston College and Juris Doctor from George Washington University. He also completed the Leadership Development Program at the University of Virginia Darden School of Business.

“We are pleased to welcome Bill to ATC and to our executive leadership team,” said ATC President, Chairman and Chief Executive Officer John Procario. “We welcome his strong leadership, and legal and regulatory experience.”

]]>
http://www.atcllc.com/whats-current/atc-names-bill-marsan-as-general-counsel/feed/ 0
ATC awards $74,500 for community plantings http://www.atcllc.com/blog/atc-awards-74500-for-community-plantings/ http://www.atcllc.com/blog/atc-awards-74500-for-community-plantings/#comments Fri, 20 Dec 2013 21:58:00 +0000 http://www.atcllc.com/uncategorized/atc-awards-74500-for-community-plantings/

American Transmission Co. in 2013 launched a planting program to support tree and vegetation planting in communities in its service area. During the first year of the program 59 eligible municipalities and counties received financial support for planting projects on public property within their communities in the form of grants ranging from $250 to $5,000.

To qualify, recipients committed to complying with ATC’s maintenance standards for all current and future planting plans and urban forestry activities near high-voltage electric transmission lines. Priority favored projects that promote safety and reliability of the transmission system by supporting right-of-way best management practices and keeping trees out of the right-of-way.

Tree Planting Program funding recipients are noted in the ATC news release. ATC will accept applications for its 2014 Tree Planting Program June 1 through Sept. 30, 2014, and recipients will be selected by the end of 2014.

Additional information, including a program brochure and eligibility information, is available on the ATC website.

]]>
http://www.atcllc.com/blog/atc-awards-74500-for-community-plantings/feed/ 0
American Transmission Co. awards $74,500 to sponsor community plantings http://www.atcllc.com/whats-current/american-transmission-co-awards-74500-to-sponsor-community-plantings/ http://www.atcllc.com/whats-current/american-transmission-co-awards-74500-to-sponsor-community-plantings/#comments Thu, 19 Dec 2013 17:04:57 +0000 http://www.atcllc.com/?p=4150 Program supports efforts to beautify communities

PEWAUKEE, Wis. – American Transmission Co. this year launched a planting program to support tree and vegetation planting in communities in its service area. During the first year of the program 59 eligible municipalities and counties received financial support for planting projects on public property within their communities in the form of grants ranging from $250 to $5,000.

“As an owner and operator of the area electric transmission system, it is our responsibility to keep trees and brush out of the rights-of-way of our power lines for safety and reliability reasons,” said ATC Environmental and Local Relations Manager Greg Levesque. “This program allows us to improve electric reliability by educating communities about plantings that are consistent with our safety and maintenance standards while also supporting efforts to beautify communities.”

To qualify, recipients committed to complying with ATC’s maintenance standards for all current and future planting plans and urban forestry activities near high-voltage electric transmission lines. Priority favored projects that promote safety and reliability of the transmission system by supporting right-of-way best management practices and keeping trees out of the right-of-way.

2013 Tree Planting Program funding recipients:

Antigo, Wis.
Appleton, Wis.
Baraboo, Wis.
Bayside, Wis.
Brooklyn, Wis.
Bruce, Wis.
Cambridge, Wis.
Combined Locks, Wis.
De Forest, Wis.
Delafield, Wis.
Dunn, Wis.
Fitchburg, Wis.
Fond du Lac, Wis.
Franklin, Wis.
Fredonia, Wis.
Germantown, Wis.
Gilman, Wis.
Grafton, Wis.
Grand Chute, Wis.
Greenfield, Wis.
Greenville, Wis.
Hillsboro, Wis.
Hortonville, Wis.
Hull, Wis.
Kronenwetter, Wis.
Mauston, Wis.
McFarland, Wis.
Menasha, Wis.
Merrimac, Wis.
Necedah, Wis. 
Neenah, Wis.
Oak Creek, Wis.
Oliver, Wis.
Omro, Wis.
Owen, Wis.
Ozaukee County, Wis.
Peshtigo, Wis.
Pittsville, Wis.
Port Edwards, Wis.
Prairie Du Chien, Wis.
Prairie du Sac, Wis.
Rhinelander, Wis.
Richland Center, Wis.
Sheboygan, Wis.
Spencer, Wis.
Stevens Point, Wis.
Stoddard, Wis.
Superior, Wis.
Tomah, Wis.
Tomahawk, Wis.
Waterford, Wis.
Waukesha, Wis.
Waunakee, Wis.
Waupaca, Wis.
Wausau, Wis.
Wilson, Wis.
Winnebago County, Wis.
Winneconne, Wis.
Wisconsin Dells, Wis.

ATC will accept applications for its 2014 Tree Planting Program June 1 through Sept. 30, 2014, and recipients will be selected by the end of 2014. Additional information, including a program brochure and eligibility information, is available on the ATC website: http://www.atcllc.com/learning-center/trees-and-vegetation/grow-smart-and-safely-in-your-community/.

]]>
http://www.atcllc.com/whats-current/american-transmission-co-awards-74500-to-sponsor-community-plantings/feed/ 0
Pleasant Prairie-Zion Energy Center transmission line placed in service http://www.atcllc.com/whats-current/pleasant-prairie-zion-energy-center-transmission-line-placed-in-service/ http://www.atcllc.com/whats-current/pleasant-prairie-zion-energy-center-transmission-line-placed-in-service/#comments Mon, 09 Dec 2013 18:14:51 +0000 http://www.atcllc.com/?p=4144 Multi-Value Project delivers economic benefits, establishes another important high-voltage interstate connection

PEWAUKEE, Wis. – American Transmission Co. Friday energized a newly constructed 345-kilovolt electric transmission line that establishes another important high-voltage interstate connection between Wisconsin and Illinois. The approximately 5-mile line runs from the Pleasant Prairie Substation in Pleasant Prairie, Wis., to the Zion Energy Center Substation in Zion, Ill. The new line will improve operation of the electric system in southeastern Wisconsin and northeastern Illinois.

“The new power line relieves congestion on the existing interstate transmission system, and will provide savings to electric utilities and their customers by creating a reliable pathway to move electricity from the most efficient generators to energy markets,” said ATC Major Projects Planning Manager Tom Dagenais.  

The Midcontinent Independent System Operator designated the project as one of 17 Multi-Value Projects across the Midwest that deliver significant economic benefits. This is the first of three ATC projects designated by MISO as Multi-Value Projects to be placed into service. MISO recognized the economic benefits of large capacity regional transmission lines when it introduced a portfolio of 17 projects whose costs would be shared among utilities and their customers across the entire MISO service territory. MISO estimates that the average utility customer in the region will see $23 in annual benefits from lowered delivered energy costs for about $11 a year in investment.

ATC received approval in April 2012 from the Illinois Commerce Commission and May 2012 from the Public Service Commission of Wisconsin to build the transmission line, and construction on the project began late last year.

Note to editors: A map and additional project information is available at www.atc-projects.com. Information about MISO Multi-Value Projects is available at https://www.misoenergy.org/Planning/Pages/MVPAnalysis.aspx

]]>
http://www.atcllc.com/whats-current/pleasant-prairie-zion-energy-center-transmission-line-placed-in-service/feed/ 0
A bird’s eye view of our Avian Protection Program http://www.atcllc.com/blog/a-birds-eye-view-of-our-avian-protection-program/ http://www.atcllc.com/blog/a-birds-eye-view-of-our-avian-protection-program/#comments Tue, 26 Nov 2013 22:26:00 +0000 http://www.atcllc.com/uncategorized/a-birds-eye-view-of-our-avian-protection-program/

Balancing our responsibility to improve electric system reliability with our environmental responsibilities in planning and construction is critical, and we have developed practices that provide guidance for construction work: avoidance, protection and restoration.

Read more about our Avian Protection Program.

]]>
http://www.atcllc.com/blog/a-birds-eye-view-of-our-avian-protection-program/feed/ 0
Crews use helicopters during Pleasant Prairie-Zion Project construction http://www.atcllc.com/blog/crews-use-helicopters-during-pleasant-prairie-zion-project-construction/ http://www.atcllc.com/blog/crews-use-helicopters-during-pleasant-prairie-zion-project-construction/#comments Tue, 19 Nov 2013 20:16:00 +0000 http://www.atcllc.com/uncategorized/crews-use-helicopters-during-pleasant-prairie-zion-project-construction/

Helicopters can be a real time and cost saver in transmission line construction projects. In this video, a helicopter is being used to string ropes between structures on our Pleasant Prairie-Zion Transmission Line Project near Pleasant Prairie, Wis. The ropes are then used to pull the wires between the poles.

]]>
http://www.atcllc.com/blog/crews-use-helicopters-during-pleasant-prairie-zion-project-construction/feed/ 0
Underground construction begins for Western Milwaukee County Project http://www.atcllc.com/blog/underground-construction-begins-for-western-milwaukee-county-project/ http://www.atcllc.com/blog/underground-construction-begins-for-western-milwaukee-county-project/#comments Tue, 19 Nov 2013 03:55:00 +0000 http://www.atcllc.com/uncategorized/underground-construction-begins-for-western-milwaukee-county-project/ Western Milwaukee County underground construction

Construction is underway on the underground portion of our Western Milwaukee County Electric Reliability Project. The project involves construction of two sets of 138-kilovolt lines, each two miles long, to connect a new We Energies substation to the transmission grid. The two separate lines are needed to assure redundancy to the Milwaukee Regional Medical Center, which operates two Level 1 trauma centers. Although construction was not scheduled to start until next year, we took advantage of the opportunity to begin the underground portion ─about 1,250 feet─to coincide with underground road work being performed by the Wisconsin Department of Transportation.

]]>
http://www.atcllc.com/blog/underground-construction-begins-for-western-milwaukee-county-project/feed/ 0
Special foundations used for Wisconsin River island construction http://www.atcllc.com/blog/special-foundations-used-for-wisconsin-river-island-construction/ http://www.atcllc.com/blog/special-foundations-used-for-wisconsin-river-island-construction/#comments Mon, 18 Nov 2013 22:05:00 +0000 http://www.atcllc.com/uncategorized/special-foundations-used-for-wisconsin-river-island-construction/

We are using micropile technology to replace an aging transmission structure on an island in the Wisconsin River in Stevens Point, Wis.

A micropile is a high-performance drilled and grouted foundation that can be installed in environmentally sensitive locations using lightweight specialty equipment. In this case, the micropile will eliminate the need for bringing concrete trucks on to the island.

Seawalls have been installed along the shore in Bukolt Park in Stevens Point to accommodate a barge that will be used to ferry crews and equipment to the island when the work is performed this winter.

]]>
http://www.atcllc.com/blog/special-foundations-used-for-wisconsin-river-island-construction/feed/ 0
ATC and Xcel Energy file state regulatory application to build Badger Coulee Transmission Line Project http://www.atcllc.com/whats-current/atc-and-xcel-energy-file-state-regulatory-application-to-build-badger-coulee-transmission-line-project/ http://www.atcllc.com/whats-current/atc-and-xcel-energy-file-state-regulatory-application-to-build-badger-coulee-transmission-line-project/#comments Tue, 22 Oct 2013 17:44:22 +0000 http://www.atcllc.com/?p=4078 Line would extend from north of La Crosse area to northern Dane County

MADISON, Wis. – Following years of analysis and community involvement, American Transmission Co. and Xcel Energy today filed an application with the Public Service Commission of Wisconsin seeking approval to build an approximately 160- to 180-mile, 345-kilovolt transmission line from the La Crosse area to northern Dane County.

The Badger Coulee Transmission Line Project has been designated a Multi-Value Project by the Midcontinent Independent System Operator because it will enable the delivery of energy in support of reliability, economic and public policy benefits. Studies indicate that the project will offset the need for about $160 million in lower voltage upgrades in western Wisconsin, provide increased access to the wholesale energy market and could provide $259 million to $841 million in net economic benefits over the life of the project. The project also would establish another pathway for renewable energy into Wisconsin with a connection to key load centers. 

The PSC requires ATC and Xcel Energy to propose two route options for the transmission line. More than 90 percent of the approximately 182-mile northern route uses existing utility and Interstate or U.S. Highway corridors, and about 60 percent of the approximately 159-mile southern route uses shared corridors. Both route options have the same end points: Xcel Energy’s new Briggs Road Substation near Holmen and ATC’s North Madison Substation in the Town of Vienna, continuing to ATC’s Cardinal Substation in the Town of Middleton. If the project is approved, the PSC will select the final route. The estimated cost is $514 million to $552 million, depending on the route.

“We appreciate the public’s active involvement over the past several years in helping us evaluate possible routes,” said ATC Environmental and Local Relations Manager Greg Levesque.  “We’ve looked at hundreds of paths for these lines and made adjustments based on what we learned from area landowners, businesses, community organizations and local officials.”

“The regulatory review process should take 12 to 18 months,” said Xcel Energy Project Manager David Rockwell. “During that time, the PSC will provide opportunities for the public and other stakeholders to get involved.”

If the project is approved, construction of the project would begin in 2016 to meet an in-service date of 2018.

Note to editors: A map of the final route options and additional project information are available at www.BadgerCoulee.com

ATC and Xcel Energy’s application with the PSC can be found by visiting www.psc.wi.gov and entering Docket No. 5-CE-142 (current docket number) or 137-CE-160 (previous docket number).

###

About ATC
ATC is a Wisconsin-based utility that owns, operates, builds and maintains the high-voltage electric transmission system serving portions of the Upper Midwest. Formed in 2001 as the nation’s first multi-state transmission-only utility, ATC has invested $2.8 billion to improve the adequacy and reliability of its infrastructure. ATC now is a $3.3 billion company with 9,480 miles of transmission lines and 529 substations. The company is a member of the MISO regional transmission organization, and provides nondiscriminatory service to all customers, supporting effective competition in energy markets without favoring any market participant. For more information, visit www.atcllc.com.

About Xcel Energy
Xcel Energy is a major U.S. electricity and natural gas company, with retail operations in eight Western and Midwestern states, including Wisconsin. Xcel Energy provides a comprehensive portfolio of energy-related products and services to 3.4 million electricity customers and 1.9 million natural gas customers through its regulated operating companies. Company headquarters are located in Minneapolis, and Wisconsin-Michigan operating company headquarters are located in Eau Claire, Wis. For more information about Xcel Energy visit www.xcelenergy.com.

]]>
http://www.atcllc.com/whats-current/atc-and-xcel-energy-file-state-regulatory-application-to-build-badger-coulee-transmission-line-project/feed/ 0
ATC files application with Michigan Public Service Commission http://www.atcllc.com/whats-current/atc-files-application-with-michigan-public-service-commission/ http://www.atcllc.com/whats-current/atc-files-application-with-michigan-public-service-commission/#comments Mon, 14 Oct 2013 18:18:43 +0000 http://www.atcllc.com/?p=4066 Company seeks approval for 138-kV line in Menominee and Delta counties

DE PERE, Wis. – American Transmission Co. is asking Michigan regulators to approve a new 138-kV transmission line to improve reliability. 

The 60-mile line between the Holmes Substation in Menominee County and the Old Mead Road Substation near the NewPage mill in Escanaba is needed because of unique conditions of the electricity supply system in the area. “The transmission system is only marginally balanced,” said Brett French, ATC external relations manager. “Changes in demand or generation can significantly impact the reliability of the transmission system, creating difficulties when performing maintenance or managing unplanned outages. The project will greatly improve reliability of service to customers in the area.” 

ATC has developed a proposed and alternate route for the new line. The proposed route makes maximum use of co-location opportunities, placing the new facilities on existing transmission line or other rights-of-way. The western half of the proposed route would share a corridor with an existing transmission line; the eastern half would share an abandoned railroad corridor currently owned by the Michigan Department of Transportation and managed by the Department of Natural Resources. In exchange for sharing the corridor, ATC proposes to develop a 10-foot-wide multi-purpose recreational trail between Hermansville and Wells Township. 

The alternate route also follows established corridors, generally following an active railroad and U.S. Highway 2. 

Estimated cost of the project is between $105 million and $132 million. A more-refined estimate will be determined as detailed design of the line continues and a final route is selected.

“Filing the application moves the project into the approval process,” French said. “The Michigan Public Service Commission has one year to approve or deny the project. If approved, the PSC selects the route. It is very important for those interested in the project to participate in the commission’s process.”

To access the application and follow the regulatory review, visit the MPSC website http://efile.mpsc.state.mi.us/efile and search for Case # U-17272.

]]>
http://www.atcllc.com/whats-current/atc-files-application-with-michigan-public-service-commission/feed/ 0
American Transmission Co. releases annual 10-year plan http://www.atcllc.com/whats-current/american-transmission-co-releases-annual-10-year-plan/ http://www.atcllc.com/whats-current/american-transmission-co-releases-annual-10-year-plan/#comments Thu, 03 Oct 2013 18:25:28 +0000 http://www.atcllc.com/?p=4043 Regional planning demonstrates economic value of grid improvements

PEWAUKEE, Wis. – Noting that evolving energy markets and increased use of renewable energy are driving the need for electrical grid improvements, American Transmission Co. has announced plans to assure continued reliability in its recent 10-Year Transmission System Assessment.

“Future projects will address economic and public policy benefits, along with local and regional reliability,” said John Flynn, ATC’s executive vice president of strategic planning and project development. “Our 10-year plan calls for $3 billion to $3.6 billion in transmission system improvements.”

The expenditures include $1.2 billion in improvements and additions to the transmission network, $1.1 billion in maintenance and $0.5 billion in regional projects, the costs of which will be shared across the Upper Midwest. Other capital projects will range from $0.2 billion to $0.8 billion.

The report also notes that as regional planning efforts evolve and become more sophisticated, the economic benefits of transmission improvements become more evident. Easing congestion and providing access to sources of lower cost energy will help keep electricity prices in check. ATC estimates that, over the past three years, 99 percent of the cost of its transmission projects will be offset by savings in energy prices over the life of the projects.

The 10-Year Assessment, available online at www.ATC10YearPlan.com, lists more than 70 projects across the ATC service area.

]]>
http://www.atcllc.com/whats-current/american-transmission-co-releases-annual-10-year-plan/feed/ 0
ATC to rebuild transmission line in southeast Wisconsin, four-county region http://www.atcllc.com/whats-current/atc-to-rebuild-transmission-line-in-southeast-wisconsin-four-county-region/ http://www.atcllc.com/whats-current/atc-to-rebuild-transmission-line-in-southeast-wisconsin-four-county-region/#comments Mon, 19 Aug 2013 18:32:25 +0000 http://www.atcllc.com/?p=3958 Original line built in late 1940s       

Pewaukee, Wis. – American Transmission Co. has received approval from the Public Service Commission of Wisconsin to reconstruct an existing 53-mile, 138-kV transmission line through a four-county region in southeast Wisconsin. This rebuild will occur between the Waukesha Substation in the City of Waukesha, through Jefferson and Dodge Counties to the St. Lawrence Substation in the Village of Slinger in Washington County.

Known as the Quad County Reliability Project, this project will help maintain reliability of the electric transmission system. The existing transmission line was originally built in the late 1940s and this rebuild will allow the system to meet current and future electricity loads.

Work on the project includes replacing approximately 423 structures along the entire route. New electricity-carrying wires and fiber optic wires will be installed on 35 miles of the line; the remaining portions of the line will carry the existing conductors, which will be transferred from the old structures to the new ones. In some areas, new structures have already been replaced as part of a separate project needed to achieve required safety clearances between the wires and the ground.

Construction is expected to begin in fall 2014. The estimated cost of the project is $59 million and the targeted in-service date is 2017. Landowners along the right-of-way have been informed of the project and will continue to be kept apprised as the project proceeds. No new right-of-way is needed for this project, but ATC will work with landowners to access the right-of-way through their property if necessary.

 Additional information is available at www.atc-projects.com.

]]>
http://www.atcllc.com/whats-current/atc-to-rebuild-transmission-line-in-southeast-wisconsin-four-county-region/feed/ 0
Helicopter, air saw to be used for tree trimming http://www.atcllc.com/whats-current/helicopter-air-saw-to-be-used-for-tree-trimming-4/ http://www.atcllc.com/whats-current/helicopter-air-saw-to-be-used-for-tree-trimming-4/#comments Tue, 06 Aug 2013 18:50:05 +0000 http://www.atcllc.com/?p=3939 Ground access to transmission line corridor presents difficulties

A helicopter and heavy-duty air saw will be used to trim trees along a 20-mile transmission line corridor west of Stevens Point, Wis., this week.

“Difficult terrain and wetlands around the transmission line corridor make it very difficult to access with ground crews,” said Dan Horton, vegetation management specialist for American Transmission Co. “The helicopter and air saw allow trimming to be performed in a few hours; a ground-based crew might take several days to accomplish the same amount of work in difficult conditions.”

ATC has contracted with Aerial Solutions, Inc., a company that specializes in aerial tree management along transmission line corridors. The helicopters are equipped with a heavy-duty air saw with rotary blades suspended on a 90-foot vertical boom. In some areas, additional vegetation may be removed by ground crews.

Managing the growth of trees and other vegetation is key to helping ensure public safety and electric system reliability. ATC performs routine vegetation management on its 9,480 miles of transmission lines in five-year cycles.

]]>
http://www.atcllc.com/whats-current/helicopter-air-saw-to-be-used-for-tree-trimming-4/feed/ 0
New WIRES study first guide to all benefits of building transmission http://www.atcllc.com/whats-current/wires-new-study-is-first-guide-to-all-benefits-of-building-transmission/ http://www.atcllc.com/whats-current/wires-new-study-is-first-guide-to-all-benefits-of-building-transmission/#comments Tue, 30 Jul 2013 19:50:32 +0000 http://www.atcllc.com/?p=3898 economicImpact_220x220

A new study commissioned by WIRES and authored by economists at The Brattle Group finds that new high-voltage transmission investments offer numerous potential benefits that have too often been disregarded as remote, intangible or hard to estimate.

Read the WIRES news release or download the study.

 

]]>
http://www.atcllc.com/whats-current/wires-new-study-is-first-guide-to-all-benefits-of-building-transmission/feed/ 0
Borgard elected to ATC board of directors http://www.atcllc.com/whats-current/borgard-elected-to-atc-board-of-directors/ http://www.atcllc.com/whats-current/borgard-elected-to-atc-board-of-directors/#comments Fri, 28 Jun 2013 18:08:55 +0000 http://www.atcllc.com/?p=3783 PEWAUKEE, Wis. – Lawrence T. Borgard has joined the board of directors of American Transmission Co.

Borgard is the president and chief operating officer–utilities for Integrys Energy Group. He is responsible for the day-to-day operations of Integrys’ six regulated electric and natural gas utilities. Collectively, the subsidiaries serve 1.6 million natural gas customers and 500,000 electric customers across four Midwest states.

He began his career at Wisconsin Public Service Corp. as an engineer in 1984, rising to leadership positions in field operations, regulatory compliance, transmission and planning. More recently, he has held executive level positions at multiple Integrys subsidiaries.

A recent chairman of the board of the American Gas Association, Borgard also serves on the board of directors of Bellin Health in Green Bay, Wis., and was a recent campaign chairman for the United Way of Brown County. He also is an executive advisor and member of the board of governors of the Metropolitan Planning Commission in Chicago.

On the ATC board, Borgard replaces Charles Schrock, chairman, president and chief executive officer of Integrys Energy Group.

]]>
http://www.atcllc.com/whats-current/borgard-elected-to-atc-board-of-directors/feed/ 0
Eric Lundberg joins ATC Pewaukee headquarters http://www.atcllc.com/whats-current/eric-lundberg-joins-atc-pewaukee-headquarters/ http://www.atcllc.com/whats-current/eric-lundberg-joins-atc-pewaukee-headquarters/#comments Thu, 20 Jun 2013 19:41:52 +0000 http://www.atcllc.com/?p=3763 Will manage business development financial services

 PEWAUKEE, Wis. – American Transmission Co. is expanding its business development efforts across North America and has added Eric Lundberg to its staff to manage financial services.

 Lundberg comes to ATC from Agile Energy, a developer of utility-scale renewable and natural gas energy projects based in San Bruno, Calif., where he served as vice president of finance. He brings nearly 20 years of experience in the electric power industry, having performed financial modeling and analysis, risk assessment, forecasting and other financial duties at PacifiCorp and The AES Corporation. His international experience includes projects in Chile and Puerto Rico.

 A Certified Public Accountant, Lundberg holds a bachelor of science degree in accounting from Houghton College.

]]>
http://www.atcllc.com/whats-current/eric-lundberg-joins-atc-pewaukee-headquarters/feed/ 0
American Transmission Co. launches program to sponsor community planting http://www.atcllc.com/whats-current/american-transmission-co-launches-program-to-sponsor-community-planting/ http://www.atcllc.com/whats-current/american-transmission-co-launches-program-to-sponsor-community-planting/#comments Thu, 16 May 2013 16:18:19 +0000 http://www.atcllc.com/?p=3421 Program supports efforts to beautify communities

PEWAUKEE, Wis. – American Transmission Co. this month launched a planting program to support tree and vegetation planting in communities in its service area. Under the program, eligible cities, villages, towns, counties and tribes may apply for financial support for planting projects on public property within their community.

“As an owner and operator of the area electric transmission system, it is our responsibility to keep trees and brush out of the rights-of-way of our power lines for safety and reliability reasons,” said ATC Environmental and Local Relations Manager Greg Levesque. “While we can’t allow trees and brush in our rights-of-way, we do understand that they are an important part of the community landscape. This program helps us support efforts to beautify communities in a manner that is consistent with our safety and maintenance standards.” 

To qualify, communities must commit that all current and future planting plans and urban forestry activities near high-voltage electric transmission lines will comply with ATC’s maintenance standards. Priority will favor projects that promote safety and reliability of the transmission system by supporting right-of-way best management practices and keeping trees out of the right-of-way.

ATC will accept program applications June 1 through Sept. 30 each year, and recipients will be selected by the end of the calendar year. Awards will range from $100 to $5,000. 

Additional information, including a program brochure and eligibility information, is available on the ATC website: http://www.atcllc.com/learning-center/trees-and-vegetation/grow-smart-and-safely-in-your-community/.

]]>
http://www.atcllc.com/whats-current/american-transmission-co-launches-program-to-sponsor-community-planting/feed/ 0
ATC wins Environmental Innovation Award for Rockdale-West Middleton Project http://www.atcllc.com/whats-current/atc-wins-environmental-innovation-award-for-rockdale-west-middleton-project/ http://www.atcllc.com/whats-current/atc-wins-environmental-innovation-award-for-rockdale-west-middleton-project/#comments Thu, 16 May 2013 13:59:02 +0000 http://www.atcllc.com/?p=3430 Company honored at WMC’s Business Friend of the Environment Awards

PEWAUKEE, Wis. – American Transmission Co. on May 15 was recognized by Wisconsin Manufacturers & Commerce for environmental innovation on the Rockdale-West Middleton Transmission Line Project. The 32-mile, 345-kilovolt line provides an important transmission connection between eastern and western Dane County, Wis. The line was energized in early 2013.

ATC received the Environmental Innovation Award for its work designing and building transmission structures in the Yahara wetlands along the Beltline Highway in Madison, Wis. Award winners were selected by an independent panel of judges representing industry, the Department of Natural Resources, the University of Wisconsin and environmental groups.

“Placing structures in the wetlands required the team to address the challenges of accessing the wetland right-of-way and setting structures without causing significant or long-term environmental impacts,” said Environmental Project Manager Amy Lee. “To do this, the team undertook a multidisciplinary evaluation to consider foundation and structure design, construction methods, cost and environmental impacts.”

Construction access and timing
Crews used 2.8 acres of construction matting to access work areas at the edges of the marsh where ground was more stable and used low ground-pressure vehicles called marsh buggies to travel further into the marsh. Because of their wide tracks, these vehicles exert very low ground pressure, even less than a human foot.

Helicopters also were used on multiple occasions to move material and equipment to areas without mat roads. The project team carefully planned construction timing; completing work in the wetlands during the winter months and limiting construction timeframes to avoid spring and fall bird migration and spring fish spawning. Together, these methods eliminated the need for a mat road in the unstable portions of the marsh to provide access for traditional large cranes and heavy concrete trucks.

Foundation installation
ATC engineers and contractors designed and installed 16 helical pier foundations to hold the weight of the structures and have minimal impact on the Yahara wetlands.

“Helical pier foundations are much different from typical concrete foundations,” said Lee. “These hollow foundations screw into the ground and can be unscrewed in the event that they ever have to be decommissioned. They also required no excavation, generated no drilling spoils, and the portable installation equipment was moved with low-impact marsh buggies, barges and skids.” 

Setting structures and stringing wires
Heavy-lift helicopters allowed the team to set eight H-frame structures in less than a day, which is much faster than conventional methods. After structure setting was complete, a smaller helicopter was used to string pull rope and move insulators into permanent positions on the structures.

Protecting habitat for migrating and breeding birds
“To protect birds, we placed bird flight diverters in this area, along with three other locations along the route,” said Lee. “Bird flight diverters make shield wire more visible, increasing the likelihood that the birds will see the wire and adjust their flight pattern to avoid it. Using H-frame structures also allowed us to place wires in a horizontal configuration, which minimizes the obstacle for birds in flight.”

In addition to innovation in design and construction of the line, the project also achieved the following environmental milestones:

  • 30 waterways and 5.6 miles of wetlands crossed and only 0.054 acre of wetlands filled
  • 5 miles of mats used to preserve wetlands and protect agricultural lands
  • Excellent compliance, with no environmental violations or fines
  • More efficient line eliminates 34,000 to 140,000 metric tons of carbon emissions each year from coal plants not having to operate

“We are committed to environmental stewardship and innovation in all aspects of our business,” said Environmental and Local Relations Manager Greg Levesque. “This is evidenced by our participation in the Department of Natural Resource’s Green Tier program, Clean Corporate Citizen designation in Michigan, as well as the policies and actions that guide our construction projects.”

Additional project information, including a final route map and video of work in the Yahara wetlands, is available at www.RockdaleWestMiddleton.com.

]]>
http://www.atcllc.com/whats-current/atc-wins-environmental-innovation-award-for-rockdale-west-middleton-project/feed/ 0
Proposed and alternate routes announced for ATC transmission line http://www.atcllc.com/whats-current/proposed-and-alternate-routes-announced-for-atc-transmission-line/ http://www.atcllc.com/whats-current/proposed-and-alternate-routes-announced-for-atc-transmission-line/#comments Wed, 15 May 2013 18:00:40 +0000 http://www.atcllc.com/?p=3427 65-mile line would run through Menominee and Delta counties

DE PERE, Wis. – American Transmission Co. will present proposed and alternate route options for a new 138-kilovolt power line as part of its Bay Lake Project at an open house June 5, 2013. The line between the Holmes Substation in Menominee County and an Escanaba-area substation is needed to improve electric reliability in the area.

“The Bay Lake project has changed somewhat since we announced it last year,” said Brett French, external relations manager. “We originally proposed two lines from Holmes to the Escanaba area but, late last year, it was determined that only one line would be needed for the foreseeable future.”

That change required the project team to re-evaluate preliminary routes that had been presented to landowners and other interested parties last fall. During the last six months, route options were identified that maximized the opportunities to co-locate with existing transmission lines, thus minimizing the amount of new right-of-way required. The proposed routes maximize the use of existing transmission line corridors and an abandoned railroad corridor. If the project is approved, the final route will be selected by the Michigan Public Service Commission. An open house will be held:

Wednesday, June 5
Island Resort & Casino
W399 U.S. Highway 2
Harris, Mich.
1 to 7 p.m., EDT

No formal presentation is planned; interested parties are urged to drop in at their convenience.

Additional information, including maps and fact sheets, is available at www.BayLakeProject.com

]]>
http://www.atcllc.com/whats-current/proposed-and-alternate-routes-announced-for-atc-transmission-line/feed/ 0
ATC identifies proposed route options for Bay Lake Project http://www.atcllc.com/whats-current/atc-identifies-proposed-route-options-for-bay-lake-project/ http://www.atcllc.com/whats-current/atc-identifies-proposed-route-options-for-bay-lake-project/#comments Wed, 10 Apr 2013 19:58:56 +0000 http://www.atcllc.com/?p=3038 Lines would run from North Appleton Substation to Morgan Substation

DE PERE, Wis. – American Transmission Co. has identified proposed route options for transmission lines in Outagamie, Brown and Oconto counties.

The facilities, first announced as part of the Bay Lake Project in April 2012, are needed to address electric reliability concerns in northeastern Wisconsin and the Upper Peninsula of Michigan. Elements of the project proposed for northeastern Wisconsin include new substation facilities located at the site of the company’s North Appleton Substation on French Road in the Town of Freedom, and a 345,000-volt and a 138,000-volt line between the North Appleton and Morgan substations.

“Using feedback received from the public at open houses last year, along with computer modeling and other data and analysis, we have determined that the best location for the new substation facilities is at our North Appleton site,” explained David Hovde, ATC local relations consultant. “Similar information was used to identify route options for the transmission lines.”

Landowners whose property may be affected by the lines are being notified, and open houses are scheduled to talk with property owners and other interested parties about the proposals. Open houses will run from 1 to 7 p.m. on the following days and locations:

Wednesday, May 8                          Thursday, May 9
Oconto Falls Senior Center                 The Colonial House Supper Club
512 Caldwell Ave.                               N4330 County Road E      
Oconto Falls, Wis.                             Freedom, Wis.

ATC intends to file an application with the Public Service Commission of Wisconsin for the facilities in early 2014.

The Bay Lake Project also includes a new 138,000-volt line in Michigan, from the Holmes Substation in Menominee County to a substation in Escanaba. An open house for that project is scheduled for June. 

More project information, including an interactive map, is available on the project website, www.BayLakeProject.com, and a toll-free landowner hotline also has been established for the project: 855-831-5853.

]]>
http://www.atcllc.com/whats-current/atc-identifies-proposed-route-options-for-bay-lake-project/feed/ 0
Helicopter crews patrol ATC transmission lines http://www.atcllc.com/whats-current/helicopter-crews-patrol-atc-transmission-lines-3/ http://www.atcllc.com/whats-current/helicopter-crews-patrol-atc-transmission-lines-3/#comments Fri, 05 Apr 2013 19:05:49 +0000 http://www.atcllc.com/?p=3034 PEWAUKEE, Wis. – Helicopter crews began patrolling American Transmission Co. electric transmission lines this week to look for damage, right-of-way encroachments and vegetation issues.

ATC contracted the services of Chemair Helicopters of Jefferson, Wis., to patrol the transmission system, which covers portions of Wisconsin, Michigan, Minnesota and Illinois. The patrols are expected to be completed by the end of April, weather permitting.

Crews will inspect the lines by flying approximately 10 feet above the wires, and they will avoid flying over livestock where possible. Schedules may vary due to weather, but crews are expected to be in the following areas this month:

  • Early April: Southeast Wisconsin; Appleton and Green Bay areas
  • Mid-April: Central Wisconsin, southwest Wisconsin and Dane County
  • Late April: Northern Wisconsin and the Upper Peninsula of Michigan

ATC conducts helicopter patrols two or three times a year to detect potential problems that can be corrected to avoid unplanned power outages. Aerial inspections allow crews to reach secluded or difficult-to-reach lines and identify potential problems such as damaged lines or insulators, or tree limbs that could fall, damage equipment and cause power outages. Many of ATC’s 9,440 miles of transmission lines are located in relatively remote areas of Wisconsin and the Upper Peninsula of Michigan, and it is difficult and time consuming for crews to reach these areas by vehicle or on foot.

Note to editors: A map showing the locations ATC’s transmission facilities is available at www.atcllc.com.

]]>
http://www.atcllc.com/whats-current/helicopter-crews-patrol-atc-transmission-lines-3/feed/ 0
Lorenz named ATC human resources director http://www.atcllc.com/whats-current/lorenz-named-atc-human-resources-director/ http://www.atcllc.com/whats-current/lorenz-named-atc-human-resources-director/#comments Thu, 28 Mar 2013 14:50:20 +0000 http://www.atcllc.com/?p=2954 Will oversee recruitment, talent development, total rewards, payroll and safety

 PEWAUKEE, Wis. – Lori Lorenz has joined the leadership team at American Transmission Co. as director, human resources.

 Lorenz brings a wealth of human resources expertise to ATC; she most recently was vice president, human resources at Aurora Health Care in Milwaukee. Prior to that, she held leadership roles in human resources at Robert W. Baird & Co. While at Baird, the organization achieved Fortune’s “100 Best Companies to Work For” recognition for nine consecutive years.

 A UW-Whitewater graduate, Lorenz holds certifications as Senior Professional in Human Resources, Global Professional in Human Resources and Certified Compensation Professional. She is highly involved in various professional organizations and serves on the personnel committee of the Roger’s Memorial Hospital board of directors, on the steering committee of the Business Health Care Group and is a board member of Carmen High School of Science & Technology in Milwaukee. She volunteers with Junior Achievement, St. Anthony’s on the Lake Catholic Church and Arrowhead School District. Lorenz was recognized in 2008 as one of The Business Journal’s “Forty Under 40” list of young business and community leaders in the Milwaukee metro area.

]]>
http://www.atcllc.com/whats-current/lorenz-named-atc-human-resources-director/feed/ 0
PSC approves ATC’s Western Milwaukee County Electric Reliability Project http://www.atcllc.com/whats-current/psc-approves-atcs-western-milwaukee-county-electric-reliability-project/ http://www.atcllc.com/whats-current/psc-approves-atcs-western-milwaukee-county-electric-reliability-project/#comments Thu, 21 Mar 2013 15:10:14 +0000 http://www.atcllc.com/?p=2912 Project includes two new transmission lines

PEWAUKEE, Wis. – American Transmission Co. on Wednesday received a final written order from the Public Service Commission of Wisconsin authorizing construction of two new 138-kilovolt transmission lines needed to improve electric system reliability in western Milwaukee County.

The approved project involves construction of two transmission lines and a new substation planned by We Energies near Watertown Plank Road and 93rd Street, adjacent to the existing We Energies Milwaukee County power plant and substation. Approximately 90 percent of the ordered routes is on municipal or public property and less than 10 percent is on private or commercial property.

The new substation and transmission lines are needed to respond to the area’s growing electric needs and the critical nature of the Level 1 adult and pediatric trauma centers located within the Milwaukee Regional Medical Center complex. The medical center calls for a higher level of electric service reliability, one that includes a backup source for electricity in the event one of the two lines experiences an outage.

The project was announced to the public in October 2010. ATC held three open houses and company representatives attended more than 150 meetings to gather feedback and comments from area landowners, businesses, community organizations and local officials. ATC in February 2012 filed an application with the PSC to construct the project.  “We appreciate the efforts taken by the public to ensure their voices were heard by the Commission,” said Mary Carpenter, ATC local relations consultant. “We will continue to keep the public informed throughout the coming stages of the project.”

Construction of the line is planned to start in summer 2014, and the line is expected to be in service in spring 2015. The PSC-approved cost for ATC’s portion of the project is approximately $22.7 million.

Note to editors: A map and additional information about the project is available at www.atc-projects.com.

]]>
http://www.atcllc.com/whats-current/psc-approves-atcs-western-milwaukee-county-electric-reliability-project/feed/ 0
Rockdale-West Middleton Transmission Line Project placed in service http://www.atcllc.com/whats-current/rockdale-west-middleton-transmission-line-project-placed-in-service/ http://www.atcllc.com/whats-current/rockdale-west-middleton-transmission-line-project-placed-in-service/#comments Mon, 11 Mar 2013 18:06:44 +0000 http://www.atcllc.com/?p=2852 Line completed four months ahead of schedule and under budget

MADISON, Wis. —American Transmission Co. has energized the completed 32-mile, 345-kilovolt Rockdale-West Middleton Transmission Line.

The project was first introduced to the public in 2004, kicking off with a comprehensive outreach effort which included 22 public meetings attended by 3,300 people over three years. More than 2,600 written comments were submitted by stakeholders and included in the company’s application to the Public Service Commission of Wisconsin.

Much of the stakeholder input centered around environmental and visual impacts along the proposed routes. In 2009, after nearly two years of regulatory review, the PSC ordered a portion of the line to be built along the environmentally sensitive, highly visible and heavily travelled Beltline Highway in Madison, Wis.

Brian Fischer, Rockdale-West Middleton project manager, pointed to the company’s coordinated performance on multiple fronts during the past four years of planning, design and construction as evidence of the project’s success. “Our project team’s practice of collaboration and taking into account all factors—rather than considering each area or stage separately—resulted in unique solutions that saved time, money and minimized environmental impacts,” said Fischer.

  • Schedule: Construction and energization was completed four months ahead of schedule
  • Budget: Project came in 30 percent under the budget set by the Public Service Commission of Wisconsin
  • Construction innovation: Helicopter structure setting and helical pier foundations in the Yahara Wetlands
  • Maximizing right-of-way and minimizing aesthetic impacts: Used five different pole types and a variety of conductor configurations in order to “thread the needle” through a congested urban area
  • Collaboration: Worked with nine municipalities and 179 landowners—reaching easement agreements with 97 percent of the landowner
  • Protecting the environment:
  • 30 waterways and 5.6 miles of wetlands crossed and only 0.054 acre of wetlands lost
  • 5 miles of mats used to preserve wetlands and protect agricultural lands
  • Excellent compliance, with no environmental violations or fines
  • More efficient line eliminates 34,000 to 140,000 metric tons of carbon emissions each year from coal plants not having to operate

Fischer noted several other factors in the project’s success. “We received outstanding support from local officials, and state regulators worked with us in a cooperative manner to ensure that their concerns were addressed effectively. Madison Gas & Electric and Alliant Energy also gave us excellent support in coordinating and scheduling the electric system outages that were needed during construction.”

The line can carry 1,267 megawatts of electricity, enough to power 239,000 homes.

“I extend my sincere thanks to those involved with the project,” said Fischer. “We had many partners in this project, and all of them deserve credit for our success.” In addition to Madison Gas & Electric and Alliant Energy, several contractors worked on the project, including:

  • Construction: MJ Electric, Tri-State Drilling, Inc.
  • DOT Coordination: Ayres Associates
  • Engineering: Sargent & Lundy, GEI Consultants, Power Engineers
  • Environmental monitoring: Stantec
  • Helical pier foundations: Helical Pier Systems Ltd.
  • Helicopter: Air 2, LLC; Erickson Air-Crane, Inc.
  • Real estate: Land Service Company
  • Restoration/traffic signage: Q3 Contracting
  • Surveying: AECOM Technology Corporation
  • Vegetation management: Asplundh Tree Expert Co.

 Additional information, including final route map and a video of work in the Yahara Wetlands, is available at www.RockdaleWestMiddleton.com.

]]>
http://www.atcllc.com/whats-current/rockdale-west-middleton-transmission-line-project-placed-in-service/feed/ 0
ATC files application for Quad County Electric Reliability Project http://www.atcllc.com/whats-current/atc-files-application-for-quad-county-electric-reliability-project/ http://www.atcllc.com/whats-current/atc-files-application-for-quad-county-electric-reliability-project/#comments Thu, 28 Feb 2013 21:58:13 +0000 http://www.atcllc.com/?p=2819 Project involves rebuilding aging line in southeastern Wisconsin

PEWAUKEE, Wis. – American Transmission Co. is seeking approval from state regulators for a project to improve electric system reliability by rebuilding 58 miles of existing 138-kilovolt transmission lines in portions of four southeastern Wisconsin counties: Waukesha, Jefferson, Dodge and Washington.

ATC this week filed the required regulatory application for a Certificate of Authority with the Public Service Commission of Wisconsin. Permits also are needed from the Wisconsin Department of Natural Resources.

The reconstruction is needed to replace aging equipment that is approaching the end of its lifespan. The rebuilt line will help meet current and future electricity loads, and support the safe and reliable operation of the electric system.

Work on the project includes replacing the majority of the structures along the entire 58 mile route. No new right-of-way is needed. New conductors and fiber optic wires will be installed on 35 miles of the line; new structures on the remaining 23 miles will carry existing conductors, which will be transferred from the old structures to the new ones.

ATC anticipates regulatory approval in spring 2013 and the start of construction in fall 2014. The estimated cost of the project is $64 million and the targeted in-service date is spring 2017.

Additional information is available at www.atc-projects.com.

]]>
http://www.atcllc.com/whats-current/atc-files-application-for-quad-county-electric-reliability-project/feed/ 0
ATC announces changes to Bay Lake Project http://www.atcllc.com/whats-current/atc-announces-changes-to-bay-lake-project-1/ http://www.atcllc.com/whats-current/atc-announces-changes-to-bay-lake-project-1/#comments Thu, 07 Feb 2013 15:50:23 +0000 http://www.atcllc.com/?p=2769 Some work deferred in northern Wisconsin; scope scaled back in Michigan

DE PERE, Wis. – American Transmission Co. has modified the scope of its Bay Lake Project – a proposed collection of transmission lines and substations to enhance reliability in northeastern Wisconsin and the Upper Peninsula of Michigan.

“As we noted when announcing the project in spring 2012, there’s a delicate balance among transmission, generation and electric load in the region. Now, a year later, that balance continues to shift,” explained David Hovde, ATC’s local relations representative for the project. “The industry also is transitioning to more region-wide transmission planning, with the regional operator, MISO, playing a larger role. These issues have required further study; consequently, we are deferring some work in northern Wisconsin and making revisions to the project in Michigan.”

Specifically, work is being deferred on the proposed 345-kilovolt line between the Morgan Substation in Oconto County, Wis., and the Plains Substation near Quinnesec, Mich. MISO is undertaking a Northern Area Study, which is reviewing long-range transmission needs in Manitoba, North Dakota, South Dakota, Minnesota, Wisconsin and Michigan. 

Additionally, feedback from industry stakeholders and further analysis of evolving reliability standards indicates that a single-circuit 138-kV line between the Holmes Substation in Menominee County, Mich., and the Escanaba area will be adequate for the foreseeable future. This will require substantial review of the routing and siting work done last year to identify opportunities to co-locate the new circuit with existing 69-kV facilities. This also may bring additional stakeholders into the process. An open house to present two routes for the new line will be held in the area in June 2013.

No changes have been made to the proposal between the Green Bay area and the Morgan Substation. Open houses will be conducted in May 2013 to present the location of a new Green Bay-area substation and two routes for a 345-kV line and a 138-kV line.

Additional information is available at www.BayLakeProject.com

]]>
http://www.atcllc.com/whats-current/atc-announces-changes-to-bay-lake-project-1/feed/ 0
Myers named manager of business development at ATC http://www.atcllc.com/whats-current/myers-named-manager-of-business-development-at-atc-1/ http://www.atcllc.com/whats-current/myers-named-manager-of-business-development-at-atc-1/#comments Fri, 01 Feb 2013 16:34:35 +0000 http://www.atcllc.com/?p=2702 Niagara native has extensive energy policy experience

 PEWAUKEE, Wis. – Eric Myers has joined American Transmission Co. as manager of business development, working to expand electric transmission opportunities beyond ATC’s primary service territory in Wisconsin and Michigan.

 Myers most recently served as director of energy and environmental policy at Duke Energy in Charlotte, N.C., responsible for federal water and natural resources policies impacting the electric power industry. He also served as a senior analyst in the commercial fuels division of Cinergy, based in Cincinnati, as a member of the company’s leadership development program. Myers began his career in the utility industry at the Edison Electric Institute working in energy and environmental policy, and served as executive director of a coalition of telecommunications and energy companies. During college, he held consecutive summer internships in the Wisconsin legislature and the U.S. Congress.

 Myers earned a Bachelor of Science degree in political science and a Certificate in Environmental Studies from UW-Madison.  He holds an MBA from The George Washington University. He and his wife Sarah, who is a native of Elm Grove, will be relocating from North Carolina with their two children this summer.

 ###

 

]]>
http://www.atcllc.com/whats-current/myers-named-manager-of-business-development-at-atc-1/feed/ 0
American Transmission Co. recognized for environmental achievement http://www.atcllc.com/whats-current/american-transmission-co-recognized-for-environmental-achievement/ http://www.atcllc.com/whats-current/american-transmission-co-recognized-for-environmental-achievement/#comments Thu, 31 Jan 2013 22:57:43 +0000 http://www.atcllc.com/?p=2691 Michigan’s DEQ names ATC “Clean Corporate Citizen”

DE PERE, Wis. – The Michigan Department of Environmental Quality has recognized American Transmission Co.’s environmental stewardship activities with one of its highest honors, the Clean Corporate Citizen designation.

Known as “C3,” it is a voluntary program that recognizes environmental stewardship at Michigan facilities. Candidates demonstrate facility-specific environmental management systems, active pollution prevention initiatives, and a consistent record of compliance with state and federal environmental requirements.

“Achieving and maintaining superior environmental performance has always been a top priority for our company,” explained Greg Levesque, ATC’s environmental manager. “We are committed to environmental leadership throughout our business, as evidenced by our participation in the Wisconsin Department of Natural Resources Green Tier Program. It is only natural that we would adhere to the same standards with our work in Michigan.”

]]>
http://www.atcllc.com/whats-current/american-transmission-co-recognized-for-environmental-achievement/feed/ 0
ATC announces open houses for Spring Valley-North Lake Geneva Electric Reliability Project http://www.atcllc.com/whats-current/atc-announces-open-houses-for-spring-valley-north-lake-geneva-electric-reliability-project/ http://www.atcllc.com/whats-current/atc-announces-open-houses-for-spring-valley-north-lake-geneva-electric-reliability-project/#comments Tue, 15 Jan 2013 22:07:59 +0000 http://www.atcllc.com/?p=2640 New electric transmission line and substation proposed to improve electric reliability

PEWAUKEE, Wis. – American Transmission Co. is announcing the proposed Spring Valley-North Lake Geneva Electric Reliability Project with informational open houses in late January for residents and other stakeholders to review substation sites and potential routes for the proposed 25-mile, 138-kilovolt line from southern Walworth County to western Kenosha County. The new transmission line and substation are needed to improve electric system reliability in the area.

“This is the start of our public outreach on the proposed new electric infrastructure. The open house is an opportunity for area residents to learn about the project and review the various route options and substation sites currently under consideration,” said Mary Carpenter, local relations representative. “Public input and feedback helps us better evaluate the route options for challenges and sensitivities.” 

The electric transmission system in the area is vulnerable to low voltages and power outages and will no longer adequately support the lower-voltage distribution system. ATC studies indicate that the project would deliver benefits to the area by strengthening the electric transmission system to meet the growing use of electricity. This estimated $80.6 million project will provide system redundancy and allow for maintenance outages to equipment and facilities when repairs are needed.

ATC is hosting two open houses.

The public is invited to attend either of the following open houses any time between 3 p.m. and 7 p.m.:

  • Tuesday, Jan. 29, Hawks View Golf Club, 7377 Krueger Rd., Lake Geneva
  • Wednesday, Jan. 30, Christ Lutheran Church, 24929 75th St. (Hwy. 50), Paddock Lake

Following these open houses, ATC will narrow the potential route options and conduct additional open houses later this year before filing an application in 2014 with the Public Service Commission of Wisconsin for permission to build the power line and substation. If approved by the PSC, construction would begin in 2016 to meet an in-service date of 2019.

Note to editors: A map and additional information about the Spring Valley-North Lake Geneva Electric Reliability Project is available at www.atc-projects.com.

]]>
http://www.atcllc.com/whats-current/atc-announces-open-houses-for-spring-valley-north-lake-geneva-electric-reliability-project/feed/ 0
Drumm named associate general counsel at ATC http://www.atcllc.com/whats-current/drumm-named-associate-general-counsel-at-atc/ http://www.atcllc.com/whats-current/drumm-named-associate-general-counsel-at-atc/#comments Fri, 11 Jan 2013 16:44:49 +0000 http://www.atcllc.com/?p=2628 Will be responsible for federal energy regulatory matters

PEWAUKEE, Wis. – Brian Drumm has joined American Transmission Co. as associate general counsel. An attorney licensed to practice law in Wisconsin, Michigan and Washington, D.C., he will be responsible for corporate and policy issues before the Federal Energy Regulatory Commission.

Prior to joining ATC, Drumm worked as expert attorney at DTE Energy Co., Detroit, Mich., where he was the sole in-house counsel for federal energy regulatory affairs. DTE is the largest utility company in Michigan and one of the largest utility companies in the country. He joined DTE after 10 years working for law firms in Milwaukee, Wis., and the Washington, D.C. area.

“Brian’s experience with issues before the FERC will bring additional expertise to the ATC legal team as we address the myriad issues facing the transmission industry,” said Catherine Heigel, executive vice president, general counsel and corporate secretary of ATC.

Drumm received his bachelor’s degree in political science and pre-law from Michigan State University and his law degree from Indiana University School of Law (Bloomington).

]]>
http://www.atcllc.com/whats-current/drumm-named-associate-general-counsel-at-atc/feed/ 0
ATC begins construction on Pleasant Prairie-Zion Energy Center Project http://www.atcllc.com/whats-current/atc-begins-construction-on-pleasant-prairie-zion-energy-center-project/ http://www.atcllc.com/whats-current/atc-begins-construction-on-pleasant-prairie-zion-energy-center-project/#comments Fri, 04 Jan 2013 17:13:30 +0000 http://www.atcllc.com/?p=2618 Transmission line will provide multiple benefits to the area

PEWAUKEE, Wis. – American Transmission Co. later this month will begin construction activities on a new 5.8-mile, 345-kilovolt electric transmission line that will strengthen the electric system in southeastern Wisconsin and northeastern Illinois. ATC received approval last May from the Public Service Commission of Wisconsin and Illinois Commerce Commission to build the Pleasant Prairie-Zion Energy Center Transmission Line Project. The project also received approval from the Midwest Independent System Operator as a multi-value project for the economic benefits the line will provide to customers of local utilities.

The Pleasant Prairie-Zion Energy Center line establishes another important high-voltage interstate connection between Wisconsin and Illinois. The new line will relieve congestion on the existing transmission system in the area, allowing output from the most economic power plants in the region to supply electricity more of the time. 
 
“We are pleased to begin construction on this project,” said Mary Carpenter, ATC local relations representative. “We have been working on designing the line, developing construction access plans and obtaining the necessary easements and permits for construction.”

Construction activities beginning this month include vegetation removal and laying construction mats in some areas. In February crews will begin erecting steel poles and stringing wires beginning on the north end of the project in Pleasant Prairie and moving to the south to the Zion Energy Center. 

The line will largely follow the existing railroad right-of-way between the two end points. The project, estimated at $31 million, is anticipated to be completed and in service by August 2013.

Note to editors: A map and additional information about the project is available at www.atc-projects.com.

]]>
http://www.atcllc.com/whats-current/atc-begins-construction-on-pleasant-prairie-zion-energy-center-project/feed/ 0
PSC approves ATC’s Monroe County-Council Creek Project http://www.atcllc.com/whats-current/psc-approves-atcs-monroe-county-council-creek-project/ http://www.atcllc.com/whats-current/psc-approves-atcs-monroe-county-council-creek-project/#comments Wed, 28 Nov 2012 19:56:33 +0000 http://www.atcllc.com/?p=2581 Plan includes new substation, rebuilding existing transmission line between Sparta and Tomah areas

MADISON, Wis. – American Transmission Co. on Tuesday received approval from the Public Service Commission of Wisconsin to build the new Timberwolf Substation in the Town of Tomah and upgrade an approximately 17-mile, 161- and 69-kilovolt electric transmission line from the Monroe County Substation in the Town of Sparta to the Council Creek Substation in the City of Tomah.  

 “The current transmission system that serves the area is aging and susceptible to overloads and severe low voltages,” said ATC Project Manager Andy Schaeve. “Rebuilding the 69-kV line and adding a new 161-kV line will help strengthen electric reliability for the area. The new line also will provide economic savings by reducing line losses and increasing access to lower cost power.”

The project involves replacing the structures and wires of the existing 69-kV transmission line and adding a 161-kV circuit to the new steel structures. Transmission line work will generally be completed within the existing right-of-way area. To allow for flexibility on the 69-kV system, ATC also will build the new Timberwolf Substation approximately 1/2 mile south of Interstate 90 along Highway 131.

ATC in July 2010 filed an application with the PSC to construct the project. The estimated project cost is $48 million. The line is expected to be in-service in late 2014.

Note to editors: A map and additional information about the project is available at www.atc-projects.com.

]]>
http://www.atcllc.com/whats-current/psc-approves-atcs-monroe-county-council-creek-project/feed/ 0
ATC withdraws Barnhart-Branch River project filing at PSC http://www.atcllc.com/news/atc-withdraws-barnhart-branch-river-project-filing-at-psc/ http://www.atcllc.com/news/atc-withdraws-barnhart-branch-river-project-filing-at-psc/#comments Tue, 30 Oct 2012 14:19:35 +0000 http://www.atcllc.com/?p=2465 Project affected by announcement of Kewaunee Power Station closing

 PEWAUKEE, Wis. – The announcement by Dominion Resources Inc. that the Kewaunee Power Station would close in spring 2013 is affecting plans for a proposed transmission line reinforcement project in eastern Wisconsin.

 “Our Barnhart-Branch River project was proposed, in part, to address transmission system limitations in Calumet, Manitowoc and Sheboygan counties,” explained Ron Snead, director of planning for American Transmission Co. The transmission limitations resulted in operating restrictions on both the Point Beach and Kewaunee nuclear generators.

 ATC introduced the project to the public in 2010 and recently filed an application for approval with the Public Service Commission of Wisconsin. “Given the significant impact the Kewaunee plant closing will have on the balance between electric demand, generation and transmission in eastern Wisconsin, we have decided to withdraw the application at this time,” said Snead.

 Preliminary analysis shows that the closure of the Kewaunee Power Station would alleviate some, but not all, of the issues addressed by ATC’s Barnhart-Branch River project. ATC’s planning staff will conduct additional analysis regarding transmission system reinforcements to determine specific solutions to support full operation of the Point Beach plant.

 MISO, the regional transmission operator, also will undertake a power grid reliability review prior to the plant’s closure.

]]>
http://www.atcllc.com/news/atc-withdraws-barnhart-branch-river-project-filing-at-psc/feed/ 0
ATC files application for Barnhart-Branch River project http://www.atcllc.com/news/atc-files-application-for-barnhart-branch-river-project/ http://www.atcllc.com/news/atc-files-application-for-barnhart-branch-river-project/#comments Wed, 17 Oct 2012 14:53:30 +0000 http://www.atcllc.com/?p=2438 New facilities would strengthen electric grid in eastern Wisconsin

PEWAUKEE, Wis. – American Transmission Co. is seeking approval from state regulators for a project to improve electric system reliability by reconfiguring the 345-kilovolt transmission grid in eastern Wisconsin.

A regulatory application for the proposed Barnhart-Branch River project, which includes two new substations and a new 345-kV transmission line, has been filed with the Public Service Commission of Wisconsin. Permits also are needed from the Wisconsin Department of Natural Resources.

ATC’s preferred alternative is to convert approximately 51 miles of 345-/138-kV double-circuit line in Calumet, Manitowoc and Sheboygan counties to a double-circuit 345-kV line. This alternative would require a new, approximately 18-mile 138-kV line in Sheboygan County to replace the current 138-kV facilities. The other alternative would be to build a new, 40-mile 345-kV line that essentially follows the Interstate 43 corridor in Manitowoc and Sheboygan counties. The preferred alternative maximizes the use of existing ATC facilities while minimizing new right-of-way requirements, associated environmental impacts and project cost. Estimated costs of the project range from $193 million to $262 million, depending on the project alternative, route and substation sites ordered by the PSC.

Additional information is available at www.atc-projects.com

]]>
http://www.atcllc.com/news/atc-files-application-for-barnhart-branch-river-project/feed/ 0
Helicopter crews patrol ATC transmission lines http://www.atcllc.com/whats-current/2430/ http://www.atcllc.com/whats-current/2430/#comments Mon, 15 Oct 2012 19:44:03 +0000 http://www.atcllc.com/?p=2430 Inspection of lines during next four weeks will help prevent outages

PEWAUKEE, Wis. – American Transmission Co. is using helicopter crews to inspect its electric transmission system across four states through mid-November.

The crews, using Bell 206B Jet Ranger helicopters, are looking for equipment damage, right-of-way encroachments and vegetation issues throughout the system, which spans portions of Wisconsin, Michigan, Minnesota and Illinois. Identifying these issues can prevent future unplanned outages. The helicopters fly directly adjacent to and above the lines at a distance of approximately 25 feet and avoid flying over livestock where possible.

ATC crews have begun helicopter inspections in the northwest portion of the company’s system, starting in northern Wisconsin and the Upper Peninsula of Michigan, and will continue in a southwesterly direction through the service area during the next few weeks.

ATC inspects its 9,440 miles of transmission lines by helicopter two to three times a year to identify potential problems and reach the more secluded locales in the company’s service area that are difficult to access by land.

ATC is utilizing the services of Chemair Helicopters of Jefferson, Wis., for the inspections. The effort is expected to conclude before the annual opening of gun deer hunting season, as well as before the transition of fall to winter weather.

Note to editors: A map of ATC’s service area is available at www.atcllc.com.

]]>
http://www.atcllc.com/whats-current/2430/feed/ 0
ATC and Xcel Energy announce public open houses for Badger Coulee Transmission Line Project http://www.atcllc.com/whats-current/atc-and-xcel-energy-announce-public-open-houses-for-badger-coulee-transmission-line-project/ http://www.atcllc.com/whats-current/atc-and-xcel-energy-announce-public-open-houses-for-badger-coulee-transmission-line-project/#comments Fri, 05 Oct 2012 19:15:40 +0000 http://www.atcllc.com/?p=2411 Kaya Freiman
American Transmission Co.              
877-506-6117
kfreiman@atcllc.com

Brian Elwood  
Xcel Energy   
715-737-2565
brian.t.elwood@xcelenergy.com
       

Five public open houses will be held in October

MADISON, Wis. – American Transmission Co. and Xcel Energy are continuing a multi-year public outreach process for the proposed Badger Coulee Transmission Line Project with the fourth in a series of public open houses presenting route options for the proposed 150- to 170-mile, 345-kilovolt line from north of the La Crosse area to northern Dane County.

Studies indicate that the project would deliver benefits toWisconsinand the Midwest region by improving electric system reliability, delivering economic benefits forWisconsinutilities and electricity consumers, and expanding infrastructure to support greater use of renewable energy. If the project is approved by the Public Service Commission of Wisconsin, the final project length and cost will be determined after a route is selected by the PSC.

ATC and Xcel Energy are hosting five informational open houses. There will be no formal presentation. The open house format allows attendees to drop in at any time and discuss many aspects of the project with ATC and Xcel Energy staff. There will be representatives from a variety of areas, including transmission planning, engineering, real estate, environmental, and construction.   

The public is invited to attend any of the following open houses. Open houses at all locations will be held from 1 to 7 p.m.

Oct. 23, Stoney Creek Inn andConferenceCenter, Onalaska
Oct. 24, Cashton Community Hall, Cashton
Oct. 25, Best Western Arrowhead Lodge & Suites, Black River Falls
Oct. 29, Anjero’s Sports Bar/Grill and Banquet Facility, Mauston
Oct. 30, WaunakeeVillageCenter, Waunakee

ATC and Xcel Energy plan to submit two routes to the PSC in early 2013. If the project is approved, the PSC will select one final route to be built.

Note to editors: A map and additional information about the project is available at www.BadgerCoulee.com.

###

About the Badger Coulee project
The Badger Coulee project was announced to the public in July 2010. The Federal Energy Regulatory Commission in July 2012 interpreted a MISO regional transmission owners agreement to require equal ownership of the proposed Badger Coulee project. ATC and Xcel Energy are currently jointly developing the project pending FERC action on ATC’s request for FERC to reconsider the July 2012 order.   

About Xcel Energy
Xcel Energy is a major U.S. electricity and natural gas company, with retail operations in eight Western and Midwestern states, including Wisconsin. Xcel Energy provides a comprehensive portfolio of energy-related products and services to 3.4 million electricity customers and 1.9 million natural gas customers through its regulated operating companies. Company headquarters are located in Minneapolis, and Wisconsin-Michigan operating company headquarters are located in Eau Claire, Wisconsin. For more information about Xcel Energy visit www.xcelenergy.com.

]]>
http://www.atcllc.com/whats-current/atc-and-xcel-energy-announce-public-open-houses-for-badger-coulee-transmission-line-project/feed/ 0
American Transmission Co. announces future investment http://www.atcllc.com/news/american-transmission-co-announces-future-investment/ http://www.atcllc.com/news/american-transmission-co-announces-future-investment/#comments Wed, 03 Oct 2012 19:38:23 +0000 http://www.atcllc.com/?p=2401 Planning assessment calls for $3.9 – $4.8 billion in investment through 2021

 PEWAUKEE, Wis. – American Transmission Co. has developed plans to ensure future regional electric system reliability and access to economic energy over the next decade in its recently released 10-Year Transmission System Assessment.

 “The industry and its stakeholders continue to make progress in planning for transmission solutions that address regional reliability and economic needs,” explained Ron Snead, ATC’s director of system planning. “Our 10-year forecast calls for improvements and maintenance to our network, as well as projects that will strengthen the regional grid.” 

 The bulk of the expenditures includes nearly $2 billion in improvements and additions to ATC’s electric system; $1.1 billion in maintenance; and $0.8 billion in regional projects, the costs of which will be shared across the Upper Midwest.

 MISO, the regional transmission planning authority, late last year approved its first portfolio of projects whose costs will be shared among a broad base of electricity customers. Three of these Multi-Value Projects fall within ATC’s service territory: the Badger Coulee project from the La Crosse area to Madison in Wisconsin; the Pleasant Prairie-Zion Energy Center project, a five-mile link between Kenosha County, Wis. and northern Illinois; and the Cardinal Bluffs project from Madison, Wis., to Dubuque County, Iowa.

 The 10-Year Assessment, available online at www.ATC10YearPlan.com, also notes that new technologies will increasingly play a role in improving system operators’ ability to control the grid and integrate renewable resources. The summary report lists more than 70 projects across ATC’s service territory.

]]>
http://www.atcllc.com/news/american-transmission-co-announces-future-investment/feed/ 0
American Transmission Co., Minnesota Power enter into partnership agreement http://www.atcllc.com/news/test-post/ http://www.atcllc.com/news/test-post/#comments Thu, 09 Feb 2012 16:47:11 +0000 http://www.atcllc.com/?p=1568 Companies will jointly develop transmission to move renewable power, enhance electric system reliability in Midwestern U.S.

Pewaukee, Wis. – American Transmission Co. and Minnesota Power, a utility division of ALLETE (NYSE: ALE), have entered into a partnership agreement to study transmission development options to move Midwestern wind energy as well as Canadian hydroelectric power into Minnesota, Wisconsin and Michigan to help local utilities enhance reliability and meet renewable energy goals.

Separately, Minnesota Power plans to enhance its transmission infrastructure fromWinnipegtoMinnesota’sMesabiIronRange. Minnesota Power recently signed a 15-year agreement to purchase 250 megawatts of hydroelectricity from Manitoba Hydro’s proposed 695-MW Keeyask Hydroelectric Plant in Northern Manitoba.

To further facilitate movement of this renewable energy, ATC and Minnesota Power are partnering to develop a proposed 50-mile, double-circuit 345-kilovolt transmission line from theMesabiIronRangeto the companies’ jointly owned Arrowhead Substation inDuluth,Minn., for service in approximately 2020. In addition, the partners are studying transmission options to strengthen regional electric system reliability and move clean energy from the Arrowhead Substation inDuluthintoWisconsinandMichigan. Total project cost, ownership shares and cost allocation still are to be determined.

John Flynn, ATC vice president of Strategic Planning and Business Development, said, “The transmission grid does not end at state lines or national borders. Strategic connections between clean energy generation and load centers within a given region can deliver the greatest reliability, economic and public policy benefits for utilities and electric consumers.”

ALLETE Chairman, President and CEO Alan R. Hodnik, said, “Transmission development is the vital link in connecting these abundant Canadian renewable energy resources to the Midwestern United States. We look forward to working with ATC on identifying and developing cost-effective solutions for the safe and reliable delivery of this power to Minnesota Power customers as well as other utilities in the region.”

ATC and Minnesota Power worked together on the 220-mile, 345-kV Arrowhead-Weston transmission line from Duluth, Minn., to Wausau, Wis., which was placed in service in 2008.

]]>
http://www.atcllc.com/news/test-post/feed/ 0
ATC names two new board members http://www.atcllc.com/news/atc-names-two-new-board-members/ http://www.atcllc.com/news/atc-names-two-new-board-members/#comments Fri, 08 Jul 2011 08:00:37 +0000 http://www.atcllc.com/news-releases/atc-names-two-new-board-members/ PEWAUKEE, Wis. – Two new members have been elected to the board of directors of American Transmission Co., Patricia Kampling and Alan Schriber.

Kampling is president and chief operating officer of Alliant Energy. She joined Alliant as vice president of finance in 2005, after an extensive career with Exelon. She holds bachelor of arts degrees in economics and mechanical engineering from Swarthmore College, and a master of business administration degree in finance from the University of Chicago. Currently, she also serves as a member of the board of directors for Briggs & Stratton Corp. in Milwaukee.

Schriber is a former college professor, broadcasting executive and public utilities commissioner. He most recently was chair of the Ohio Public Utilities Commission, where he also chaired the Ohio Power Siting Board. He holds a Ph.D. in economics from Indiana University and a master’s degree in economics from Miami University. He also serves on the National Governors’ Association Electricity Task Force and the State of Ohio Security Task Force.

]]>
http://www.atcllc.com/news/atc-names-two-new-board-members/feed/ 0
ATC announces second round of open houses for Badger Coulee Transmission Line Project http://www.atcllc.com/news/american-transmission-co-announces-second-round-of-open-houses-for-badger-coulee-transmission-line-project/ http://www.atcllc.com/news/american-transmission-co-announces-second-round-of-open-houses-for-badger-coulee-transmission-line-project/#comments Thu, 02 Jun 2011 08:00:00 +0000 http://www.atcllc.com/?p=1152 Public encouraged to provide input on potential corridors at eight informational open houses to be held in June throughout the project study area

MADISON, Wis. – American Transmission Co. is continuing a multi-year public outreach process for the proposed Badger Coulee Transmission Line Project with the second in a series of informational open houses in late June for residents and other stakeholders to review potential corridors for the proposed 150-mile, 345-kilovolt line from north of La Crosse to northern Dane County.

“As a result of further study and stakeholder comments, we have identified potential corridors that may be suitable for a new transmission line and will continue to be examined,” said ATC Local Relations Manager Sarah Justus.

Studies indicate that the approximately $425 million project would deliver benefits to Wisconsin and the Midwest region by improving electric system reliability, delivering economic benefits for Wisconsin utilities and electric consumers, and expanding infrastructure to support greater use of renewable energy.

“Since the fall 2010 open houses, ATC has expanded its original study area north of La Crosse to provide the flexibility that may be needed to connect to the CapX2020 Hampton-Rochester-La Crosse transmission line project as currently proposed,” said ATC Major Projects Siting Consultant Pete Holtz. “We have identified five potential new substation areas where the Badger Coulee Transmission Line Project could make a single connection to the CapX2020 project north of La Crosse.”

ATC is hosting eight open houses throughout the project study area to gather feedback on potential corridors and provide stakeholders with more information about the project.

The public is invited to attend any of the following open houses:

  • June 20, Stoney Creek Inn and Conference Center, Onalaska
  • June 21, Club 16, Sparta
  • June 22, Cashton Community Hall, Cashton
  • June 23, Wilderness Glacier Canyon Conference Center, Wisconsin Dells
  • June 27, Ettrick Community Center, Ettrick
  • June 28, Three Bears Lodge, Warrens
  • June 29, Mauston Grayside Elementary, Mauston
  • June 30, Waunakee Middle School, Waunakee

Open houses at all locations run from 1 to 7 p.m.

ATC will hold two more rounds of open houses over the next two years to gather public input and narrow potential routes before filing an application to build the line with the Public Service Commission of Wisconsin, anticipated in 2013. If approved by the PSC, construction of the new line would begin in 2016 to meet an in-service date of 2018.

“We invite everyone who could be affected by the project to attend an open house and get involved,” said Justus.

Note to editors: A map and additional information about the Badger Coulee Transmission Line Project is available at www.BadgerCoulee.com.

]]>
http://www.atcllc.com/news/american-transmission-co-announces-second-round-of-open-houses-for-badger-coulee-transmission-line-project/feed/ 0
ATC proposes power line for Escanaba area http://www.atcllc.com/news/american-transmission-co-proposes-power-line-for-escanaba-area/ http://www.atcllc.com/news/american-transmission-co-proposes-power-line-for-escanaba-area/#comments Tue, 31 May 2011 08:00:12 +0000 http://www.atcllc.com/?p=1150 Six-mile line would improve electric reliability, alleviate problems on current system

DE PERE, Wis. – Local residents and officials are invited to attend an informational open house to learn about an electric reliability project for the Escanaba area proposed by American Transmission Co.

“The transmission system that currently serves the Escanaba area is frequently overloaded and the lines are so critical that it is difficult to take components out of service for maintenance,” explains David Hovde, ATC local relations consultant. “We are proposing a new line and substation to improve reliability for the area.”

The project is in its early stages – no potential routes or substation locations have been determined. ATC has identified a study area within which to locate the facilities. The open house is designed to gather feedback from the local community to help make those decisions.

The open house will be from 2 to 7 p.m. on Tuesday, June 7, at Bay College in rooms JHUC 958 and 962. No formal presentation is planned; guests should drop in as their schedules allow. Company representatives will be available to discuss planning, routing, siting, design, construction and real estate issues.

A map of the study area and more information about the project, known as the Chandler-18th Road Electric Reliability Project, is available at www.atc-projects.com.

]]>
http://www.atcllc.com/news/american-transmission-co-proposes-power-line-for-escanaba-area/feed/ 0
Duke Energy and American Transmission Co. Form Joint Venture to Build Transmission in North America http://www.atcllc.com/news/duke-energy-and-american-transmission-co-form-joint-venture-to-build-transmission-in-north-america/ http://www.atcllc.com/news/duke-energy-and-american-transmission-co-form-joint-venture-to-build-transmission-in-north-america/#comments Wed, 13 Apr 2011 08:00:10 +0000 http://www.atcllc.com/?p=1148 CHARLOTTE, N.C. – Duke Energy and American Transmission Co. announced the creation of Duke-American Transmission Co., a joint venture that will build, own and operate new electric transmission infrastructure in North America.

The companies believe Duke-American Transmission Co. (DATC) is well-positioned to help address increasing demand for affordable, reliable transmission capacity in the United States and Canada. DATC has begun identifying opportunities to build, own and operate new transmission projects that meet potential customers’ capacity and voltage requirements.

DATC will own all of the transmission assets it builds and operates. Equity ownership of DATC will be split equally between Duke Energy and ATC.

The joint venture will operate as a transmission utility. As a result, it will be subject to the rules and regulations of the Federal Energy Regulatory Commission, MISO, PJM and various other independent system (grid) operators, as well as any states in which DATC develops projects. Per the structure of their new joint venture, Duke Energy and ATC may continue to develop transmission projects independently.

“Thoughtful, well-designed transmission projects afford customers, regulators and other key stakeholders superior flexibility as they determine which energy resources can help meet demand for electricity in the decades to come,” said Duke Energy Commercial Businesses Senior Vice President Phil Grigsby. “Duke Energy and ATC share the belief that sound transmission infrastructure can serve as a springboard for next-generation energy technologies.”

“This joint venture is an important step in advancing ATC’s strategy to grow outside our current service area,” said John Flynn, ATC vice president of Strategic Planning and Business Development. “We have been very successful in planning, permitting and building transmission in the Midwest. Through our partnership with Duke Energy, we will take our expertise to other parts of North America to develop transmission solutions that not only deliver reliable electricity, but also economic and public policy benefits.”

]]>
http://www.atcllc.com/news/duke-energy-and-american-transmission-co-form-joint-venture-to-build-transmission-in-north-america/feed/ 0
Helicopter crews patrol ATC transmission lines http://www.atcllc.com/news/helicopter-crews-patrol-atc-transmission-lines/ http://www.atcllc.com/news/helicopter-crews-patrol-atc-transmission-lines/#comments Tue, 05 Apr 2011 08:00:16 +0000 http://www.atcllc.com/?p=1146 PEWAUKEE, Wis. – Helicopter crews began patrolling American Transmission Co. electric transmission lines last week to look for damage, right-of-way encroachments and vegetation issues.

ATC contracted the services of Chemair Helicopters of Jefferson, Wis. Crews began patrolling the transmission system, which covers portions of Wisconsin, Michigan, Minnesota and Illinois, in Bell 206B Jet Ranger helicopters late March and are expected to continue through late April, weather permitting.

ATC conducts helicopter patrols two or three times a year to detect potential problems that can be corrected to avoid unplanned power outages. Aerial inspections allow crews to reach secluded or difficult-to-reach lines and identify potential problems such as damaged lines or insulators, or tree limbs that could fall, damage equipment and cause power outages. Many of ATC’s 9,440 miles of transmission lines are located in relatively remote areas of Wisconsin and the Upper Peninsula of Michigan, and it is difficult and time consuming for crews to reach these areas by vehicle or on foot.

Crews will inspect the lines by flying approximately 10 feet above the wires, and they will avoid flying over livestock where possible. Schedule may vary due to weather.

Note to editors: A map showing the locations ATC’s transmission facilities is available at www.atcllc.com.

]]>
http://www.atcllc.com/news/helicopter-crews-patrol-atc-transmission-lines/feed/ 0
ATC to discuss routes for proposed transmission line in Southeastern Wisconsin, Northeastern Illinois http://www.atcllc.com/news/atc-to-discuss-routes-for-proposed-transmission-line-in-southeastern-wisconsin-northeastern-illinois/ http://www.atcllc.com/news/atc-to-discuss-routes-for-proposed-transmission-line-in-southeastern-wisconsin-northeastern-illinois/#comments Wed, 23 Mar 2011 08:00:29 +0000 http://www.atcllc.com/?p=1143 Open house scheduled for April 6 at Pleasant Prairie LakeView RecPlex

PEWAUKEE, Wis. – An informational open house on Wednesday, April 6, will provide area landowners and members of the public an opportunity to comment on American Transmission Co.’s proposal for a new 345,000-volt transmission line to be built from Pleasant Prairie, Wis., to Zion, Ill.

“The project would improve electric system performance in the region and deliver economic savings for Wisconsin utilities and their electric consumers,” said Mary Carpenter, local relations representative for ATC.

ATC staff will be on hand at the LakeView RecPlex between 4 p.m. and 7 p.m. on Wednesday, April 6, to discuss with stakeholders the plans, including routes being considered for the transmission line.

“Because the distance between the Pleasant Prairie Substation and the Zion Energy Center is less than 6 miles, there are a limited number of corridors that would be suitable for a 345-kV transmission line,” said Carpenter.

ATC will continue public outreach before filing applications to build the line with the Public Service Commission of Wisconsin and the Illinois Commerce Commission in late 2011. If approved by the PSCW and ICC, construction of the new line would begin in 2013 to meet an in-service date of 2014.

Note to editors: A map and additional information on the project is available at www.atcprojects.com.

]]>
http://www.atcllc.com/news/atc-to-discuss-routes-for-proposed-transmission-line-in-southeastern-wisconsin-northeastern-illinois/feed/ 0
American Transmission Co. to discuss preliminary routes for proposed transmission lines to reinforce western Milwaukee County electric system http://www.atcllc.com/news/american-transmission-co-to-discuss-preliminary-routes-for-proposed-transmission-lines-to-reinforce-western-milwaukee-county-electric-system/ http://www.atcllc.com/news/american-transmission-co-to-discuss-preliminary-routes-for-proposed-transmission-lines-to-reinforce-western-milwaukee-county-electric-system/#comments Mon, 28 Feb 2011 08:00:48 +0000 http://www.atcllc.com/?p=1138 Open house will be March 10, 4-7 p.m. at the Wauwatosa Civic Center

PEWAUKEE, Wis. – American Transmission Co. will host a second open house on Thursday, March 10, at the Wauwatosa Civic Center to provide the public an opportunity to comment on preliminary route options for a proposed 138,000-volt transmission line to be located primarily in Wauwatosa. The project, announced in October 2010, involves the construction of a new We Energies substation adjacent to the existing Milwaukee County Substation and two transmission line connections to serve the new substation.

“Planning forecasts developed by We Energies’ show that additional power with a high level of reliability afforded by two connections to the area transmission grid is needed to serve local customers,” explains Mary Carpenter, local relations representative for ATC. “That is why we are proposing to build two transmission lines, each approximately two miles long, to connect to the new substation.”

Planning studies indicate that electric demand in the U.S. Highway 45 corridor in western Milwaukee County is expected to double as soon as 2016, and existing distribution substations and feeders that serve the area will not be adequate to meet anticipated future electric demand. “The new substation is needed to respond to the area’s growing electric needs,” says Andrew Gumm, We Energies manager of project siting. “In addition, the critical nature of the Level 1 adult and Level 1 pediatric trauma centers located within the Milwaukee Regional Medical Complex calls for a higher level of electric service reliability, one that includes a reserve source for electricity in the form of a second line in event that an alternate source is needed.”

ATC and We Energies staff will be on hand at the Wauwatosa Civic Center between 4 p.m. and 7 p.m. to discuss with stakeholders the plans, including preliminary route options being considered for the transmission lines.

“Since the first open house for the project last October, we have received valuable input from the public that, along with constructability and engineering considerations, has been used to evaluate potential corridors for the route,” says Carpenter. “We encourage the public to continue to provide us with feedback on the preliminary route options at this second of three open houses.”

ATC mailed open house invitations to potentially affected landowners and businesses. During the next year, ATC will narrow the preliminary route options to two before filing an application to build the lines with the Public Service Commission of Wisconsin in early 2012. If approved by the PSC, construction of the new line would begin in 2014 to meet an in-service date of 2015.

Note to editors: A map and additional information on the project is available at www.atcprojects.com.

]]>
http://www.atcllc.com/news/american-transmission-co-to-discuss-preliminary-routes-for-proposed-transmission-lines-to-reinforce-western-milwaukee-county-electric-system/feed/ 0
ATC announces Barnhart-Branch River transmission project in area http://www.atcllc.com/news/atc-announces-barnhart-branch-river-transmission-project-in-area/ http://www.atcllc.com/news/atc-announces-barnhart-branch-river-transmission-project-in-area/#comments Mon, 07 Feb 2011 08:00:31 +0000 http://www.atcllc.com/?p=1140 Informational open houses scheduled in Plymouth, New Holstein & Brillion

DE PERE, Wis. – A project to reinforce the high-voltage electric transmission system in eastern Wisconsin will be introduced to local area residents at open houses in February.

American Transmission Co. is proposing to reinforce the 345-kilovolt grid in the region in response to changes being made at the Point Beach Nuclear Plant that include an increase in generating capacity. The 345-kilovolt, or 345-kV, system is the backbone of ATC’s network, used to transfer large amounts of electricity across long distances.

“The Barnhart-Branch River project will involve two new substations in Manitowoc and Sheboygan counties,” said David Hovde, local relations consultant for ATC. “In addition, we will need to either upgrade and replace some existing transmission lines in the area, or build a new, high-voltage line to connect the new substations. We are in the early stages in developing this project and look forward to talking with local residents and officials about our plans.”

Open houses are scheduled for:

  • Tuesday, Feb. 22 at Cobblestone Creek Dining & Banquet Hall in Brillion,
  • Wednesday, Feb. 23 at Altona Supper Club in New Holstein and
  • Thursday, Feb. 24 at Amore in Plymouth.

All open houses will run from 1 to 7 p.m. No formal presentation is planned; interested parties should drop in as their schedule allows.

Note to editors: more information, including a project-area map, is available at our website: www.atcprojects.com

]]>
http://www.atcllc.com/news/atc-announces-barnhart-branch-river-transmission-project-in-area/feed/ 0
American Transmission Co. improves electric reliability for Racine- Kenosha area http://www.atcllc.com/news/american-transmission-co-improves-electric-reliability-for-racine-kenosha-area/ http://www.atcllc.com/news/american-transmission-co-improves-electric-reliability-for-racine-kenosha-area/#comments Wed, 15 Dec 2010 08:00:19 +0000 http://www.atcllc.com/?p=1136 Work includes equipment replacement and vegetation management

PEWAUKEE, Wis. – American Transmission Co. recently wrapped up reliability improvements to the electric transmission system that serves portions of Racine and Kenosha. Approximately $5 million was spent to install optical ground wire, modify structures, replace insulators and upgrade substation equipment. In addition, ATC is conducting vegetation management activities to remove incompatible vegetation in the project area to ensure the safety and reliability of the line. This work is expected to conclude in spring 2011.

Some of the components, including insulators and protective equipment on portions of the 138,000-volt transmission system, had been in service more than 70 years. “This type of equipment is built to last many decades, and it generally has performed well,” said project manager Mike Kamarainen. “But the deteriorating condition, including rust and corrosion, meant the time had come to replace and retire a number of components.”

According to Kamarainen, periodic outages have been a problem in recent years. “The completion of this project allows ATC to provide direct connectivity to its control centers and helps strengthen electric reliability in the Racine and Kenosha areas,” he added. “The vegetation work adds another level of safety and reliability to the system in the area.”

]]>
http://www.atcllc.com/news/american-transmission-co-improves-electric-reliability-for-racine-kenosha-area/feed/ 0
American Transmission Co. Milton power line completed and in service http://www.atcllc.com/news/american-transmission-co-milton-power-line-completed-and-in-service/ http://www.atcllc.com/news/american-transmission-co-milton-power-line-completed-and-in-service/#comments Mon, 13 Dec 2010 08:00:38 +0000 http://www.atcllc.com/?p=1134 Line provides power to new Rock Energy Cooperative substation

MADISON, Wis. – American Transmission Co. on Friday completed construction and placed in service a new four-mile, 69-kilovolt electric transmission line serving the Milton area. The line brings power to the new Rock Energy Cooperative substation built near the Milton Crossroads Business Park.

The line connects REC’s new Red Hawk Substation located near Milton Harmony Townline Road and County Highway M to the transmission grid that serves the area. “The new transmission line and substation will serve a growing need for reliable electric service in the region and will support continued growth of the Milton industrial park,” said Denny Schultz, director of utility operations at REC.

ATC and REC introduced the project and preliminary route corridors to the public in August 2009, identified the final route in January 2010, and began construction in August 2010. In total, contractors completed roughly 4,600 hours of injury-free work, and completed the project five days ahead of schedule. The final project cost was approximately $4 million, which is about $200,000 under budget.

“We appreciate the participation and cooperation of landowners, businesses and public officials in the area during the entire process,” says Jon Callaway, local relations representative for ATC. “We will continue to work with landowners and keep them informed of our activities as we complete restoration of the right-of-way this winter and next spring, and as we manage the vegetation along the line in the coming years.”

Note to editors: A map of the route is available on our website at www.atc-projects.com.

]]>
http://www.atcllc.com/news/american-transmission-co-milton-power-line-completed-and-in-service/feed/ 0
American Transmission Co. to conduct soil boring along western portion of Rockdale-West Middleton transmission line route Process will help determine pole placement and design http://www.atcllc.com/news/american-transmission-co-to-conduct-soil-boring-along-western-portion-of-rockdale-west-middleton-transmission-line-route-process-will-help-determine-pole-placement-and-design/ http://www.atcllc.com/news/american-transmission-co-to-conduct-soil-boring-along-western-portion-of-rockdale-west-middleton-transmission-line-route-process-will-help-determine-pole-placement-and-design/#comments Fri, 03 Dec 2010 08:00:23 +0000 http://www.atcllc.com/?p=1132 MADISON, Wis. – American Transmission Co. is continuing preliminary field work for a new 32-mile, 345,000-volt electric transmission line through Dane County between the towns of Middleton and Christiana. ATC will begin conducting soil borings along the western half of the power line route along the Beltline and Highway 14 in the next few days, continuing until the end of January.

The process involves drilling a small 2- or 3-inch diameter hole, at depths up to 40 feet, periodically along the route to sample the soil and assess its makeup. The soil boring information is used to determine the exact placement of the structures, whether they will be placed in soil or rocks, and what provisions will be required to ensure the concrete foundations will adequately secure and stabilize the steel structures.

“Conducting soil boring is a necessary step in designing a transmission line of this type,” says Brian Fischer, ATC project manager. “We like to take advantage of frozen ground conditions when conducting this work in order to minimize environmental impacts.”

Soil boring will be completed by ATC subcontractor Subsurface Exploration Services, LLC at approximately 70 locations along the western half of the route. Most of the work will be completed within Wisconsin Department of Transportation right-of-way. While the 20-ton drilling truck used for the soil borings will be visible from the Beltline, no significant traffic impacts are anticipated.

“Construction mats will be used to protect and level the ground at a handful of locations where the terrain is not level enough for safe operation of the drilling truck,” says Amy Lee, ATC environmental project manager. “ATC will also have environmental monitors on hand to supervise work in environmentally sensitive areas, and some areas will require the removal of minimal vegetation to allow crews to safely maneuver and operate the drill truck.”

Soil boring along the portion of the route that crosses the wetlands adjacent to the Yahara River was completed in January 2010 to take advantage of the opportunity to minimize environmental disturbances during the winter months. No additional borings in the Yahara wetlands are currently planned prior to the start of construction activities, which are planned to begin on the eastern half of the route in fall 2011. Construction of the 32-mile line is expected to be completed in 2013.

]]>
http://www.atcllc.com/news/american-transmission-co-to-conduct-soil-boring-along-western-portion-of-rockdale-west-middleton-transmission-line-route-process-will-help-determine-pole-placement-and-design/feed/ 0
PSCW approves Clear Lake-Woodmin transmission line http://www.atcllc.com/news/pscw-approves-clear-lake-woodmin-transmission-line/ http://www.atcllc.com/news/pscw-approves-clear-lake-woodmin-transmission-line/#comments Tue, 09 Nov 2010 08:00:15 +0000 http://www.atcllc.com/?p=1129 American Transmission Co. to build 7.2-mile power line in Oneida, Vilas counties

DE PERE, Wis. – Electric system reliability will be improved in the Wisconsin Northwoods with recent approval of the Clear Lake-Woodmin transmission line. The Public Service Commission of Wisconsin authorized construction of the 7.2 mile line between the Clear Lake Substation southeast of Woodruff on Highway 47 and the proposed Woodmin Substation west of Highway 47 in the town of Arbor Vitae.

“We appreciate the involvement and participation of local officials and community residents as we worked to identify an appropriate project,” said Lee Meyerhofer, senior local relations representative for ATC. “We will continue to stay in touch with landowners and officials as we take our project into the construction phase.”

Construction of the $21 million project will begin in Fall 2011. Much of the new line will be built following an existing electric distribution line and road right-of-way. Only about seven acres of new right-of-way will be needed.

The project is needed to support the local distribution network. Wisconsin Public Service Corp., the local distribution utility, will build the Woodmin Substation.

More information on the project is available on the “projects” page of our web site, www.atcllc.com

]]>
http://www.atcllc.com/news/pscw-approves-clear-lake-woodmin-transmission-line/feed/ 0
American Transmission Co. names Flynn VP of Business Development http://www.atcllc.com/news/american-transmission-co-names-flynn-vp-of-business-development/ http://www.atcllc.com/news/american-transmission-co-names-flynn-vp-of-business-development/#comments Tue, 26 Oct 2010 08:00:11 +0000 http://www.atcllc.com/?p=1127 PEWAUKEE, Wis. – American Transmission Co. has named John Flynn as vice president of Business Development, effective Nov. 15, 2010. In this newly created position, Flynn will lead ATC in its effort to expand its electric transmission development opportunities outside of ATC’s primary footprint of Wisconsin and Upper Michigan.

Flynn most recently served in several key transmission leadership roles at American Electric Power in Columbus, Ohio, including managing director of Strategic Planning, Finance & Business Development for AEP Transmission, as well as president of Pioneer Transmission (a joint venture between AEP and Duke Energy), and executive vice president of Electric Transmission America (a joint venture between AEP and MidAmerican Holdings). Flynn’s 20-year career in the energy industry also includes financial, regulatory and policy responsibilities with Northeast Utilities, Progress Energy and Arthur Andersen.

“We are excited to add an experienced professional like John to our business development efforts,” said John Procario, chairman, president and chief executive officer of ATC. “John brings industry experience and the strong leadership skills needed to help position ATC for continual growth as the transmission company of choice throughout North America.”

Flynn graduated from Fairfield University with a bachelor’s degree in accounting.

]]>
http://www.atcllc.com/news/american-transmission-co-names-flynn-vp-of-business-development/feed/ 0
American Transmission Co. to discuss preliminary route corridors for proposed power line to serve western Milwaukee County http://www.atcllc.com/news/american-transmission-co-to-discuss-preliminary-route-corridors-for-proposed-power-line-to-serve-western-milwaukee-county/ http://www.atcllc.com/news/american-transmission-co-to-discuss-preliminary-route-corridors-for-proposed-power-line-to-serve-western-milwaukee-county/#comments Wed, 13 Oct 2010 08:00:05 +0000 http://www.atcllc.com/?p=1124 Open house will be Oct. 21, 4-7 p.m. at the Wauwatosa Civic Center

PEWAUKEE, Wis. – An informational open house on Thursday, Oct. 21 at the Wauwatosa Civic Center will provide area landowners and members of the public an opportunity to comment on American Transmission Co.’s proposal for a new 138,000- volt transmission line to be located primarily in Wauwatosa.

“An approximately 2-mile transmission line is needed to connect to a new substation proposed by We Energies,” explains Mary Carpenter, local relations representative for ATC. “We Energies’ planning forecasts indicate that additional power is needed in the area to serve their local customers.”

According to We Energies’ planning studies, electric demand in the U.S Highway 45 corridor in western Milwaukee County is projected to double as soon as 2016-2018. “Studies also indicate that existing distribution substations and feeders that serve the area will not be adequate to meet anticipated future electric demand,” says Andrew Gumm, We Energies manager of project siting. “To respond to the area’s growing electric needs, we plan to build a new distribution substation adjacent to the existing Milwaukee County Substation and Milwaukee County Power Plant at 93rd Street and Watertown Plank Road.”

American Transmission Co. staff, along with representatives from We Energies, will be on hand at the Wauwatosa Civic Center between 4 p.m. and 7 p.m. on Thursday, Oct. 21, to discuss with stakeholders the plans, including preliminary corridors being considered for the power line.

“We look to the public, particularly people who may be impacted, to participate in the process by providing comments and input,” says Carpenter. “This first of three informal open houses is the best venue for people to learn about the project and to have a voice in shaping decisions about where the line will be located.”

ATC mailed open house invitations to potentially affected landowners and businesses. During the next year, ATC will narrow the potential routes before filing an application to build the line with the Public Service Commission of Wisconsin in early 2012. If approved by the PSCW, construction of the new line would begin in 2014 to meet an inservice date of 2015.

Note to editors: A map and additional information on the project is available at www.atcprojects.com

]]>
http://www.atcllc.com/news/american-transmission-co-to-discuss-preliminary-route-corridors-for-proposed-power-line-to-serve-western-milwaukee-county/feed/ 0
Helicopter crews will patrol ATC transmission lines http://www.atcllc.com/news/helicopter-crews-will-patrol-atc-transmission-lines/ http://www.atcllc.com/news/helicopter-crews-will-patrol-atc-transmission-lines/#comments Fri, 17 Sep 2010 08:00:09 +0000 http://www.atcllc.com/?p=1122 PEWAUKEE, Wis. – Helicopter crews began the annual patrolling of American Transmission Co. electric transmission lines Monday to look for damage, right-of-way encroachments and vegetation issues.

ATC contracted the services of Chemair Helicopters of Jefferson, Wis. Crews are patrolling the transmission system in Bell 206B Jet Ranger helicopters. Weather permitting, crews will follow the general timeline below to inspect lines within the ATC service territory:

  • Mid-September – Upper Peninsula of Michigan and northern Wisconsin
  • Late September, early October — northern and central Wisconsin
  • November and December — southern Wisconsin

ATC conducts helicopter patrols two or three times a year to detect potential problems that can be corrected to avoid unplanned power outages. Many of ATC’s 9,400 miles of transmission lines are located in relatively remote areas of Wisconsin and the Upper Peninsula of Michigan, and it is difficult and time consuming for crews to reach these areas by vehicle or on foot. Aerial inspections allow crews to reach secluded or difficult-to-reach lines and identify potential problems such as damaged lines or insulators, or tree limbs that could fall, damage equipment and cause power outages.

Crews will inspect the lines by flying approximately 10 feet above the wires, and they will avoid flying over livestock where possible. Schedule may vary due to weather and the need to work around the gun deer hunting season.

Note to editors: A map of the ATC service territory is available at www.atcllc.com

]]>
http://www.atcllc.com/news/helicopter-crews-will-patrol-atc-transmission-lines/feed/ 0
ATC’s studies identify $3.4 billion in transmission investment needed over next 10 years http://www.atcllc.com/news/atc%e2%80%99s-studies-identify-3-4-billion-in-transmission-investment-needed-over-next-10-years/ http://www.atcllc.com/news/atc%e2%80%99s-studies-identify-3-4-billion-in-transmission-investment-needed-over-next-10-years/#comments Thu, 09 Sep 2010 08:00:54 +0000 http://www.atcllc.com/?p=1119 Annual planning assessment includes regional, multi-benefit projects for reliability, economic savings and renewable energy delivery

PEWAUKEE, Wis. – American Transmission Co. has issued its annual 10-Year Transmission System Assessment, calling for $3.4 billion in electric transmission system improvements in portions of Wisconsin and Upper Michigan through 2019.

“There is an increasing need for an expanded regional transmission system because of an emerging wholesale marketplace and federal and state policy changes,” explains Flora Flygt, director of strategic projects at ATC. “This year’s assessment not only addresses projects needed for system reliability, but also includes emerging projects that meet larger, regional needs based on economic benefits and public policy initiatives for renewable energy.”

ATC’s 2010 assessment of transmission system needs includes:

  • $1.0 billion for transmission network upgrades,
  • $1.7 billion in interconnection and asset renewal projects, replacements and other small network improvements and
  • $0.7 billion in regional, multi-benefit projects.

Several regional planning initiatives undertaken by multiple stakeholders have identified common projects, including 345-kV lines between La Crosse and Madison, Wis., and Madison and Dubuque, Iowa. While still under study, ATC is beginning public outreach later this month on the Badger Coulee project, a proposed 150-mile 345-kV line between La Crosse and the greater Madison areas. Other emerging projects include new or upgraded 138- and 345-kV facilities to accommodate a generator upgrade at Point Beach Nuclear Plant and a potential six-mile, 345-kV line to alleviate congestion on transmission facilities in Kenosha County.

“Access to economic sources of generation continues to be an emphasis in our planning studies,” notes Paul Roehr, director of system planning. “The infrastructure improvements we have made in the last 10 years have eased constraints on our system and have allowed our customers access to lower-cost sources of electricity.”

When the Midwest wholesale market was established in 2005, the average locational marginal price within ATC’s footprint was $63.27 per megawatt hour, more than $10 higher than the average in neighboring market hubs. In 2009, the difference was only $1.27 per megawatt hour.

Since 2001, ATC has invested more than $2.2 billion to:

  • upgrade more than 1,650 miles of transmission line,
  • improve 140 electric substations and
  • build 40 new transmission lines (530 miles).

ATC’s 10-Year Assessment is available online at www.atc10yearplan.com

]]>
http://www.atcllc.com/news/atc%e2%80%99s-studies-identify-3-4-billion-in-transmission-investment-needed-over-next-10-years/feed/ 0
American Transmission Co. announces open houses for Badger Coulee Transmission Line Project http://www.atcllc.com/news/american-transmission-co-announces-open-houses-for-badger-coulee-transmission-line-project/ http://www.atcllc.com/news/american-transmission-co-announces-open-houses-for-badger-coulee-transmission-line-project/#comments Wed, 08 Sep 2010 08:00:23 +0000 http://www.atcllc.com/?p=1117 Eight informational open houses to be held throughout the project study area

PEWAUKEE, Wis. – American Transmission Co. is beginning a multi-year public outreach process for the proposed Badger Coulee Transmission Line Project with the first in a series of informational open houses for residents and other stakeholders in the 150-mile project study area in late September and early October.

Studies indicate that a 345-kilovolt transmission line from the La Crosse area to the greater Madison area would provide multiple benefits to the state of Wisconsin including improved electric system reliability, economic savings for utilities and energy consumers, and better access to renewable energy.

ATC is hosting eight open houses throughout the project study area to provide stakeholders with more information about the project and answer questions. The public is invited to attend any of the following open houses:

Monday, Sept. 27, Stoney Creek Inn, Onalaska
Tuesday, Sept. 28, Westby Coon Prairie Lutheran Church, Westby
Wednesday, Sept. 29, Kalahari Resort Convention Center, Wisconsin Dells
Thursday, Sept. 30, Sauk Prairie Community Center, Sauk City
Monday, Oct. 4, Hillsboro Fireman’s Community Center, Hillsboro
Tuesday, Oct. 5, Cranberry Country Lodge, Tomah
Wednesday, Oct. 6, Madison Marriott West Convention Center, Middleton
Thursday, Oct. 7, Grace Bible Church, Portage
Open houses at all locations run from 1 to 7 p.m.

“Before ATC seeks local or regulatory approval for a project, a comprehensive public involvement process takes place to gather input and feedback for a proposed transmission line,” said ATC Local Relations Manager Sarah Justus. “We invite everyone who could be impacted by the project to get involved. Successful planning and siting of transmission lines that bring power into your communities depends on local participation.” ATC will hold three more rounds of open houses over the next two years to gather public input and narrow potential routes before filing an application to build the line with the Public Service Commission of Wisconsin, anticipated in 2013. If approved by the PSC, construction of the new line would begin in 2016 to meet an in-service date of 2018.

Note to editors: A map and additional information on the Badger Coulee Transmission Line Project is available at www.BadgerCoulee.com

]]>
http://www.atcllc.com/news/american-transmission-co-announces-open-houses-for-badger-coulee-transmission-line-project/feed/ 0
American Transmission Co. beginning construction on Milton power line http://www.atcllc.com/news/american-transmission-co-beginning-construction-on-milton-power-line/ http://www.atcllc.com/news/american-transmission-co-beginning-construction-on-milton-power-line/#comments Mon, 16 Aug 2010 08:00:44 +0000 http://www.atcllc.com/?p=1115 Line will bring power to new Rock Energy Cooperative substation

MADISON, Wis. – American Transmission Co. on Friday will begin construction activities on a new four-mile, 69-kilovolt electric transmission line to serve the Milton area. Construction activities will begin with vegetation clearing along the route in preparation for ATC to drill holes and set pole foundations beginning in September.

The new line is needed to bring power to a new substation that Rock Energy Cooperative is building near the Milton Crossroads Business Park. ATC and REC introduced the project and preliminary route corridors to the public in August 2009, and held two public open houses to gather input on possible routes before identifying the final route in January 2010. During the past several months ATC has been designing the line and acquiring easements from landowners along the route. The new Red Hawk Substation is currently under construction, and the entire project is planned to be complete and in service this winter.

“We have worked closely with landowners, businesses and public officials impacted by the route,” says Jon Callaway, local relations representative for ATC. “As we move forward with the construction activities, we will we continue to work with landowners to secure easements and keep them informed of our construction activities.”

The approximately $4.2 million line will connect an existing 69-kilovolt transmission line that runs parallel to Cty Hwy Y to a new Rock Energy Cooperative substation near the intersection of Harmony Milton Town Line Road and Cty Hwy M. The western part of the new line will be mostly on agricultural land; the remainder of the line will follow Town Line Road, the future site of the realigned Hwy 26 and Cty Hwy M.

Note to editors: A map of the route is available on our website at www.atc-projects.com

]]>
http://www.atcllc.com/news/american-transmission-co-beginning-construction-on-milton-power-line/feed/ 0
ATC applies for permission to improve transmission system in Sparta-Tomah area http://www.atcllc.com/news/atc-applies-for-permission-to-improve-transmission-system-in-sparta-tomah-area/ http://www.atcllc.com/news/atc-applies-for-permission-to-improve-transmission-system-in-sparta-tomah-area/#comments Mon, 02 Aug 2010 08:00:34 +0000 http://www.atcllc.com/?p=1112 Regulatory filing submitted to Public Service Commission of Wisconsin

PEWAUKEE, Wis. – American Transmission Co. has filed an application with the Public Service Commission of Wisconsin to rebuild and upgrade an existing electric transmission line that connects the Monroe County Substation near Sparta and the Council Creek Substation near Tomah. ATC also will build a new substation as part of the project to improve electric system reliability.

“Rebuilding the existing line and adding an additional 161-kilovolt line will enhance electric reliability for the Sparta and Tomah communities,” said Charles Gonzales, senior local relations representative for ATC. “The new 161-kilovolt line will also provide economic savings by reducing line losses and providing access to lower-cost generation.”

Work on the 17-mile line, primarily along Highway 16, will involve replacing poles and wires on the existing 69-kV transmission line, adding a 161-kV circuit to the new steel poles and building the new Timberwolf Substation approximately one half-mile south of Interstate 90 along Highway 131.

ATC is coordinating with Dairyland Power Cooperative, Xcel Energy, Alliant Energy and Oakdale Electric Cooperative on the project. Construction of the approximately $36 million project will be completed within the area of the existing right-of-way and is expected to be in service mid-2013. For more information visit the PSC website at http://psc.wi.gov/ and enter Docket ID: 137-CE-158.

Note to editors: A map of the route is available at http://www.atc-projects.com/MCCC.shtml.

]]>
http://www.atcllc.com/news/atc-applies-for-permission-to-improve-transmission-system-in-sparta-tomah-area/feed/ 0
American Transmission Co. announces plans for 150-mile, 345-kV transmission line in western Wisconsin http://www.atcllc.com/news/american-transmission-co-announces-plans-for-150-mile-345-kv-transmission-line-in-western-wisconsin/ http://www.atcllc.com/news/american-transmission-co-announces-plans-for-150-mile-345-kv-transmission-line-in-western-wisconsin/#comments Mon, 26 Jul 2010 08:00:34 +0000 http://www.atcllc.com/?p=1110 Badger Coulee Transmission Line Project is a multi-benefit project demonstrating reliability, economic and renewable benefits

PEWAUKEE, Wis. – Following approximately two years of study and analysis, American Transmission Co. has determined that a 345-kilovolt transmission line from the La Crosse area to the greater Madison area would provide multiple benefits to the state of Wisconsin including improved electric system reliability, economic savings for utilities and energy consumers, and access to additional renewable energy. As it finalizes its evaluation of the multiple benefits of the project, ATC will begin the public outreach efforts on the proposed Badger Coulee Transmission Line and will host a series of open houses this fall with the public and other stakeholders in the 150-mile area from La Crosse to Madison to explore routing options for the new line.

“There are multiple benefit indicators that make the Badger Coulee Transmission Line Project a plus for Wisconsin residents and the Midwest,” says John Procario, ATC president, chairman and chief executive officer. “It’s an exciting new project because it demonstrates multiple benefits. Badger Coulee enhances electric system reliability; it provides direct energy cost savings to electricity users, and it supports the public’s desire for the greater use of renewable energy resources.”

The Badger Coulee Transmission Line will improve electric system reliability in western Wisconsin by providing increased regional electric transfer capability into Wisconsin and alleviating stability issues in the Upper Midwest. ATC’s studies also indicate that building a more efficient high-voltage line offsets the need for approximately $140 million in lower-voltage upgrades in western Wisconsin communities.

The economic benefits of the Badger Coulee Transmission Line include providing utilities with greater access to the wholesale electricity market by reducing energy congestion. A new 345-kV line in western Wisconsin will give utilities greater capability to buy and sell power within the Midwest when it’s economic to do so, and those savings can be passed on to electricity consumers. A 345-kV line also delivers electricity more efficiently than lower voltage or heavily loaded transmission lines and reduces line losses in the delivery of power.

ATC’s studies further indicate that the Badger Coulee Transmission Line will support the transfer of renewable energy into Wisconsin to help meet public policy goals in Wisconsin and the Midwest region. That’s consistent with several regional transmission studies in which ATC is participating with other utilities that identify this corridor as key to moving renewable energy.

Announcement of the proposed Badger Coulee Transmission Line kicks off an inclusive and exhaustive process of public involvement and regulatory review. Following public input on routes, ATC currently expects to file an application to build the line with the Public Service Commission of Wisconsin in 2013. If approved by the PSC, construction on the new line would begin in 2015 to meet an in-service date of 2018.

Note to editors: A map and additional information on the Badger Coulee Transmission Line Project is available at www.atc-projects.com

]]>
http://www.atcllc.com/news/american-transmission-co-announces-plans-for-150-mile-345-kv-transmission-line-in-western-wisconsin/feed/ 0
American Transmission Co. and SMART Study co-sponsors release Phase One study results for transporting renewable energy across Upper Midwest http://www.atcllc.com/news/american-transmission-co-and-smart-study-co-sponsors-release-phase-one-study-results-for-transporting-renewable-energy-across-upper-midwest/ http://www.atcllc.com/news/american-transmission-co-and-smart-study-co-sponsors-release-phase-one-study-results-for-transporting-renewable-energy-across-upper-midwest/#comments Thu, 01 Jul 2010 08:00:11 +0000 http://www.atcllc.com/?p=1108 PEWAUKEE, WI – American Transmission Co. along with co-sponsors Electric Transmission America, a transmission joint venture between subsidiaries of American Electric Power (NYSE: AEP) and MidAmerican Energy Holdings Co., Exelon Corp. (NYSE: EXC), NorthWestern Energy (NYSE: NWE), Xcel Energy (NYSE: XEL), and MidAmerican Energy Co., a subsidiary of MidAmerican Energy Holdings Co., today released Phase One of a comprehensive study of the transmission needed in the Upper Midwest to ensure reliability and support renewable energy development for transport to population and electricity load centers.

Phase One results of the Strategic Midwest Area Transmission (SMART) Study recommend three alternatives for further study based on a rigorous reliability assessment and stakeholder input. One alternative is primarily 765-kV extra-high voltage transmission, another includes 765-kV combined with limited use of highvoltage direct current transmission lines, while the third constitutes a combination of both 345-kV and 765-kV transmission lines. The three alternatives will be evaluated further during the second phase of the study, scheduled for completion during the third quarter of 2010. The Phase One report can be downloaded at www.smartstudy.biz.

The sponsors retained Quanta Technology LLC to evaluate extra-high voltage transmission alternatives and provide recommendations for new transmission development in the Upper Midwest. In Phase One, Quanta evaluated eight transmission alternatives designed to support the integration of 56.8 gigawatts of nameplate wind generation within the study area including North Dakota, South Dakota, Nebraska, Minnesota, Iowa, Missouri, Wisconsin, Illinois, Indiana, Michigan and Ohio. This translates into enough energy to power more than 15 million households. Quanta assessed and compared transmission alternatives including conducting an economic analysis quantifying the impact and economic benefits of several transmission options.

“Our participation in this and other regional studies is key to ensuring the continued reliability of the electric system grid while also achieving the public policy goals for the integration of greater amounts of renewable energy,” says John Procario, president, chairman and CEO of ATC. “Our approach to transmission planning has increasingly focused on regional issues and benefits. While we continue to analyze the need for improvements on the system within our footprint, we recognize a need to look more broadly across the region. Many regional planning collaborations continue with multiple stakeholders, including utilities, regulators, policy makers, large energy users and others. As these efforts mature, more large-scale infrastructure improvements are being studied to address the needs of the regional marketplace.”

The SMART Study’s goal is to develop a 20-year transmission plan that ensures reliable electricity transport, provides an efficient transmission system to integrate new generators and foster efficient markets, minimizes environmental impacts, and supports state and national energy policies.

]]>
http://www.atcllc.com/news/american-transmission-co-and-smart-study-co-sponsors-release-phase-one-study-results-for-transporting-renewable-energy-across-upper-midwest/feed/ 0
Fitchburg – Verona Electric System Upgrade Project Complete http://www.atcllc.com/news/fitchburg-%e2%80%93-verona-electric-system-upgrade-project-complete/ http://www.atcllc.com/news/fitchburg-%e2%80%93-verona-electric-system-upgrade-project-complete/#comments Wed, 30 Jun 2010 08:00:33 +0000 http://www.atcllc.com/?p=1106 Project will meet the area’s increasing electricity needs

MADISON, Wis. – American Transmission Co. put into service a critical reinforcement to the electric transmission network serving southern Dane and northern Green counties today. The project included building the new Oak Ridge Substation in Fitchburg and constructing approximately six miles of new 138-kilovolt transmission line to connect the new substation to an existing substation in Verona.

“This new infrastructure is providing much needed reinforcement to the transmission system serving the area,” says Charlie Gonzales, ATC local relations representative. “The new line can better accommodate electric load growth in the community, and it creates an alternate path for electricity to flow in the event of an outage on another portion of the network.”

The project was introduced to the public in 2005, approved by the Public Service Commission of Wisconsin in January 2008 and construction began in summer 2008. Construction of the new substation was completed in May 2009, two months ahead of schedule, and the overall project costs will come in under the PSC-approved amount at $18.8 million.

Although construction is completed and the line is in service, some work remains. ATC continues to complete restoration along the right-of-way. “We take great measures to minimize the impact of construction,” says Gonzales. “We want area residents to know we are committed to restoring the corridor.”

“We appreciate the involvement and cooperation of the residents as we worked through the siting and construction of this line,” says Mark Sanzenbacher, ATC project manager.

Note to editors: A map and additional information on the Fitchburg-Verona project is available at www.atc-projects.com

]]>
http://www.atcllc.com/news/fitchburg-%e2%80%93-verona-electric-system-upgrade-project-complete/feed/ 0
Landgren to retire from American Transmission Co. http://www.atcllc.com/news/landgren-to-retire-from-american-transmission-co/ http://www.atcllc.com/news/landgren-to-retire-from-american-transmission-co/#comments Tue, 01 Jun 2010 08:00:44 +0000 http://www.atcllc.com/?p=1104 PEWAUKEE, Wis. – Dale A. Landgren, vice president and chief strategic officer at American Transmission Co., has announced his retirement, effective Dec. 31, 2010.

As chief strategic officer, Landgren’s responsibilities include planning, federal and regional relations and policy, customer relations and interconnection services. Those functions now will report to other members of the executive team, with Landgren helping make the transition through the remainder of the year.

“As one of the company’s founding executives, Dale played an important role in the development and growth of ATC,” said John Procario, president and chief executive officer. “He guided our strategic planning process, identifying projects and policies that built out our legacy networks into a more robust system, helping the company grow from $550 million in assets to $2.75 billion today.”

Well-respected in the electric transmission industry, Landgren was a significant player in the establishment of the Midwest Independent System Operator. He served on the Management Council of the Midwest ISO from 1996 to 1998 and chaired the Transmission Owners Group from 2000-2002. Landgren has continued to play an important role in the North American Electric Reliability Corp., currently serving as chair of the Midwest Reliability Organization Board and serving on the NERC Member Representative Committee.

Prior to helping establish ATC in 2000, Landgren had a 27-year career at Wisconsin Electric Power Co. (now We Energies), where he was named an officer in 1997.

Landgren earned a bachelor of science degree in electrical engineering at Marquette University and a master’s degree in economics from the University of Chicago.

]]>
http://www.atcllc.com/news/landgren-to-retire-from-american-transmission-co/feed/ 0
American Transmission Co. announces plan to improve transmission system serving Sparta, Tomah http://www.atcllc.com/news/american-transmission-co-announces-plan-to-improve-transmission-system-serving-sparta-tomah/ http://www.atcllc.com/news/american-transmission-co-announces-plan-to-improve-transmission-system-serving-sparta-tomah/#comments Wed, 26 May 2010 08:00:51 +0000 http://www.atcllc.com/?p=1102 Project involves rebuilding and adding a circuit within existing transmission right-of-way

PEWAUKEE, Wis. – American Transmission Co. plans to rebuild and upgrade an existing electric transmission line that connects the Monroe County Substation near Sparta and the Council Creek Substation near Tomah. ATC also will build a new substation as part of the project to improve electric system reliability.

“Rebuilding this line, adding the new circuit and building the new substation will provide many benefits to the electric transmission system serving the Sparta and Tomah communities,” says Charles Gonzales, ATC local relations representative. “The line will improve electric system reliability, increase efficiency of the transmission system and provide economic savings due to the transmission system’s ability to access lower-cost generation when it’s economic for the local utility to do so and move it into the area.”

The existing transmission system that serves the area is approximately 40 years old and is susceptible to overloads and severe low voltages. Work on the 17-mile line, primarily along Highway 16, will involve replacing the poles and wires on the existing 69-kilovolt transmission line, adding a 161-kV circuit to the new steel poles and building the new Timberwolf Substation approximately one half-mile mile south of Interstate 90 along Highway 131.

ATC is coordinating with Dairyland Power Cooperative, Xcel Energy, Alliant Energy and Oakdale Electric Cooperative on the project. Construction of the approximately $36 million project will be completed within the area of the existing right-of-way and is expected to be in service mid-2013.

ATC is conducting an open house to provide more information about the proposed project and answer questions. The public is invited to drop in at the open house on Tuesday, June 8, between 4 and 7 p.m. at Ambassador Baptist Church, 15623 Highway 16, located 6 miles east of Sparta and 10 miles west of Tomah. No formal presentation is planned.

Note to editor: A map of the route is available on our Web site at http://www.atc-projects.com/MCCC.shtml.

]]>
http://www.atcllc.com/news/american-transmission-co-announces-plan-to-improve-transmission-system-serving-sparta-tomah/feed/ 0
ATC wins environmental stewardship award http://www.atcllc.com/news/atc-wins-environmental-stewardship-award/ http://www.atcllc.com/news/atc-wins-environmental-stewardship-award/#comments Mon, 24 May 2010 08:00:02 +0000 http://www.atcllc.com/?p=1099 Innovative use of engineered construction mats cited

DE PERE, Wis. – American Transmission Co. has captured a Business Friend of the Environment Award from the Wisconsin Environmental Working Group, an affiliate of Wisconsin Manufacturers & Commerce.

The company was recognized for its “willingness to go beyond the regulatory requirements by seeking out and implementing a cost-effective, environmentally conscientious method for protecting the Bear Creek Marsh” near Stevens Point during a recent power line construction project. ATC worked closely with several vendors to develop an engineered “air bridge” system of construction mats to protect a massive wetland complex from heavy construction equipment. The air bridge had engineered, certified load ratings and essentially floated on the vegetative layer, rising and falling with water levels. Impacts to the wetland were minimal.

“We are pleased to be recognized for our stewardship,” said Franc Fennessy, director of land management and stakeholder affairs. “We are committed to environmental leadership in all aspects of our business, as evidenced by our participation in the Department of Natural Resource’s Green Tier program, as well as policies and actions that guide our construction projects, such as the one that crossed the Bear Creek Marsh.”

2010 marks the 21st year that the Wisconsin Environmental Working Group has recognized programs that “demonstrate an innovative approach to environmental protection, or a level of effort beyond that which is required by regulatory compliance.

]]>
http://www.atcllc.com/news/atc-wins-environmental-stewardship-award/feed/ 0
American Transmission Co. names Jett director of Business Development http://www.atcllc.com/news/american-transmission-co-names-jett-director-of-business-development/ http://www.atcllc.com/news/american-transmission-co-names-jett-director-of-business-development/#comments Thu, 20 May 2010 08:00:25 +0000 http://www.atcllc.com/?p=1097 PEWAUKEE, Wis. – American Transmission Co. has named Paul Jett director of Business Development, effective June 1, 2010. Jett is the first member of the newly created Business Development team, which will work to identify electric transmission development opportunities outside of ATC’s primary footprint of Wisconsin and Upper Michigan.

Jett most recently served as director of regional transmission organization activities for Duke Energy. Jett worked at Cinergy for 19 years prior to the company’s merger with Duke Energy in 2006. During his tenure at Cinergy, Jett held numerous leadership roles in system operations, operations engineering, regional coordination and planning, regulatory and legislative strategy, federal regulatory policy, and control area operations.

Jett currently serves as chair of the Midwest ISO Steering Committee and vice chair of the Midwest ISO Advisory Committee. He previously served as chair of the Midwest ISO Transmission Owners’ Committee in 2007 and 2008.

“We are excited to add an experienced professional like Paul to our new Business Development team as we expand our business,” said John Procario, president, chief executive officer and chairman of ATC. “Paul brings business and industry experience and the strong leadership skills needed to help position ATC for continual growth as the premier transmission utility in the United States.”

Jett earned a bachelor’s of science degree in electrical engineering technology from the University of Cincinnati and a master’s degree in business administration from Thomas More College.

]]>
http://www.atcllc.com/news/american-transmission-co-names-jett-director-of-business-development/feed/ 0
Regulatory review underway for proposed power line http://www.atcllc.com/news/regulatory-review-underway-for-proposed-power-line/ http://www.atcllc.com/news/regulatory-review-underway-for-proposed-power-line/#comments Mon, 10 May 2010 17:18:53 +0000 http://www.atcllc.com/?p=1095 PSCW determines ATC’s application is complete

DE PERE, Wis. – A proposed 115,000-volt electric transmission line proposed by American Transmission Co. is under review by the Public Service Commission of Wisconsin. The line would run seven or eight miles from the Clear Lake Substation on Highway 47 to a new substation to be built by Wisconsin Public Service Corp. along Arnett Road west of Woodruff.

“The WPS distribution system that serves electricity customers in the area is located at the northwestern end of the portion of the transmission system known as the ‘Rhinelander Loop,’” explains Lee Meyerhofer, senior local relations representative for ATC. “The distribution system needs additional transmission support to maintain local reliability.”

ATC introduced the project in late 2008 and worked with area residents and local officials to identify route alternatives. If approved, the PSCW will determine the route the new line would follow. The regulatory review includes opportunities for interested parties to provide comments on the project.

]]>
http://www.atcllc.com/news/regulatory-review-underway-for-proposed-power-line/feed/ 0
American Transmission Co. signs agreements with U.S. Department of Energy for smart grid investment grants http://www.atcllc.com/news/american-transmission-co-signs-agreements-with-u-s-department-of-energy-for-smart-grid-investment-grants/ http://www.atcllc.com/news/american-transmission-co-signs-agreements-with-u-s-department-of-energy-for-smart-grid-investment-grants/#comments Tue, 20 Apr 2010 08:00:46 +0000 http://www.atcllc.com/?p=1093 $12.7 million to be used to enhance smart grid within ATC footprint

PEWAUKEE, Wis. – American Transmission Co. has entered into two agreements with the United States Department of Energy, accepting investment grants totaling $12.7 million to invest in smart grid technologies to be incorporated into ATC’s transmission system.

The DOE in October notified ATC that two of its applications for smart grid investment grants were selected for smart grid grant awards. The grants to ATC are among 100 made nationwide – totaling $3.4 billion – by the DOE to advance smart grid technologies.

One of the grants will be used to equip ATC substations with phasor measurement units, a new technology for monitoring the status of the grid in real time. PMUs are considered one of the most important measuring devices for the future of power systems because they provide a wider, more integrated and time-synchronized view of the system as a whole. ATC installed a limited number of the PMU devices on its system last year and evaluated their performance with a positive result. A $1.3 million grant will help ATC equip remaining substations in its footprint with the smart technology.

A second $11.4 million grant will assist in extending the use of fiber optic cable to enhance communications between ATC’s substations and its system operations centers. ATC has installed optical ground wire on a number of recent transmission construction projects. The more widespread use of OPGW that will be fostered by the grant will provide ATC with a more secure and reliable data network infrastructure. The OPGW also provides a means to transmit information from the PMUs back to the operations centers for use in system analysis.

“We are pleased to enter into these agreements and take part in the effort to more fully deploy smart grid technologies to enhance the operation of our transmission system,” said John Procario, ATC president and chief executive officer. “These projects will help improve our ability to monitor the grid and enhance the reliability of the transmission infrastructure needed to help keep the lights on.”

ATC has three years to spend the grant money. Projects are currently in the detail design phase and construction will continue into early 2013.

]]>
http://www.atcllc.com/news/american-transmission-co-signs-agreements-with-u-s-department-of-energy-for-smart-grid-investment-grants/feed/ 0
ATC places upgraded power line in service http://www.atcllc.com/news/atc-places-upgraded-power-line-in-service/ http://www.atcllc.com/news/atc-places-upgraded-power-line-in-service/#comments Mon, 12 Apr 2010 08:00:09 +0000 http://www.atcllc.com/?p=1091 Rebuilt facilities in northern Wisconsin, Upper Michigan improve power flow

DE PERE, Wis. – The last section of a rebuilt electric transmission line between Conover, Wis., and Quinnesec, Mich. has been placed into service.

“Upgrading this 74-mile line from 69,000 volts to 138,000 volts has helped reinforce the electric system in the entire region,” said Tom Schemm, construction project manager for American Transmission Co., owner and operator of the line. “These were some of the oldest facilities on our system, and the need for system improvements in this area was evident in the 1990s.”

ATC proposed the project in 2004; it was approved by the Public Service Commission of Wisconsin in 2006 at an authorized cost of $118 million. The project also included a new 16- mile,115-kilovolt line between Eagle River and Conover, which was placed in service in June 2008. Rebuilding the lines between Conover and Quinnesec began in 2009 and was completed more than two months ahead of schedule and about 12 percent under budget. The project also involved construction of two new substations and modifications or upgrades to six additional substations.

“These facilities essentially complete the interconnection of three previously weak areas – the 115-kilovolt system north of Wausau, the western Upper Peninsula and the Iron Mountain, Mich., area,” Schemm said. “That will increase overall reliability in the area and improve our ability to transfer power between northern Wisconsin and Upper Michigan.” The older facilities also were vulnerable to lightning strikes and outages.

“Collaboration with our contractors, vendors and suppliers, including MJ Electric Inc. and Black & Veatch Engineering, helped us squeeze some of the cost out of the project through strategic use of lay-down yards, redesign of poles and foundations and efficient use of labor,” Schemm said. “Lessons learned on this project will be incorporated in our future construction activities.”

]]>
http://www.atcllc.com/news/atc-places-upgraded-power-line-in-service/feed/ 0
American Transmission Co. completes work on cost-saving power line http://www.atcllc.com/news/american-transmission-co-completes-work-on-cost-saving-power-line/ http://www.atcllc.com/news/american-transmission-co-completes-work-on-cost-saving-power-line/#comments Mon, 15 Mar 2010 08:00:21 +0000 http://www.atcllc.com/?p=1089 High-voltage line in south central Wisconsin connects to regional generation sources

PEWAUKEE, Wis. – American Transmission Co. has put into service a new, 35-mile highvoltage electric transmission line in south central Wisconsin that provides local electric utilities with improved access to the regional energy market to buy and sell electricity when it is economic to do so. The 345-kilovolt circuit was built on an existing transmission line right-of-way between the Rockdale Substation in the Town of Christiana in Dane County and the Paddock Substation located in the Town of Beloit in Rock County. The lines that extend south out of the Paddock Substation into Illinois create a path for importing power into Wisconsin.

“Completion of this project is a significant milestone,” said Flora Flygt, director of Transmission Planning. Paddock-Rockdale is the first transmission line project within the footprint of the Midwest Independent System Operator that was justified on economics. Until this project, transmission lines in the region have almost exclusively been built to enhance reliability of electric power in the area. Although improved reliability will be a by-product of the project, economics drove the decision to build.

Flygt said, “The primary benefit of this line is local electric distribution companies now have greater ability to participate in the wholesale electricity market.” She explains, “Wisconsin has fewer transmission line connections to other states compared with its neighboring states. This transmission congestion limits the ability of electric utilities to access the market to purchase lower-cost electricity when prices are lower and sell into the market when prices are higher. The economic benefits of enhanced access can be passed on to end-use customers. The Paddock- Rockdale project provides the needed transmission capacity for today’s energy marketplace, especially with the growing movement toward renewable energy.”

The Paddock-Rockdale project was completed ahead of schedule, and within the approved $133 million budget. Anticipated savings from the project are expected to more than pay for its development.

During construction of the line, ATC took careful consideration of the cost and the environment, using a helicopter for a portion of the work to expedite stringing wire and installing components. By accessing the line via helicopter, fewer timber mats were placed as temporary roads for construction equipment on the ground. As a result, soil disturbance was minimized, which makes restoration work following completion of construction easier and less costly. Restoration will continue throughout the spring and summer.

Note to editors: A map and additional information on the Paddock-Rockdale project is available at www.atc-projects.com

]]>
http://www.atcllc.com/news/american-transmission-co-completes-work-on-cost-saving-power-line/feed/ 0
American Transmission Co. names Banks to lead Internal Audit, Compliance http://www.atcllc.com/news/american-transmission-co-names-banks-to-lead-internal-audit-compliance/ http://www.atcllc.com/news/american-transmission-co-names-banks-to-lead-internal-audit-compliance/#comments Mon, 22 Feb 2010 08:00:15 +0000 http://www.atcllc.com/?p=1087 PEWAUKEE, Wis. – American Transmission Co. has named Juanita C. Banks director of Internal Audit and Compliance. Banks will provide strategic direction for both departments and will oversee ATC’s compliance with new federal mandatory reliability standards that ensure the safe and reliable operation of the bulk electric system. Banks will report to Bert Garvin, vice president, general counsel and secretary.

Banks served as manager of internal audit at ATC for four years where she also chaired the ethics committee. Most recently, Banks was an associate director of internal audit with Protiviti Inc., an internal audit and business risk consulting firm. She also held accounting and auditing positions at WH Brady, Northwestern Mutual and Arthur Andersen, and worked as a special agent with the Wisconsin Department of Justice.

Banks received a bachelor’s degree in accounting from the University of Wisconsin –Milwaukee. She is a certified public accountant and certified internal auditor.

]]>
http://www.atcllc.com/news/american-transmission-co-names-banks-to-lead-internal-audit-compliance/feed/ 0
American Transmission Co. to begin soil boring in Yahara Wetlands http://www.atcllc.com/news/american-transmission-co-to-begin-soil-boring-in-yahara-wetlands/ http://www.atcllc.com/news/american-transmission-co-to-begin-soil-boring-in-yahara-wetlands/#comments Mon, 01 Feb 2010 08:00:15 +0000 http://www.atcllc.com/?p=1084 Environmentally friendly process will help determine pole placement

MADISON, Wis. – Although the actual construction won’t begin until 2011, American Transmission Co. is starting preliminary field work this week for a new 32-mile, 345,000-volt electric transmission line through Dane County between the towns of Middleton and Christiana. The power line route along the Beltline Highway that was approved last summer by the Public Service Commission of Wisconsin includes the placement of several transmission structures in the wetlands adjacent to the Yahara River.

Determining the exact placement, depth and design of structures requires an analysis of the conditions for supporting a 120-foot, steel transmission pole. This analysis, which is accomplished through soil borings, helps determine whether the structures will be placed in soil, rocks or moisture and what provisions will be required to ensure the concrete pole foundations are adequate to secure and stabilize the weight of the poles.

“Conducting soil boring is a fairly routine task on any power line construction project,” says Brian Fischer, ATC project manager. “But marshy wetland areas present additional challenges to ensure that we are minimizing disturbances to an environmentally sensitive area.”

For this reason, ATC’s contractors are conducting the work during the winter months using a specialized vehicle called a Marsh Buggy to access these wetlands where at least ten structures may be located. “This vehicle is designed to navigate marshy areas while minimizing impacts, and has been used successfully on similar projects in other areas of the country where environmental impacts had to be managed,” says Fischer.

The Marsh Buggy, which will be visible from the Beltline Highway, will carry the soil boring equipment and will remain on site for about two to four weeks beginning this week. The vehicle measures about 25 feet long and 14 feet wide, and may be frequently visible from the Beltline. “While visually the Marsh Buggy may appear intrusive, it’s the best piece of equipment available for the job and it’s the best time of year to perform this type of work in this particular area,” says Amy Lee, ATC environmental project manager. “In addition, ATC will have environmental staff on site monitoring this two-to-four week operation, which will also require the removal of some vegetation to allow crews to safely maneuver the vehicle and operate the soil boring equipment.”

In addition to the Marsh Buggy, a second smaller vehicle similar to an ATV, called an ARGO, will be used to transport crews and supplies to and from the Marsh Buggy.

Elsewhere on the 32-mile route, crews will be conducting soil borings in the coming months using standard vehicles and also performing environmental surveying, along with other activities in advance of the start of construction in 2011. Construction is expected to be completed in 2013.

]]>
http://www.atcllc.com/news/american-transmission-co-to-begin-soil-boring-in-yahara-wetlands/feed/ 0
American Transmission Co. names Sanford deputy general counsel http://www.atcllc.com/news/american-transmission-co-names-sanford-deputy-general-counsel/ http://www.atcllc.com/news/american-transmission-co-names-sanford-deputy-general-counsel/#comments Thu, 21 Jan 2010 08:00:09 +0000 http://www.atcllc.com/?p=1082 PEWAUKEE, Wis. – American Transmission Co. has named Dan Sanford deputy general counsel and director of Legal Services. Sanford, who served as managing attorney, will report to Robert Garvin, vice president, general counsel and secretary.

Sanford joined ATC in December 2001 as one of its first staff attorneys, and was promoted to managing attorney in 2007. He has provided guidance to ATC’s management and operations on a wide range of business issues, concentrating on state and federal legal and regulatory matters. In his new role, he will be responsible for continuing to provide guidance to ATC’s general counsel and management and will manage the activities of legal department.

Sanford has extensive experience in the electric and gas industry representing a breadth of industry enterprises including natural gas pipelines, natural gas and electric distribution companies, and independent marketers. Prior to joining ATC, Sanford represented several large utilities including Questar Corp., Florida Power Corp. and Wisconsin Electric, as well as serving as deputy general counsel for the American Gas Association.

Sanford received both a bachelor’s degree in political science and law degree from the University of Wisconsin – Madison.

]]>
http://www.atcllc.com/news/american-transmission-co-names-sanford-deputy-general-counsel/feed/ 0
American Transmission Co. to discuss proposed and alternate routes for new power line http://www.atcllc.com/news/american-transmission-co-to-discuss-proposed-and-alternate-routes-for-new-power-line/ http://www.atcllc.com/news/american-transmission-co-to-discuss-proposed-and-alternate-routes-for-new-power-line/#comments Fri, 08 Jan 2010 08:00:53 +0000 http://www.atcllc.com/?p=1078 Open house will be Jan. 27 at Woodruff Town Hall

DE PERE, Wis. – Representatives from American Transmission Co. will return to the community to discuss the proposed and alternate route options for a new, seven-mile power line in the Minocqua-Woodruff area. These are the routes that will be submitted to the Public Service Commission of Wisconsin for approval. ATC is required to submit at lease two route alternatives.

“The proposed Clear Lake-Woodmin transmission line is needed because local electricity use continues to increase at about three to four percent each year, which is taxing the distribution system operated by Wisconsin Public Service Corp.,” explains Lee Meyerhofer, senior local relations representative for ATC. “A new line extending the transmission system from the Clear Lake Substation on Highway 47 near Mid Lake Road to a new substation proposed by WPS along Highway 47 near Arnett Road west of Woodruff appears to be the best solution for future reliability.”

ATC has conducted three previous open houses to solicit local feedback on siting the new line. “We appreciate the time and effort of local residents to participate in the development of this project,” Meyerhofer says.

Residents are invited to drop in at the open house on Jan. 27 at the Woodruff Town Hall, 1418 First Ave., between 1 and 3 pm or 5 and 7 pm. No formal presentation is planned.

]]>
http://www.atcllc.com/news/american-transmission-co-to-discuss-proposed-and-alternate-routes-for-new-power-line/feed/ 0
American Transmission Co. and Rock Energy Cooperative announce route for new Milton-area power line http://www.atcllc.com/news/american-transmission-co-and-rock-energy-cooperative-announce-route-for-new-milton-area-power-line/ http://www.atcllc.com/news/american-transmission-co-and-rock-energy-cooperative-announce-route-for-new-milton-area-power-line/#comments Fri, 08 Jan 2010 08:00:05 +0000 http://www.atcllc.com/?p=1074 A portion of the line to follow realigned Highway 26 right-of-way

PEWAUKEE, Wis. – After months of study and gathering input from area landowners and public officials, American Transmission Co. and Rock Energy Cooperative have identified a route for a new 69-killovolt electric transmission line to serve the Milton area.

The new ATC-owned electric transmission line will be approximately 4 miles long and will bring power to a new substation Rock Energy Cooperative plans to build near the Milton Industrial Park. “We are pleased to be moving forward with this project,” says Denny Schultz, representative of Rock Energy Cooperative. “This line will benefit the area greatly by meeting the growing need for reliable electric service in the area and by supporting the continued growth of the Milton Industrial Park.”

ATC introduced the preliminary route corridors to the public in August 2009 and held two public open houses to gather input on possible routes. “Throughout the past several months we have worked closely with landowners, businesses and public officials to identify a suitable route for this new line,” says Jon Callaway, senior local relations representative for ATC. “The participation of Milton-area citizens in this process has been invaluable in helping to identify the best route option, one that that offers reduced impacts on both the community and the environment.”

The next steps over the next several months, according to Callaway, involve pre-construction activities such as securing local permits, surveying, environmental and archeological review and soil testing. “In addition, we’ll be working with affected property owners to secure easements. We expect to begin construction of the power line next fall,” he adds.

The approximately $5.3 million line will connect an existing 69-kilovolt transmission line that runs parallel to County Highway Y to a new Rock Energy Cooperative substation near the intersection of Harmony Milton Town Line Road and County Highway M. The western part of the new line will be mostly on agricultural land; the remainder of the line will follow Town Line Road, the future site of the realigned Highway 26 and County Highway M.

Note to editor: A map of the route is available on our Web site at www.atc-projects.com.

]]>
http://www.atcllc.com/news/american-transmission-co-and-rock-energy-cooperative-announce-route-for-new-milton-area-power-line/feed/ 0
Delgado announces retirement from American Transmission Co. http://www.atcllc.com/news/delgado-announces-retirement-from-american-transmission-co/ http://www.atcllc.com/news/delgado-announces-retirement-from-american-transmission-co/#comments Mon, 04 Jan 2010 08:00:23 +0000 http://www.atcllc.com/?p=1080 PEWAUKEE, Wis. – As the founder and first chief executive of the utility that has become a national leader in building electric transmission infrastructure, José M. Delgado, executive chairman of American Transmission Co., has announced his plans to retire effective Feb. 28, 2010, after 10 years with the company. John C. Procario was hired in April as president and chief executive officer and will succeed Delgado as chairman of the board.

Delgado was named CEO of ATC in late 1999 to form and lead the first multi-state transmission-only utility in the United States with assets in four states: Wisconsin, Michigan, Minnesota and Illinois.

Since ATC became operational on Jan. 1, 2001, the company has grown from $500 million in assets to $2.5 billion today. Under Delgado’s leadership, ATC invested more than $2 billion in transmission infrastructure to improve electric system reliability and provide better access to power. The company has built and upgraded more than 1,800 miles of transmission lines including the 220-mile Arrowhead-Weston transmission line from Wausau, Wis., to Duluth, Minn. Overcoming considerable public opposition, ATC completed this project safely, within budget and ahead of schedule while delivering significant electrical, environmental and economic benefits to the region. For this project, ATC was recognized with the Edison Electric Institute’s 2009 Edison Award – considered the industry’s highest honor.

Delgado established a strong environmental ethic at ATC. In 2005, the company became the first utility in Wisconsin to receive the Green Tier designation from the Department of Natural Resources for demonstrating superior environmental performance. In 2009, the company’s new corporate headquarters was built with water reclamation, solar power and other sustainable features and aims at a gold LEED (Leadership in Energy and Environmental Design) designation from the U.S. Green Building Council.

In assessing his career at the helm of ATC, Delgado said, “The transmission grid is in much better shape than when we started operations in 2001. That was one of the major reasons for our formation. We resolved the limitations affecting electric operations in our region, improving reliability and access, and delivering significant economic and environmental benefits, as well.”

He added, “On nearly 60 transmission line projects, ATC developed a reputation for communicating openly and treating the public fairly, and for our expertise in planning, siting and building transmission. Our employees have operated the system expertly as well. Now, John Procario and our staff are ready to take ATC to the next level.”

Prior to the formation of ATC, Delgado spent 27 years at Wisconsin Electric Power Co. (d.b.a. We Energies) starting as an electrical engineer and ending as vice president of Electric System Operations.

Delgado, a recognized leader in the electric industry, has served in numerous positions and organizations within the industry. He was the first chairman of the North American Electric Reliability Corp.’s Transmission Owners and Operators Forum. He has been co-chair of EEI’s CEO Reliability Committee and vice president of the Association of Edison Illuminating Companies. He also has served on the Industry Leaders Council of the Consortium for Electric Reliability Technology Solutions (the advisory board to the Department of Energy laboratories). He is a member of the Department of Energy’s Electric System Reliability Task Force.

Earlier, Delgado was president of MAIN, the former regional reliability council for eastern Wisconsin, Illinois and western Missouri, and a trustee of NERC, as well as other positions on committees within the utility industry.

He is an alumnus of Marquette University and the University of Wisconsin-Milwaukee.

]]>
http://www.atcllc.com/news/delgado-announces-retirement-from-american-transmission-co/feed/ 0
ATC applies for permission to build power line in Door County http://www.atcllc.com/news/atc-applies-for-permission-to-build-power-line-in-door-county/ http://www.atcllc.com/news/atc-applies-for-permission-to-build-power-line-in-door-county/#comments Wed, 18 Nov 2009 08:00:59 +0000 http://www.atcllc.com/?p=1072 Regulatory filing submitted to Public Service Commission of Wisconsin

DE PERE, Wis. – American Transmission Co. has filed an application with the Public Service Commission of Wisconsin to build a new eight- or nine-mile power line from Sturgeon Bay to a substation along Dunn Road in the Town of Sevastopol.

“The new line is needed to address electric transmission reliability issues in the Sturgeon Bay, Egg Harbor and Sister Bay areas,” explains David Hovde, senior local relations representative for ATC. “The two 69,000-volt lines that currently serve Door County leave the area vulnerable to outages when either line is out of service for repair or maintenance.”

ATC plans to add a new, 138,000-volt circuit to reinforce the system. Two route alternatives are described in the regulatory application. The proposed route follows the existing transmission line corridor from the Canal Substation southeast of downtown Sturgeon Bay to the Dunn Road Substation. The alternate route also follows the existing line for about five miles, then follows a new corridor to the Dunn Road Substation. ATC is required by state law to submit two route alternatives; the PSCW selects the route if the project is approved.

]]>
http://www.atcllc.com/news/atc-applies-for-permission-to-build-power-line-in-door-county/feed/ 0
ATC enters two long-term construction contracts http://www.atcllc.com/news/atc-enters-two-long-term-construction-contracts/ http://www.atcllc.com/news/atc-enters-two-long-term-construction-contracts/#comments Tue, 03 Nov 2009 08:00:31 +0000 http://www.atcllc.com/?p=1069 Agreements with MJ Electric, Henkels & McCoy worth $200 million over four years

PEWAUKEE, Wis. – American Transmission Co. recently signed contracts with two nationally recognized construction services firms for transmission line and substation work. Construction work will be divided evenly between Pennsylvania-based Henkels & McCoy, which will provide services primarily in ATC’s southern territory, and MJ Electric, a Quanta Services (NYSE: PWR) company, which will support projects in northern Wisconsin and Michigan’s Upper Peninsula.

“ATC has an ambitious plan that calls for $2.5 billion in infrastructure improvements over the next 10 years,” said Mike Rowe, ATC vice president for construction. “That is just within our footprint – a number of regional planning studies are underway to identify transmission infrastructure needs to help Midwestern states meet renewable energy portfolio requirements. We look forward to working with these demonstrated leaders in the energy construction industry to safely and reliably expand the transmission grid.”

Henkels & McCoy is a family-owned company in its third generation, recognized nationally as a premier provider of utilities services. “We are extremely enthusiastic about supporting ATC’s infrastructure improvement plans and its commitment to safety excellence and environmental awareness,” said Rod Henkels, Henkels & McCoy president and CEO. “We look forward to assisting ATC in meeting its objectives and satisfying the ongoing needs of its customers.”

MJ Electric, based in Iron Mountain, Mich., is part of Quanta Services, a nationwide leader of energy infrastructure solutions. The company recently concluded a long-term contract with ATC, which included work on more than 100 miles of transmission line projects in northern Wisconsin and the Upper Peninsula. “We are eager to again work with ATC and contribute to the success of its aggressive transmission infrastructure enhancements,” said Steve Reiten, president of MJ Electric. “The long-term relationship between the two companies illustrates our shared goals of service to our customers and the delivery of safe, economic solutions that address the nation’s energy problems.”

Under the agreements, the two companies will provide all construction resources, including labor, equipment and management strategies, to safely and cost-effectively implement ATC’s construction plans.

]]>
http://www.atcllc.com/news/atc-enters-two-long-term-construction-contracts/feed/ 0
U.S. Department of Energy selects American Transmission Co. applications for smart grid grants http://www.atcllc.com/news/u-s-department-of-energy-selects-american-transmission-co-applications-for-smart-grid-grants/ http://www.atcllc.com/news/u-s-department-of-energy-selects-american-transmission-co-applications-for-smart-grid-grants/#comments Tue, 27 Oct 2009 08:00:34 +0000 http://www.atcllc.com/?p=1066 PEWAUKEE, Wis. – The U.S. Department of Energy notified American Transmission Co. today that two ATC applications for smart grid investment grants totaling $12.7 million were selected for award negotiations. The grants to ATC are among 100 being made nationwide – totaling $3.4 billion – by the DOE to advance smart grid technologies.

One of ATC’s applications was for $1.3 million in funding to extend its use of phasor measurement units – a new technology for monitoring the status of the grid in real time. Earlier this year, ATC installed a limited number of the PMU devices on its system and evaluated their performance. The PMUs are considered one of the most important measuring devices of the future of power systems because they provide a wider, more integrated and time synchronized view of the system as a whole.

A second ATC application for $11.4 million was for funding to extend its use of fiber optics to improve communications between its electric substations and its system operations centers. ATC already has installed optical ground wire fiber on a number of its recent transmission construction projects. More widespread use of OPGW will provide ATC with a more secure and reliable data network infrastructure. The OPGW also provides a means to transmit information from the PMUs back to the operations centers.

“We are pleased that these two project applications were selected,” said John Procario, ATC president and chief executive officer. “The grants give us a means to proceed with these new technologies to improve our ability to monitor the grid and enhance the reliability of our infrastructure needed to help keep the lights on.”

]]>
http://www.atcllc.com/news/u-s-department-of-energy-selects-american-transmission-co-applications-for-smart-grid-grants/feed/ 0
American Transmission Co. studies show need for $2.5 billion in investment http://www.atcllc.com/news/american-transmission-co-studies-show-need-for-2-5-billion-in-investment/ http://www.atcllc.com/news/american-transmission-co-studies-show-need-for-2-5-billion-in-investment/#comments Wed, 21 Oct 2009 08:00:03 +0000 http://www.atcllc.com/?p=1059 Plans call for new lines, system upgrades and asset renewal

PEWAUKEE, Wis. – American Transmission Co. has completed its annual electric transmission system assessment and has identified $2.5 billion in necessary improvements over the next 10 years. The total includes $1 billion for transmission network upgrades, along with $1.5 billion in interconnection and asset renewal projects, infrastructure replacements and relocations, and other smaller network reliability improvements. That is down from the 2008 10-year assessment of $2.7 billion, although the current forecast may change due to regional initiatives to build transmission infrastructure to support renewable generation.

“While ATC has made significant progress since beginning operation in 2001, we continue our process to assess and reassess the needs of our customers to determine and evolve, over time, the best set of transmission projects to meet those needs,” explained Flora Flygt, director of transmission planning at ATC. “Now, more than ever, we are committed to an open, collaborative process to select best-value projects that resolve multiple electric system issues over a broad region.”

The $1 billion investment in new transmission infrastructure includes:

  • 131 miles of new transmission lines,
  • upgrades to more than 399 miles of existing lines and
  • 21 new transformers and 29 new capacitor banks.

The ATC report lists nine regional collaborative planning initiatives in which ATC is leading or participating, including the SMARTransmission Study to identify extra-high voltage transmission infrastructure needed to move wind power within a nine-state region from the Dakotas to Ohio, as well as the Regional Generator Outlet Study being conducted by the Midwest Independent System Operator.

“While our reliability performance data indicates that our system is performing well, we are including more detailed information in this year’s assessment to acknowledge how we manage the risk of aging infrastructure,” added Paul Roehr, ATC director of reliability and interconnections. Previous assessments have discussed near-term asset renewal efforts, but this year’s report provides more detail of potential projects through the full 10-year planning horizon. That work would include:

  • maintenance on aging equipment,
  • connections to power plants,
  • infrastructure replacements and relocations,
  • distribution interconnections and
  • other smaller network reliability improvements.

Since 2001, ATC has invested $2.1 billion in its transmission system, including:

  • upgrades to more than 1,400 miles of transmission line,
  • improvements at130 electric substations and
  • construction of 36 new transmission lines (476 miles).

These reliability projects have reduced energy losses on the system that equate to

  • 15.3 million megawatt hours of electricity saved (enough to power 35,500 homes each year),
  • 14.2 million tons of carbon-dioxide emissions eliminated (associated with producing lost energy) and
  • averting the need for a 122-megawatt generating plant to serve peak demand.

ATC’s 10-year Assessment is available online at www.atc10yearplan.com

]]>
http://www.atcllc.com/news/american-transmission-co-studies-show-need-for-2-5-billion-in-investment/feed/ 0
ATC completes 17-mile transmission line project in southeastern Wisconsin http://www.atcllc.com/news/atc-completes-17-mile-transmission-line-project-in-southeastern-wisconsin/ http://www.atcllc.com/news/atc-completes-17-mile-transmission-line-project-in-southeastern-wisconsin/#comments Wed, 14 Oct 2009 08:00:01 +0000 http://www.atcllc.com/?p=1057 Jefferson County Reliability Project energized earlier this week

PEWAUKEE, Wis. – Seventeen miles of new 138,000-volt transmission line that improves the reliability of the high-voltage electric system in Jefferson County and eastern Dane County was placed into service Monday.

“This new infrastructure is providing much needed reinforcement to a transmission system that has had no significant improvements in the past 15 years,” says Mary Carpenter, ATC local relations representative. “The new line can better accommodate electric load growth in the community, and it creates an alternate path for electricity to flow in the event of an outage on another portion of the network.”

The line connects the Stony Brook Substation in Waterloo to the Jefferson Substation located outside the city of Jefferson.

“We appreciate the involvement and cooperation of the residents as we worked through the siting and construction issues on this line,” says Terry Henn, ATC project manager.

The project was introduced to the public in 2004, approved by the Wisconsin Public Service Commission in July 2006 and construction began in October 2008. Construction crews worked more than 40,000 hours over a one-year period with an exceptional safety record. The final project cost $30 million, $3.7 million less than the approved budget.

Note to editors: Visit www.atc-projects.com for additional project information and a map of the project area.

]]>
http://www.atcllc.com/news/atc-completes-17-mile-transmission-line-project-in-southeastern-wisconsin/feed/ 0
American Transmission Co. and Rock Energy Cooperative hold second public outreach meeting to discuss routes for new power line http://www.atcllc.com/news/american-transmission-co-and-rock-energy-cooperative-hold-second-public-outreach-meeting-to-discuss-routes-for-new-power-line/ http://www.atcllc.com/news/american-transmission-co-and-rock-energy-cooperative-hold-second-public-outreach-meeting-to-discuss-routes-for-new-power-line/#comments Mon, 12 Oct 2009 08:00:31 +0000 http://www.atcllc.com/?p=1055 Open house will be Oct. 21 at The Gathering Place in Milton

PEWAUKEE, Wis. – Representatives from American Transmission Co. and Rock Energy Cooperative will host an open house to discuss route options for a new power line to serve the Milton area. The open house is scheduled for Wednesday, Oct. 21, at The Gathering Place, 715 Campus St., Milton. No formal presentation is planned; residents can drop in between 4 and 7 p.m. to speak with ATC and Rock Energy staff.

“The transmission line will bring power to a new Rock Energy Substation that will serve a growing need for reliable electric service in the area and support the continued growth of the Milton Industrial Park,” says Denny Schultz, representative of Rock Energy Cooperative.

ATC presented initial potential route options to the public during an open house in August, and based on input received, revised the options to include a potential route along a railroad corridor in the City of Milton. During the past few months, ATC has been evaluating possible routes for the line, including both the preliminary corridors presented to the public in August and the railroad corridor.

“It is our practice to work closely with the public to identify route options that result in the best possible solution for the project,” explains Jon Callaway, local relations representative for ATC. “Sometimes suggestions we receive help identify new segments that may not have been included during the early planning stages, as is the case with this project.”

Invitations have been mailed to landowners and businesses along all potential routes, and other members of the public are also welcome to attend. The open house is aimed at gathering feedback from those that may be affected by the new line.

Note to editor: A map of the project area is available on our Web site at www.atc-projects.com.

]]>
http://www.atcllc.com/news/american-transmission-co-and-rock-energy-cooperative-hold-second-public-outreach-meeting-to-discuss-routes-for-new-power-line/feed/ 0
ATC completes 104-mile transmission line project in central Wisconsin http://www.atcllc.com/news/atc-completes-104-mile-transmission-line-project-in-central-wisconsin/ http://www.atcllc.com/news/atc-completes-104-mile-transmission-line-project-in-central-wisconsin/#comments Mon, 05 Oct 2009 08:00:20 +0000 http://www.atcllc.com/?p=1053 Morgan-Werner West project energized last week

DE PERE, Wis. – The last portion of a project that substantially improves the reliability of the high-voltage electric system in central and northeast Wisconsin was placed into service recently.

“Energizing the final leg of the Morgan-Werner West 345-kilovolt line completes a five-year effort to expand capacity and improve reliability in the area,” said Stan Tessmer, project manager for ATC. “We began talking with the public about the need for these two, 50+-mile lines in early 2004, received regulatory authorization in 2006 and started construction in fall of that year.” The project included a line from the Gardner Park Substation near Wausau to a new substation along Highway 22 north of Clintonville, and a line from the Morgan Substation in Oconto County to a new substation (Werner West) near New London. About 75 miles of the project (from New London to Clintonville to Wausau) was placed in service ahead of schedule in June.

“During the summer, the new facilities increased the transmission capability of our network across central Wisconsin, and allowed us to perform maintenance and upgrade work on other lines in the area in a timely and efficient manner,” explained Francis Esselman, manager of regional reliability for ATC. “We saw additional improvements on the system when the last portion of the project was energized last week. Energizing the last segment reduced overall electrical losses by about 14 megawatts – the equivalent of eight large wind turbines.”

Note to editors: A project fact sheet follows with additional information.

]]>
http://www.atcllc.com/news/atc-completes-104-mile-transmission-line-project-in-central-wisconsin/feed/ 0
American Transmission Co. promotes Rusch to director of Accounting http://www.atcllc.com/news/american-transmission-co-promotes-rusch-to-director-of-accounting/ http://www.atcllc.com/news/american-transmission-co-promotes-rusch-to-director-of-accounting/#comments Wed, 02 Sep 2009 08:00:18 +0000 http://www.atcllc.com/?p=1051 PEWAUKEE, Wis. – Robert Rusch has been promoted to director of Accounting at American Transmission Co. effective immediately. Rusch will oversee General Accounting, Financial Reporting and Analysis, and Asset Accounting. He replaces Michael Hofbauer, who recently was promoted to chief financial officer.

Rusch joined ATC in 2008. His 25 years of experience includes positions at Alliant Energy primarily in the areas of finance and treasury, and at Arthur Andersen & Co. as an auditor.

Rusch holds bachelor’s and master’s degrees in business administration from the University of Wisconsin with an emphasis in accounting and finance. He also is a certified public accountant and chartered financial analyst.

Rusch is resident of Waunakee, Wis.

]]>
http://www.atcllc.com/news/american-transmission-co-promotes-rusch-to-director-of-accounting/feed/ 0
American Transmission Co. names Garvin general counsel http://www.atcllc.com/news/american-transmission-co-names-garvin-general-counsel/ http://www.atcllc.com/news/american-transmission-co-names-garvin-general-counsel/#comments Fri, 21 Aug 2009 08:00:37 +0000 http://www.atcllc.com/?p=1049 PEWAUKEE, Wis. – The board of directors of American Transmission Co. has elected Robert Garvin vice president, general counsel and corporate secretary effective Sept. 8, 2009. Garvin replaces Walter T. Woelfle, who announced in January his plans to retire this year.

Garvin most recently served as vice president of regulatory affairs for NextEra Energy Resources, a subsidiary of FPL Group; he also served as senior attorney in the FPL Law Department. At NextEra, Garvin was responsible for developing strategy and directing state regulatory and legislative advocacy efforts in 26 states.

Prior to joining NextEra, Garvin served as a commissioner on the Public Service Commission of Wisconsin. He was elected vice president of the Organization of MISO States. Garvin also served on the board of directors of the National Association of State Regulatory Commissioners and chaired its Nuclear Waste Subcommittee.

While on the PSC, Garvin was called to active duty and deployed as a staff judge advocate with the U.S. Army 3rd Corps Support Command, 40th Corps Support Group and returned from Iraq in September 2006.

Earlier in his career, Garvin was manager of legal and government affairs for Wisconsin Public Power Inc., and he was an associate attorney for Murphy and Desmond in Madison, Wis.

“We are delighted to have a talented professional like Bert join our executive team at an important stage in the company’s development,” said John Procario, president and chief executive officer. “Bert brings a breadth of legal, policy and regulatory experience, as well as the strong leadership skills needed to help move ATC forward.”

Garvin is a graduate of the University of Wisconsin and received his law degree from the University of Wisconsin.

]]>
http://www.atcllc.com/news/american-transmission-co-names-garvin-general-counsel/feed/ 0
American Transmission Co. and Rock Energy Cooperative to discuss preliminary routes for new power line http://www.atcllc.com/news/american-transmission-co-and-rock-energy-cooperative-to-discuss-preliminary-routes-for-new-power-line/ http://www.atcllc.com/news/american-transmission-co-and-rock-energy-cooperative-to-discuss-preliminary-routes-for-new-power-line/#comments Thu, 20 Aug 2009 08:00:36 +0000 http://www.atcllc.com/?p=1045 Open house will be Aug. 26 at The Gathering Place in Milton

PEWAUKEE, Wis. – Representatives from American Transmission Co. and Rock Energy Cooperative will be on hand to discuss preliminary route options for a new power line to serve the Milton area.

“The proposed transmission line is needed to serve a growing need for reliable electric service in the area and to support continued growth of the Milton Industrial Park,” says Denny Schultz, representative of Rock Energy Cooperative. “The line will connect Rock Energy’s planned Red Hawk Substation near Milton Harmony Townline Road and County Highway M to the transmission grid that serves the area.”

ATC mailed invitations to potentially affected landowners and businesses and is conducting the open house to solicit local feedback on siting the new line.

“Participation by Milton-area citizens in this process will be key in helping to identify the best solution,” explains Jon Callaway, local relations representative for ATC.

Residents are invited to drop in at the open house on Wednesday, Aug. 26, between 4 and 7 p.m. at The Gathering Place, 715 Campus St., Milton. No formal presentation is planned.

Note to editor: A map of the project area is available on our Web site a www.atcprojects.com.

]]>
http://www.atcllc.com/news/american-transmission-co-and-rock-energy-cooperative-to-discuss-preliminary-routes-for-new-power-line/feed/ 0
American Transmission Co. sponsors study of transmission options to move renewable energy across Upper Midwest http://www.atcllc.com/news/american-transmission-co-sponsors-study-of-transmission-options-to-move-renewable-energy-across-upper-midwest/ http://www.atcllc.com/news/american-transmission-co-sponsors-study-of-transmission-options-to-move-renewable-energy-across-upper-midwest/#comments Tue, 18 Aug 2009 08:00:38 +0000 http://www.atcllc.com/?p=1042 PEWAUKEE, Wis. – American Transmission Co., along with American Electric Power (NYSE: AEP), MidAmerican Energy Holdings Co. (MECH), Exelon Corp. (NYSE: EXC), NorthWestern Energy (NYSE:NWE), and MidAmerican Energy Co., a subsidiary of MEHC, is sponsoring a comprehensive study of the transmission infrastructure needed in the Upper Midwest to support renewable energy development and transport that energy to consumers in markets to the east. The study, known as the Strategic Midwest Area Renewable Transmission Study (SMARTransmission Study), gets under way immediately.

The sponsors have retained Quanta Technology LLC to evaluate extra-high voltage transmission alternatives and provide recommendations for new transmission development in the Upper Midwest, including North Dakota, South Dakota, Illinois, Indiana, Iowa, Minnesota, Ohio, Wisconsin and Michigan’s Upper Peninsula. Quanta will conduct an analysis of transmission alternatives analyzing the impact and quantifying the economic benefits of several transmission options. The SMARTransmission Study is scheduled for completion in January 2010, and results will be shared with the Midwest Independent Transmission System Operator and PJM Interconnection, the Regional Transmission Organizations operating in these states.

“The region under study has some of the richest renewable wind potential in the U.S.,” said John Procario, ATC president and chief executive officer. “Harvesting this Midwestern wind potential and bringing the resulting electric generation to market requires an upgrade to the transmission system in the heart of the nation. Studying the transmission options at the regional level is key to identifying the most economic options.”

Procario said, “The results of the SMARTransmission Study could further provide an input into the Upper Midwest Transmission Development Initiative and other studies – efforts we also support for determining the best options for transmission facilities to help states and the region meet renewable energy goals. And by participating in this and other studies, we can identify projects that will benefit all energy users in the Midwest.”

The outcome of the SMARTransmission Study in combination with other studies currently being performed by MISO will be used as input to the regional transmission planning processes and result in transmission projects being identified. Ultimately, RTOs and states must approve the scope and timing of any new transmission projects.

While the SMARTransmission Study will identify generally how new transmission facilities should interconnect with the existing system, it will not specifically identify any of the physical geographic routes.

The partners will provide opportunities for interested stakeholders to engage in the study.

]]>
http://www.atcllc.com/news/american-transmission-co-sponsors-study-of-transmission-options-to-move-renewable-energy-across-upper-midwest/feed/ 0
Rock and Walworth counties benefit from boost to electric transmission system http://www.atcllc.com/news/rock-and-walworth-counties-benefit-from-boost-to-electric-transmission-system/ http://www.atcllc.com/news/rock-and-walworth-counties-benefit-from-boost-to-electric-transmission-system/#comments Fri, 31 Jul 2009 08:00:40 +0000 http://www.atcllc.com/?p=1039 30-mile, multi-year, multi-phase project is complete and now operating at 138,000 volts

PEWAUKEE, Wis. – After more than five years of planning and construction, American Transmission Co. earlier this month completed conversion of 30 miles of transmission lines in Rock and Walworth counties to 138,000 volts to strengthen the electric system that serves the growing area.

The line, which runs from the Rock River Substation in the town of Rock to the Elkhorn Substation in the City of Elkhorn, replaces the existing 69,000-volt transmission system that served Rock and Walworth counties for several decades, but is no longer adequate to accommodate recent and future expected growth.

Most segments of the line were constructed in existing rights-of-way, and the work consisted of modifying and replacing existing structures and wires along with upgrades at several substations. ATC worked on the project in phases, converting the voltage on the line as sections were completed over a period of five months.

The final phase of the project involves removing several miles of existing 69,000-volt transmission facilities west and north of the City of Delavan, and between the Bristol and Lake Geneva substations. Some segments will remain and will continue to carry lower-voltage distribution wires owned by Alliant Energy and We Energies. This remaining work will be completed in the coming months.

“This is a significant milestone in our plan to improve the transmission system serving the area,” says Mary Carpenter, ATC local relations representative. ”Residents and business owners in Rock and Walworth counties will benefit from reliable electricity now and for years to come.”

“We appreciate the involvement and cooperation of the residents in the two counties as we worked through the siting and construction issues on this line,” says Andy Schaeve, ATC project manager. “This project was completed safely, on time and within budget.”

Editors: Additional project information and maps are available at www.atc-projects.com

]]>
http://www.atcllc.com/news/rock-and-walworth-counties-benefit-from-boost-to-electric-transmission-system/feed/ 0
American Transmission Co. names Hofbauer CFO http://www.atcllc.com/news/american-transmission-co-names-hofbauer-cfo/ http://www.atcllc.com/news/american-transmission-co-names-hofbauer-cfo/#comments Thu, 30 Jul 2009 08:00:40 +0000 http://www.atcllc.com/?p=1037 PEWAUKEE, Wis. – The board of directors of American Transmission Co. has elected Michael Hofbauer vice president, chief financial officer and treasurer effective immediately, with responsibilities for ATC’s financial, information technology and supply chain functions.

Hofbauer joined ATC as director of accounting operations in 2001 when the company was formed. In January 2007, he was promoted to corporate controller, overseeing all finance department activities including accounting, tax, financial reporting, budgeting, treasury and risk management. Hofbauer was named interim CFO in June 2009.

Prior to joining ATC, Hofbauer held various senior-level positions with Arthur Andersen, managing consulting engagements for the healthcare and products industries as well as state and local governments. Hofbauer also managed the corporate accounting function for Midway Airlines.

Hofbauer earned a bachelor’s degree in business administration from the University of Notre Dame and a master’s degree in business administration from the University of Chicago. He also is a certified public accountant.

“We are pleased to have Mike in this new role within our corporate leadership team,” said John Procario, president and chief executive officer. “He has demonstrated broad knowledge of the financial, operational and regulatory issues impacting ATC. Mike will be a strong addition to our executive team and will be critical in executing our growth strategy.”

Editors: Hofbauer photo attached

]]>
http://www.atcllc.com/news/american-transmission-co-names-hofbauer-cfo/feed/ 0
American Transmission Co. identifies power line options to help Midwestern states meet renewable energy goals http://www.atcllc.com/news/american-transmission-co-identifies-power-line-options-to-help-midwestern-states-meet-renewable-energy-goals/ http://www.atcllc.com/news/american-transmission-co-identifies-power-line-options-to-help-midwestern-states-meet-renewable-energy-goals/#comments Tue, 07 Jul 2009 08:00:04 +0000 http://www.atcllc.com/?p=1035 Potential line from La Crosse to Madison, Wis. demonstrating renewable, economic and reliability benefits

PEWAUKEE, Wis. – American Transmission Co., a proven leader in the planning, construction and operation of transmission infrastructure, has identified various new highvoltage transmission line projects that can help deliver renewable energy while also addressing reliability issues in the Midwest.

One potential project, an approximate 150-mile 345-kilovolt line between La Crosse and Madison in western Wisconsin, is anticipated to provide multiple benefits and address needs identified in other regional planning studies. ATC has begun coordinating with the Minnesota CapX2020 group, which is proposing a 345-kV line from Minneapolis/St. Paul into La Crosse that would need to connect to ATC’s transmission system at that point. ATC also is studying the benefits of a 345-kV line from Madison south to Dubuque, Iowa, and a 345-kV line from Wisconsin’s Fox River Valley (Green Bay and Appleton areas) north and south along Lake Michigan. ATC’s studies also will examine the viability of voltage levels at 765 kV.

Each of these projects could potentially help meet the Upper Midwest Transmission Development Initiative objective for interconnecting more renewable resources to help meet state, regional and national policy goals. UMTDI is the five-state group including Wisconsin, Minnesota, Iowa, North Dakota and South Dakota, which formed last year to identify how together they could meet their individual renewable energy goals and site and pay for the needed transmission infrastructure.

John Procario, ATC chief executive officer, said, “We’ve been studying the La Crosse –Madison line since last year, and it appears needed to move wind associated with UMTDI state renewable portfolio standards. But beyond that, La Crosse – Madison is showing economic benefits for ATC customers, and it further solves a number of regional and local reliability issues including in the Minneapolis/St. Paul metro area and western Wisconsin. And that’s why we are pursuing the development of this line further. We develop and examine best-value projects that resolve multiple system issues that also can help states and the region meet their policy goals.”

Procario said, “Within the next number of months, ATC will be actively engaged in public outreach on one or more of these projects. As has been our practice, this will be a stakeholder-driven process involving our customers, landowners, local officials and any others interested in engaging in the discussion about needs, routing and siting.”

ATC has been a participant in several regional planning groups to ensure the transmission system can deliver the energy needed to meet states’ renewable goals. In fact, UMTDI last week released maps showing that renewable energy zones to the west need a strong tie to Wisconsin to move the energy to market. “We applaud the work of the governors and regulatory bodies of the five UMTDI states in identifying renewable energy zones and laying the ground work for solving the difficult cost allocation issues associated with interstate transmission lines,” Procario said.

Other regional wind planning studies being conducted by the Midwest Independent Transmission System Operator and recommendations from Wisconsin Governor’s Task Force on Global Warming also identify the need for reliable transmission infrastructure in Wisconsin to help meet climate change initiatives.

As such, ATC’s transmission planning studies are centered in three general areas in Wisconsin that are proving to be a gateway for moving wind power from North Dakota, South Dakota, Minnesota and Iowa to load centers in Wisconsin as well as the Chicago area and other points to the east.

Since formed in 2001, ATC has invested more than $2 billion to build or upgrade 1,700 miles of transmission lines including the 220-mile interstate Arrowhead-Weston line, which runs from Wausau, Wis. to Duluth, Minn.

]]>
http://www.atcllc.com/news/american-transmission-co-identifies-power-line-options-to-help-midwestern-states-meet-renewable-energy-goals/feed/ 0
American Transmission Co. honored with EEI Edison Award http://www.atcllc.com/news/american-transmission-co-honored-with-eei-edison-award/ http://www.atcllc.com/news/american-transmission-co-honored-with-eei-edison-award/#comments Wed, 24 Jun 2009 08:00:36 +0000 http://www.atcllc.com/?p=1032 Company recognized for 220-mile Arrowhead-Weston transmission line

PEWAUKEE, Wis. – The Edison Electric Institute, the association of U.S. shareholder-owned electric companies, today awarded the industry’s highest honor, the Edison Award, to American Transmission Co. in recognition of its extraordinary work in completing the 220-mile Arrowhead-Weston transmission line ahead of schedule and within the approved budget.

“When construction of the Arrowhead-Weston line began in 2005, it was the largest transmission line project underway in the country,” said José Delgado, executive chairman of ATC. “The project initially faced considerable opposition, but we gradually earned the public’s trust to construct this vital piece of infrastructure.”

Construction on the project was completed – safely – seven months early and the line was put into service in January 2008, four months ahead of schedule. The project cost was $439 million, which was within the 5 percent contingency set by the Public Service Commission of Wisconsin. “Construction also was performed in an environmentally responsible manner,” Delgado said. “And we continue to monitor environmentally sensitive areas.”

In addition to providing increased reliability to the electric grid locally and regionally, the new line provides access to lower-cost electricity and improved capability to deliver it to customers. “We estimate savings of more than $5 million to electricity customers after the line’s first year of service,” Delgado said.

Note to editors: Additional information about the Arrowhead-Weston project is summarized in a Benefits Report available on: www.atcllc.com

]]>
http://www.atcllc.com/news/american-transmission-co-honored-with-eei-edison-award/feed/ 0
American Transmission Co. to discuss preliminary routes for new power line http://www.atcllc.com/news/american-transmission-co-to-discuss-preliminary-routes-for-new-power-line/ http://www.atcllc.com/news/american-transmission-co-to-discuss-preliminary-routes-for-new-power-line/#comments Wed, 24 Jun 2009 08:00:33 +0000 http://www.atcllc.com/?p=1025 Open house will be July 15 at Woodruff Town Hall

DE PERE, Wis. – Representatives from American Transmission Co. will be on hand to discuss preliminary route options for a new, seven-mile power line in the Minocqua-Woodruff area.

“The proposed Clear Lake-Woodmin transmission line is needed because local electricity use continues to increase at about three to four percent each year, which is taxing the distribution system operated by Wisconsin Public Service Corp.,” explains Lee Meyerhofer, senior local relations representative for ATC. “A new line extending the transmission system from the Clear Lake Substation on Highway 47 near Mid Lake Road to a new substation proposed by WPS along Highway 47 near Arnett Road west of Woodruff appears to be the best solution for future reliability.”

ATC has conducted two previous open houses to solicit local feedback on siting the new line. “We appreciate the time and effort of local residents to participate in the development of this project,” Meyerhofer says.

Residents are invited to drop in at the open house on July 15 at the Woodruff Town Hall, 1418 First Ave., between 1 and 3 pm or 5 and 7 pm. No formal presentation is planned.

Note to editor: A map of the project area is available on our projects website.

 

]]>
http://www.atcllc.com/news/american-transmission-co-to-discuss-preliminary-routes-for-new-power-line/feed/ 0
American Transmission Co. receives regulatory approval for Dane County electric transmission line project http://www.atcllc.com/news/american-transmission-co-receives-regulatory-approval-for-dane-county-electric-transmission-line-project/ http://www.atcllc.com/news/american-transmission-co-receives-regulatory-approval-for-dane-county-electric-transmission-line-project/#comments Thu, 11 Jun 2009 08:00:27 +0000 http://www.atcllc.com/?p=1023 Route for Rockdale-West Middleton line to follow Beltline

MADISON, Wis. – After more than five years of public involvement and regulatory review, the Public Service Commission of Wisconsin today verbally approved a vital addition to Dane County’s electric transmission system. American Transmission Co. will build a new 32-mile, 345,000-volt electric transmission line through Dane County between the towns of Middleton and Christiana along a route that generally follows the Beltline and existing rights of way, and does not include placing the line underground.

“We are pleased that the PSC agreed with our assessment of this much-needed transmission line,” said Sarah Justus, ATC local relations manager. “This is a critically important project for the Dane County region. This regulatory approval is good news for homeowners, businesses and industries that depend upon a reliable electric system.”

ATC first identified the need for the project in 2002. In 2003, the project need was independently reviewed by the Energy Initiative, a group of Wisconsin utilities, public advocacy organizations, environmental groups and local stakeholders. The group evaluated the need for new electric transmission lines and the feasibility of alternatives in meeting Dane County’s present and future electric needs.

Before filing an application with the PSC in October 2007, ATC conducted extensive public outreach. “Over a five-year period we hosted 22 open houses attended by more than 3,300 people, and regularly corresponded with more than 13,000 Dane County residents, businesses and other stakeholders in an effort to address public concerns,” says Justus. “We appreciate the involvement of the public in helping to shape the decisions related to this project, and we are committed to keeping this dialogue open as we move forward.”

In discussing the Rockdale-West Middleton transmission line today, the PSC asked ATC for design changes at locations along the route including near the Arboretum, Odana Hills Golf Course and the area near High Point Road. These design changes add approximately $1.2 million to the cost of the project, which is now at just over $215 million.

With receipt of the PSC’s approval, the next steps include ATC conducting detailed engineering and easement acquisition. “We will continue to communicate with affected landowners throughout this process, both by mail and by hosting information meetings as we begin construction,” says Justus.

Construction on the project is expected to begin in summer 2011, and the line is expected to be in service in 2013.

]]>
http://www.atcllc.com/news/american-transmission-co-receives-regulatory-approval-for-dane-county-electric-transmission-line-project/feed/ 0
New substation boosts power to Fitchburg http://www.atcllc.com/news/new-substation-boosts-power-to-fitchburg/ http://www.atcllc.com/news/new-substation-boosts-power-to-fitchburg/#comments Tue, 09 Jun 2009 08:00:50 +0000 http://www.atcllc.com/?p=1018 MADISON, Wis. — The new Oak Ridge Substation in Fitchburg was energized and began serving local customers ahead of schedule last month. The substation is part of a larger project in progress by American Transmission Co. and Madison Gas and Electric to strengthen electric system reliability in the area.

“Placing this new substation in service is a culmination of the efforts of ATC and MGE during the last five years,” says Craig Fenrick, assistant vice president, Electric Transmission and Distribution for MGE. “This new substation will help ensure that peak summer demand for power can be met.”

The substation was energized two weeks ahead of schedule and marks the halfway point of a larger, $22.6 million project under way to strengthen and maintain the reliability of the electric system serving southern Dane and northern Green counties.

During the next phase of the project, ATC will construct a 6-mile, 138,000-volt transmission line to connect the new substation to an existing substation in Verona located near the intersection of Highways M and PB. Construction is scheduled to begin in early August, and the entire project is projected to be in service in the first quarter of 2010.

“With the addition of this new substation, customers in Fitchburg and the surrounding area have already begun to benefit from this project,” says Charlie Gonzales, ATC local relations representative. “And when the entire project is complete the region will continue to benefit from a strengthened electric transmission system for years to come.”

Note to editor: A project area map and additional information about this and other ATC projects is available at atc-projects.com.

]]>
http://www.atcllc.com/news/new-substation-boosts-power-to-fitchburg/feed/ 0
Hofbauer named interim chief financial officer and treasurer http://www.atcllc.com/news/hofbauer-named-interim-chief-financial-officer-and-treasurer/ http://www.atcllc.com/news/hofbauer-named-interim-chief-financial-officer-and-treasurer/#comments Tue, 09 Jun 2009 08:00:07 +0000 http://www.atcllc.com/?p=1020 Mike Hofbauer today was named interim chief financial officer and treasurer of American Transmission Co., following the resignation of Dan Doyle.

Hofbauer joined ATC in 2000 as director of accounting and has served as corporate controller since 2006. Prior to ATC, Hofbauer was a senior manager with Arthur Andersen LLP in Chicago. He is a certified public accountant with a bachelor’s degree in business administration from the University of Notre Dame and a master’s degree in business administration from the University of Chicago.

]]>
http://www.atcllc.com/news/hofbauer-named-interim-chief-financial-officer-and-treasurer/feed/ 0
American Transmission Co. receives approval to rebuild transmission line between Brodhead and Monroe http://www.atcllc.com/news/american-transmission-co-receives-approval-to-rebuild-transmission-line-between-brodhead-and-monroe/ http://www.atcllc.com/news/american-transmission-co-receives-approval-to-rebuild-transmission-line-between-brodhead-and-monroe/#comments Fri, 05 Jun 2009 08:00:07 +0000 http://www.atcllc.com/?p=1009 Rebuilt line will strengthen electric system reliability

MADISON, Wis. – The Public Service Commission of Wisconsin has approved American Transmission Co.’s application to rebuild the 18-mile, 69,000-volt electric transmission line that connects the Brodhead Substation and South Monroe Substation in Monroe. The new line will make a vital improvement in the reliability of the electric transmission system serving the area. The age and condition of the existing line necessitated the rebuild.

“This project will not change the voltage of the line,” says Charlie Gonzales, ATC local relations representative, “but the replacement structures will be designed to accommodate potential upgrades that might be needed in the future to support growth in the area.”

The new line will follow the route of the existing line, and the work will involve installing new poles, wires and insulators. Construction is scheduled to begin late next year and is projected to continue through summer 2011.

Note to editor: A map of the project area is available on our projects website.


 

]]>
http://www.atcllc.com/news/american-transmission-co-receives-approval-to-rebuild-transmission-line-between-brodhead-and-monroe/feed/ 0
ATC energizes new high-voltage line in Outagamie, Shawano and Marathon counties http://www.atcllc.com/news/atc-energizes-new-high-voltage-line-in-outagamie-shawano-and-marathon-counties/ http://www.atcllc.com/news/atc-energizes-new-high-voltage-line-in-outagamie-shawano-and-marathon-counties/#comments Fri, 05 Jun 2009 08:00:04 +0000 http://www.atcllc.com/?p=1013 345-kilovolt line is among highest-capacity in the state

DE PERE, Wis. — Completing the construction ahead of schedule, American Transmission Co. recently placed into service 75 miles of a 345-kilovolt power line between the Werner West Substation near New London to the Gardner Park Substation adjacent to the Weston Power Plant near Wausau. The line also passes through a new substation located along Highway 22 north of Clintonville,

“This is a significant milestone in our transmission system improvement plan,” notes Brad Ballard, ATC project manager. “We began discussing our plans to build 104 miles of transmission lines in early 2004, received regulatory authorization in 2006 and started construction in fall of that year.” Construction work is continuing in Shawano County between the Highway 22 and the White Clay substations in the Town of Washington. That segment is the last portion of the Morgan-Werner West line and is scheduled for an on-time completion later this year. Previously this year, a new 138-kV line was energized from Werner West to the Badger Substation, located adjacent to the Highway 22 facility.

“While putting the line into service is a significant achievement, it may be more important to note that the work was performed safely and in an environmentally responsible fashion,” Ballard says. “We have had just one lost-time accident in the more than two years we’ve been working on the project. Detailed construction management plans were developed for each job spread, highlighting individual or unique natural resource features that should be avoided, and describing specific restoration practices to minimize the impact of our presence in the corridor.”

The two new lines are needed to more fully support a new generator at the Weston Power Plant that went into service last year and to relieve congestion on lines in and around the Green Bay and Fox Valley areas. The Public Service Commission of Wisconsin authorized the projects at a combined cost of $263 million, within a 10-percent window.


 

]]>
http://www.atcllc.com/news/atc-energizes-new-high-voltage-line-in-outagamie-shawano-and-marathon-counties/feed/ 0
New transmission line energized in northern Dane County http://www.atcllc.com/news/new-transmission-line-energized-in-northern-dane-county/ http://www.atcllc.com/news/new-transmission-line-energized-in-northern-dane-county/#comments Fri, 24 Apr 2009 08:00:33 +0000 http://www.atcllc.com/?p=1002 Nine-mile line will provide critical reinforcement to area’s electric system

MADISON, Wis. –American Transmission Co. energized a new 138,000-volt transmission line earlier this week serving northern Dane County. The new line connects the North Madison Substation in the Town of Vienna to the Huiskamp Substation in the Town of Westport and will provide a critical reinforcement to the electric system in Dane County, where demand for electricity has grown significantly in recent years.

Prior to the building of this line, portions of Middleton, Dane, Waunakee, Vienna, Westport and the northeast side of Madison were supported primarily by a network of 69,000-volt transmission lines. Some of the lines were built more than 90 years ago and many were used to near-maximum capacity during the peak summer season for several years, making communities in the area vulnerable to outages.

“The benefits of this line in the area will be evident immediately,” said Sarah Justus, ATC local relations manager. “Last summer, limited capacity threatened to overload the system, requiring that temporary equipment and operational fixes be employed to help maintain electric service during hot, high-demand days.”

According to Justus, the system was projected to experience overloaded conditions this summer if the line was not placed in service. Additionally, system constraints provided only limited opportunity to take existing lines out of service for maintenance, further compromising reliability and increasing operating costs. “The addition of this new 138,000-volt line provides vital strengthening to the transmission system that serves the area, which is now well-positioned to maintain reliable electric service and accommodate future growth,” Justus notes.

Although construction is completed and the line is in service, work still remains on the project. “While we take great measures to avoid sensitive areas and minimize the impact of construction,” says Justus, “we want area residents to know we are committed to restoring the corridor after construction, and maintaining it in coming years.”

The project was first announced to local officials and residents in fall 2005. “We appreciate the patience and support we have received from the community during this important project,” says Justus. “We received approval by the Public Service Commission of Wisconsin in July 2007, and began construction in spring 2008. The input and involvement of the community has made a difference every step of the way.”

Note to editor: Maps of the project area are available on our web site.

]]>
http://www.atcllc.com/news/new-transmission-line-energized-in-northern-dane-county/feed/ 0
Walworth County to benefit from voltage boost to electric transmission line http://www.atcllc.com/news/walworth-county-to-benefit-from-voltage-boost-to-electric-transmission-line/ http://www.atcllc.com/news/walworth-county-to-benefit-from-voltage-boost-to-electric-transmission-line/#comments Mon, 23 Mar 2009 08:00:57 +0000 http://www.atcllc.com/?p=1000 First 10 miles of 30-mile, multi-year, multi-phase system upgrade now operating at 138,000 volts

PEWAUKEE, Wis. – After more than five years of planning and construction, American Transmission Co. last week completed conversion of 10 miles of transmission lines in Walworth County to 138,000 volts. The voltage conversion is the first phase in ATC’s 30-mile conversion project in Rock and Walworth counties that will strengthen the electric system that serves the growing area.

The eastern segments of the project, from the Elkhorn Substation located in the City of Elkhorn to the Bristol Substation and extending to the Southwest Delavan Substation located outside of Delavan, are now energized and operating at 138,000 volts. The remaining 22 miles of western segments of this multi-year, multi-phase system upgrade will continue to operate at 69,000 volts until ATC completes construction and upgrades this summer.

“This is a key milestone in the project and immediately benefits residents and business owners in Walworth County,” said Mary Carpenter, local relations representative. “We are eager to complete the remaining work on the western segments and complete the entire conversion this summer.”

According to Carpenter, the remaining effort includes work on several substations in Rock County, modifications to some existing lines, and the replacement of an existing line through the City of Delavan between the Bristol and Delavan substations. “Crews will begin the work in Delavan next week and will wrap up in June,” she said.

The final phase of the project, which will begin this summer, includes removing several miles of existing 69,000-volt lines that will be retired once the conversion is complete. These include a line north of the City of Delavan and a line between the Bristol Substation and Lake Geneva.

Note to editor: Maps showing the entire project area or individual segments are available at www.atc- projects.com.

]]>
http://www.atcllc.com/news/walworth-county-to-benefit-from-voltage-boost-to-electric-transmission-line/feed/ 0
Report outlines reliability, environmental, economic benefits of American Transmission Co.’s Arrowhead-Weston line http://www.atcllc.com/news/report-outlines-reliability-environmental-economic-benefits-of-american-transmission-co-%e2%80%99s-arrowhead-weston-line/ http://www.atcllc.com/news/report-outlines-reliability-environmental-economic-benefits-of-american-transmission-co-%e2%80%99s-arrowhead-weston-line/#comments Mon, 02 Mar 2009 08:00:30 +0000 http://www.atcllc.com/?p=998 PEWAUKEE, Wis. – One year after the 220-mile Arrowhead-Weston transmission line from Wausau, Wis. to Duluth, Minn. was completed and energized, American Transmission Co. has issued a report outlining the reliability, environmental and economic benefits of the line to communities and electricity users in Wisconsin and the Upper Midwest.

The 345-kilovolt Arrowhead-Weston transmission line:

  • strengthens electric system reliability by bringing 600 megawatts of electricity into northern and central Wisconsin,
  • provides alternate source of power for the region increasing transfer capability and stability to the electric system,
  • allows utilities greater participation in the regional energy market,
  • gives green energy greater access to consumer markets,
  • is more efficient and reduces energy losses over the 40-year life of the line:
    • saving 5.7 million megawatt hours of electricity – enough to power to 13,000 homes each year,
    • eliminating more than 5.3 million tons of carbon dioxide emissions from power plants that do not have to run,
  • provides $62 million in direct payments to the communities through which the line passes over the 40-year life of the line.

Construction of the line was completed ahead of schedule allowing ATC to energize the line four months early in January 2008. All costs have been finalized, and ATC closed its books on the project notifying the Public Service Commission of Wisconsin that the final cost was $436 million, within the 5 percent allowable contingency set by the PSCW.

“Arrowhead-Weston has met all the reliability needs that provoked its justification and approval during the permitting process,” said José Delgado, ATC president and chief executive officer. “In addition, it provides very significant environmental and economic benefits to the area we serve. It provides an outstanding value to the consumers in our service area.”

Arrowhead-Weston is the largest construction project that ATC has completed in its eight-year history. ATC has invested more than $2 billion to build, upgrade and energize more than 1,700 miles of transmission line to help improve the reliability of the grid in the Upper Midwest. In addition to reliability benefits, a more efficient high-voltage transmission system has contributed to energy savings and avoided carbon emissions. The more robust system has helped reduce electrical demand at peak times equivalent to that of a 125-megawatt generating plant. Over the life span of a more efficient transmission system, 15 million tons of carbon dioxide emissions from a generating plant are avoided.

The Arrowhead-Weston Benefits Reports can be accessed from: www.atcllc.com

]]>
http://www.atcllc.com/news/report-outlines-reliability-environmental-economic-benefits-of-american-transmission-co-%e2%80%99s-arrowhead-weston-line/feed/ 0
ATC names Procario to succeed retiring CEO Delgado http://www.atcllc.com/news/atc-names-procario-to-succeed-retiring-ceo-delgado/ http://www.atcllc.com/news/atc-names-procario-to-succeed-retiring-ceo-delgado/#comments Wed, 21 Jan 2009 08:00:41 +0000 http://www.atcllc.com/?p=996 PEWAUKEE, Wis. – John C. Procario, formerly with Cincinnati-based Cinergy, has been selected as president and chief executive officer of American Transmission Co. – the successor to José M. Delgado.

Delgado, who announced a year ago his intention to transition into retirement, has been ATC’s president and CEO since the company’s formation in 2000. Delgado will become executive chairman of the board when Procario joins ATC on April 1, 2009. Procario will report to Delgado.

Procario spent 32 years with Cinergy, now part of Duke Energy. Procario most recently served as senior vice president and chief operating officer of Regulated Businesses for Cinergy Services, Inc. During his tenure with Cinergy, he also held leadership roles in Electric Operations, Electric System Operations, Bulk Power Resource Management, and Planning and Technical Services.

For more than 30 years, Procario has been a part-time college professor at the University of Cincinnati where he developed electric power engineering courses and taught more than 100 classes in electrical engineering.

Within the electric industry, Procario has served on numerous committees including the North American Electric Reliability Corp. Engineering Committee, North American Energy Standards Board, and as chairman of the Midwest ISO’s Management Council, Transmission Owners Committee and Advisory Committee.

Procario earned bachelor’s and master’s degrees in electrical engineering from The Ohio State University.

]]>
http://www.atcllc.com/news/atc-names-procario-to-succeed-retiring-ceo-delgado/feed/ 0
New electric transmission line proposed for area http://www.atcllc.com/news/new-electric-transmission-line-proposed-for-area/ http://www.atcllc.com/news/new-electric-transmission-line-proposed-for-area/#comments Tue, 28 Oct 2008 08:00:34 +0000 http://www.atcllc.com/?p=994 Project needed to ensure local-area reliability

DE PERE, Wis. — American Transmission Co. is in the early stages of planning a new power line project to improve electric reliability in the Minocqua-Woodruff area. Local electricity use continues to increase at about three to four percent each year, which is taxing the distribution system operated by Wisconsin Public Service Corp. A new line extending the transmission system from the Clear Lake Substation on Highway 47 near Mid Lake Road to a new substation proposed by WPS along Highway 47 near Arnett Road west of Woodruff appears to be the best solution for future reliability.

“We are in the preliminary stages of this project,” explains Lee Meyerhofer, senior local relations representative for ATC. “We have identified a broad study area to look for possible corridors or routes to locate this line, which will be about seven miles long.”

ATC will host a series of public open houses to discuss the project with community members before filing its regulatory application with the Public Service Commission of Wisconsin in late 2009. The first open house is scheduled for Thursday, Nov. 13, at the Woodruff Town Hall, 1418 First Ave. from 1 to 3 pm and from 5 to 7 pm.

“The open house will be informal,” Meyerhofer said. “No presentations are scheduled; we ask that interested residents drop in to talk with our project team members.” Representatives from ATC and Wisconsin Public Service will be on hand to answer questions regarding project need and benefits, routing and siting, the regulatory review process, engineering considerations, environmental impacts and other issues.

Additional information about this project, known as the Clear Lake-Woodmin transmission line project, is available online at www.atc-projects.com

]]>
http://www.atcllc.com/news/new-electric-transmission-line-proposed-for-area/feed/ 0
Schrader elected to American Transmission Co. board of directors http://www.atcllc.com/news/schrader-elected-to-american-transmission-co-board-of-directors/ http://www.atcllc.com/news/schrader-elected-to-american-transmission-co-board-of-directors/#comments Fri, 26 Sep 2008 08:00:28 +0000 http://www.atcllc.com/?p=992 St. Paul-based health care system executive fills ATC board vacancy

PEWAUKEE, Wis. – Ann M. Schrader, chief operating officer of HealthEast Care System, has been elected to the board of directors of American Transmission Co. HealthEast is one of the largest health care providers in the Twin Cities metropolitan area with four hospitals, 1,300 physicians and a network of neighborhood clinics. Schrader replaces former Wisconsin Governor Anthony Earl, who is retiring from the ATC board.

“Ann is a capable executive who facilitated the creation of HealthEast, transforming it from a hospital-driven company to a comprehensive care system,” explains ATC President and Chief Executive Officer José M. Delgado. “We welcome Ann’s strong leadership capabilities to our board.”

A native of Spirit Lake, Iowa, Schrader holds a bachelor’s of science degree in nursing from St. Olaf College and a master’s degree from the University of Iowa. She also received a Bush Fellowship to the Minnesota Executive Development Program through the Carlson School of Management at the University of Minnesota.

Earl, a former Wisconsin governor, attorney and former partner in the Quarles & Brady law firm, has served on the ATC board of directors since its inception in 2001. “I thank Tony for his counsel and service to the board as we grew this company from concept to a high-performing transmission service provider,” Delgado said.

]]>
http://www.atcllc.com/news/schrader-elected-to-american-transmission-co-board-of-directors/feed/ 0
ATC’s transmission system studies show need for $2.7 billion in upgrades http://www.atcllc.com/news/atc%e2%80%99s-transmission-system-studies-show-need-for-2-7-billion-in-upgrades/ http://www.atcllc.com/news/atc%e2%80%99s-transmission-system-studies-show-need-for-2-7-billion-in-upgrades/#comments Thu, 25 Sep 2008 08:00:44 +0000 http://www.atcllc.com/?p=990 System reliability improved; weak areas and renewable energy demands draw attention

WAUKESHA, Wis. – American Transmission Co. identifies in its 2008 10-Year Transmission System Assessment report ( www.atc10yearplan.com ) an estimated $2.7 billion in work needed over the next 10 years to ensure that the transmission grid can reliably meet the electricity needs of people and businesses in communities throughout most of Wisconsin and Michigan’s Upper Peninsula. This is in addition to the $1.9 billion that ATC has invested in the transmission system over the past seven years.

“We’ve made major progress in improving electric system reliability in our first seven years as owner and operator of the transmission grid,” said Flora Flygt, director of ATC Transmission Planning. “Some pockets of vulnerability remain, notably Dane and Walworth counties and the Green Bay, Appleton and Rhinelander areas. In these locales, low voltages and overloaded facilities must be addressed to maintain future system reliability. New and upgraded infrastructure will be needed.”

She added, “We also have to address the infrastructure needs of adding more wind power onto the grid. Building new interstate high-voltage transmission lines with the strategic location and capacity to deliver large volumes of renewable power from remote areas where it’s located into population centers will be a central challenge for years to come.”

Of the $2.7 billion investment that ATC identified in its 2008 Assessment, approximately $1.3 billion would be for new equipment including:

  • adding 210 miles of new transmission lines,
  • upgrading more than 540 miles of existing lines and
  • installing more than 23 new transformers and 39 capacitor banks.

The remaining $1.4 billion would be for improvements including:

  • maintenance on aging equipment
  • connections to power plants
  • infrastructure replacements and relocations
  • distribution interconnections and
  • other smaller network reliability improvements

The $2.7 billion is a slight decline from the $2.8 billion estimate ATC made in its 2007 10-Year Transmission Assessment update, and it’s the third consecutive year of a decline. Flygt said, “This trend represents a historical shift from building new facilities to maintaining the assets we have. However,” she cautioned, “several developments could well cause that trend to reverse in future assessments, including new renewable energy requirements and the resulting shift in generation usage, the expected adoption of higher federal reliability standards and fundamental changes in regional power flows across the Midwest as the wholesale market continues to evolve.”

ATC’s investments since its inception in 2001 have helped to raise the transmission system’s performance in meeting peak demand, supporting a new fleet of generation, increasing import capability, interconnecting wind projects, reducing energy losses, alleviating system overloads and voltage instabilities, and improving system reliability ratings.

Since 2001, ATC has invested more than $1.9 billion in improvements to the power grid including:

  • upgrading more than 1,350 miles of transmission lines,
  • connecting more than 4,300 megawatts of new or expanded generation including 391 megawatts of wind power,
  • improving 110 electric substations,
  • building 32 new transmission lines totaling 344 miles, and
  • reducing energy losses by 16.2 million megawatt hours, enough to power 38,000 homes per year for 40 years.

ATC takes a fresh look at the future needs of the transmission system every year, and identifies and begins to prioritize potential projects that may be needed to ensure electric system reliability. ATC engineers analyze the system for changes in the various factors impacting electric system needs such as electricity usage, capacity of the system to meet those usage levels, population projections, employment trends, and anticipated generation expansion or retirement.

“We reassess our system every year,” Flygt says, “because conditions change continuously and new project needs can appear both in the near term and out on our 10-year horizon. By continuously evaluating system conditions, we are in the best position to propose and substantiate needed projects.”

]]>
http://www.atcllc.com/news/atc%e2%80%99s-transmission-system-studies-show-need-for-2-7-billion-in-upgrades/feed/ 0
American Transmission Co. to begin construction on cost-saving power line http://www.atcllc.com/news/american-transmission-co-to-begin-construction-on-cost-saving-power-line/ http://www.atcllc.com/news/american-transmission-co-to-begin-construction-on-cost-saving-power-line/#comments Thu, 28 Aug 2008 08:00:33 +0000 http://www.atcllc.com/?p=988 Line will enable high-voltage connection to regional generation sources

MADISON, Wis. – American Transmission Co. will begin construction in early September of a new, 35-mile high-voltage electric transmission line in south central Wisconsin. The line will allow local electric distribution companies to access lower-cost power produced in the region by extending an existing transmission connection to Illinois.

“By reducing transmission congestion and increasing transfer capacity, this project will improve access to lower-cost energy,” said Mary Carpenter, ATC local relations. “We will do our best to inform landowners of the impact of our work, while keeping disruptions to a minimum as we complete the project.”

The line is the first of its kind in the Midwest. Until this project, transmission lines in the region have almost exclusively been built to enhance reliability of electrical power in the area. Although improved reliability will be a by-product of the project, economics drove the decision to build. Local electric utilities will save through improved access to the wholesale electricity market and their savings will be passed on to end-use electricity customers.

The 345-kilovolt circuit will be built on an existing transmission line right-of-way between the Rockdale Substation in the Town of Christiana in Dane County and the Paddock Substation located in the Town of Beloit in Rock County. The lines that extend south out of the Paddock Substation into Illinois create a path for importing power into Wisconsin.

Construction will begin with preparation of the rights-of-way for the line with tree trimming and pouring the foundations for the poles and is projected to be in service in 2010.

Anticipated savings from the approximately $133 million project are expected to more than pay for its development.

Note to editors: A map and additional information on the Paddock-Rockdale project is available at www.atc-projects.com

ATC’s other proposal for a 345-kilovolt line between the Rockdale Substation and the West Middleton Substation in the town of Middleton (Rockdale – West Middleton project) is under regulatory review. A decision on the project is expected sometime in 2009.

]]>
http://www.atcllc.com/news/american-transmission-co-to-begin-construction-on-cost-saving-power-line/feed/ 0
American Transmission Co. energized a new power line in Walworth County http://www.atcllc.com/news/american-transmission-co-energized-a-new-power-line-in-walworth-county/ http://www.atcllc.com/news/american-transmission-co-energized-a-new-power-line-in-walworth-county/#comments Tue, 26 Aug 2008 08:00:47 +0000 http://www.atcllc.com/?p=986 Five-mile power line along Interstate 43 is part of a 30-mile, multi-phase system upgrade

PEWAUKEE, Wis. – A new, 5-mile power line is energized and providing support to the electric system serving Walworth County, according to American Transmission Co.

The new line, which runs between the Southwest Delavan Substation and the Bristol Substation on the northeast side of Delavan, represents a portion of a larger, multi-phase, multi-year project that will convert the electric transmission system in Rock and Walworth counties from 69,000 volts to 138,000 volts.

“These growing counties require a more robust system to accommodate the increasing usage and population,” said Charlie Gonzales, local relations representative. “The new system, which runs from north of Beloit to the Lake Geneva area, involves constructing new lines and modifying several substations and existing transmission lines to reinforce the network and ensure reliable service.”

According to Gonzales, the route along Interstate 43 was suggested by members of the public when ATC was considering potential routes. “With input from the community, we arrived at a route that could be supported by its residents and still meet our needs to reinforce the system in the area,” he explained.

Work continues on a segment through the city of Delavan and on a section between Delavan and Elkhorn, along with some work on the west end of the project. “We’re targeting next summer for completion and conversion to the higher voltage,” said Gonzales.

In addition to energizing the Southwest Delavan to Bristol line last week, the following work has been completed:

Turtle to West Darien: Modifications have been completed on this existing 18-mile, 69-kilovolt line to allow for conversion to 138-kV. Aging wood poles and wires between the Turtle Substation near Beloit and the West Darien Substation on the southwest side of Darien were replaced with steel poles and new wires.

West Darien to Southwest Delavan: This line, constructed mostly along new right-of-way, connects the West Darien Substation to a new Alliant Substation southwest of Delavan. Completed in 2007, the line currently operates at 69-kilovolts, but will be converted to 138-kV.

Note to editor: Maps available showing entire project area or individual segments.

]]>
http://www.atcllc.com/news/american-transmission-co-energized-a-new-power-line-in-walworth-county/feed/ 0
ATC transmission improvements double as major energy efficiency upgrades http://www.atcllc.com/news/atc-transmission-improvements-double-as-major-energy-efficiency-upgrades/ http://www.atcllc.com/news/atc-transmission-improvements-double-as-major-energy-efficiency-upgrades/#comments Mon, 28 Jul 2008 08:00:53 +0000 http://www.atcllc.com/?p=984 Impact of energy savings on grid equivalent to combustion turbine; carbon emissions reduced

WAUKESHA, Wis. – American Transmission Co.’s $1.7 billion investment in reliability and efficiency upgrades to the transmission grid over the past seven years also has contributed to energy savings and reduced carbon emissions. In figures released today, ATC demonstrates that its more robust high-voltage transmission system has helped reduce electrical output at peak times equivalent to a 125-megawatt generating plant.

“Our investment may be one of the largest energy savings programs in the Upper Midwest,” said José Delgado, ATC president and chief executive officer. “The more efficient high-voltage lines and newer infrastructure that we’ve placed in service results in lower line losses. We can translate this into significant environmental benefits. With the recent approval of the final report by Wisconsin Governor Jim Doyle’s Task Force on Global Warming, this is good news.”

Flora Flygt, director of ATC Transmission Planning, explained, “Transmission system improvements also function as major energy efficiency upgrades on the electric system because of the sheer volume of energy they carry. Even a small increase in the efficiency of the grid’s power-carrying capabilities can yield significant energy-saving and carbon-reducing results.”

She said the savings are due to reduced electricity losses. “In simple terms, our improvements mean that the wires do not get as hot, which results in substantially lower electricity losses in the process of moving power into communities,” said Flygt.

Lower losses between the generation source and the delivery point mean a reduction in the required electricity output needed to transport power and meet demand. If the generation source is a fossil-fueled power plant, the result is lower carbon emissions. Losses on ATC’s high-voltage network are relatively low at around 2.2 percent of energy carried.

ATC’s energy savings calculation compares the company’s system as it was in summer 2001 with the improved system in place by summer 2007. The reduced losses over the 40-year life of these projects equate to:

  • 16.2 million megawatt hours of electricity saved (enough to power 38,000 homes each year).
  • 15 million tons of CO2 emissions associated with producing lost energy are eliminated1.
  • The equivalent of a 125-megawatt generating plant not having to be built to serve peak demand.

The figures above do not include the savings from the 220-mile Arrowhead-Weston 345-kilovolt transmission line, which ATC placed in service in January 2008. The reduction of losses associated with the Arrowhead-Weston transmission line is estimated at roughly 24 megawatts of on-peak usage.

ATC’s program of rebuilding and up-rating existing transmission lines and constructing new ones results in power being carried more efficiently than it would be over the older, lower-voltage grid in three ways:

  • Rebuilding existing power lines using a larger conductor enhances efficiency. The larger conductor reduces the resistance of the lines, which reduces losses.
  • Adding new transmission lines to an overloaded system divides power flows over multiple paths, which reduces electric current and losses on each individual power line.
  • Installing higher voltage lines allows demand to be met with lower levels of current and lower line resistance, which also reduces losses.

On the transmission system, extra-high voltage lines typically provide the greatest potential for energy loss reduction. ATC expects to add four additional 345-kilovolt transmission lines in the next five years, which will reduce losses even further:

  • Gardner Park – Central Wisconsin is a 50-mile project in Central Wisconsin scheduled to be energized in spring 2009.
  • Morgan – Werner West is a 50-mile project in Central Wisconsin scheduled to be energized in spring 2009.
  • Paddock – Rockdale is a 35-mile project in Southern Wisconsin expected to be on line in April 2010.
  • Rockdale – West Middleton is a 35-55 mile proposed project in South Central Wisconsin slated to be in service in spring 2013.
]]>
http://www.atcllc.com/news/atc-transmission-improvements-double-as-major-energy-efficiency-upgrades/feed/ 0
ATC’s Dane County power line proposal now ready for independent study http://www.atcllc.com/news/atc%e2%80%99s-dane-county-power-line-proposal-now-ready-for-independent-study/ http://www.atcllc.com/news/atc%e2%80%99s-dane-county-power-line-proposal-now-ready-for-independent-study/#comments Mon, 14 Jul 2008 08:00:37 +0000 http://www.atcllc.com/?p=982 PSC declares application complete; formal regulatory analysis begins

MADISON, Wis. – ATC’s application to construct a 345-kilovolt transmission line between the towns of Middleton and Christiana in Dane County has been deemed “complete” by the Public Service Commission of Wisconsin. This decision marks the formal start to the PSC’s independent study, which could last up to 360 days. The PSC will evaluate the need for the project, conduct engineering and environmental impact analyses, hold technical and public hearings, and conduct a thorough evaluation of ATC’s two proposed route options.

ATC submitted its 2000-page application in October 2007 asking the PSC to review and authorize the Rockdale – West Middleton project. Since then, the company has responded to requests from the PSC for additional information and data to fully complete the application. “The completeness determination we received from the PSC means we have provided the necessary information and documentation to enable the PSC staff to begin its formal study of the project proposal,” said Sarah Justus, ATC local relations manager. “This is an important milestone because it puts a timeframe around the review period.”

Under state law, the PSC has 180 days to render a decision on the project—or petition the courts for an additional 180 days. According to Justus, it would not be unusual for the formal analysis to extend beyond 180 days given the scope of the project. “It’s in the best interest of the public that the PSC staff takes the necessary time to thoroughly study this project,” she said.

According to Justus, the PSC holds two types of hearings: a technical hearing and a public hearing. The Commission uses the technical hearing to receive factual data and expert opinions in support of or in opposition to the project. The expert witnesses generally include engineers, planners, economists, environmental specialists and accountants who have professional expertise on the issues, who testify before an administrative law judge, and are subject to cross examination. Public hearings provide a forum for members of the public to bring their suggestions and concerns to the attention of the Commission. This testimony is not subject to cross examination, but is transcribed by a court reporter and made a part of the official record that the Commission reviews in making a decision.

“Both types of hearings are beneficial to the decision-making process,” Justus explained. In addition to providing notification to local government officials, local libraries, the media and other agencies, the PSC will notify all property owners on or near the proposed route options of its public hearing schedule. “We encourage interested people to continue their involvement by participating in the PSC’s public hearings,” she said.

In the three years since the project was first introduced to the public, ATC has worked with local residents, community representatives, elected officials and others to gather input and answer questions. “We believe we have been successful in demonstrating to the public the critical need for this infrastructure project,” explained Justus. “The Rockdale – West Middleton project will reinforce the transmission network in Dane County, reduce the threat of future system outages, and provide reliable power to support Dane County’s economic development and growing population.”

Dane County has experienced in recent years some of the highest growth rates in the state, both in population and electricity usage. The existing transmission system in and around Dane County brings power in from outside the county to meet the needs for electricity. However, the system is operating at its limits and the Rockdale – West Middleton transmission line will help accommodate the growth in demand, and strengthen the efficiency and reliability of existing lower-voltage lines.

ATC estimates the project cost between $213 million and $250 million and the length between 35 and 55 miles depending on the route. If the project is approved by the PSC, construction of the new power line would start in 2010, and the line would be energized in 2013. ATC’s application, Docket No. 137-CE-147, is available for viewing in the Case Management section of the PSC’s web site at http://psc.wi.gov.

]]>
http://www.atcllc.com/news/atc%e2%80%99s-dane-county-power-line-proposal-now-ready-for-independent-study/feed/ 0
ATC places new transmission line in service http://www.atcllc.com/news/atc-places-new-transmission-line-in-service/ http://www.atcllc.com/news/atc-places-new-transmission-line-in-service/#comments Wed, 11 Jun 2008 08:00:57 +0000 http://www.atcllc.com/?p=980 Cranberry-Conover links facilities in northern Wisconsin, UP

EAGLE RIVER, Wis. – A new, 16-mile high-voltage power line is energized and providing much-needed support to the electric system serving the North Woods, according to American Transmission Co.

The new line, which runs between the Cranberry Substation south of Eagle River and the new Lakota Road Substation near Conover, links transmission facilities in northern Wisconsin and the Upper Peninsula of Michigan. The connection reduces costly constraints on the existing system, which was subject to overloading and potential service interruptions as demand for electricity increased in the area.

“We appreciate the patience and support we have received from the community while planning for and during construction of the Cranberry-Conover line,” says Lee Meyerhofer, local relations representative for ATC. “We announced the project to the local officials and residents in summer 2004, received approval from the Public Service Commission of Wisconsin in late 2006, and began construction in August 2007.”
The line may be energized, but the project is not complete. “While we strive to avoid sensitive areas and minimize the impact of construction, we want area residents to know that we are committed to restoring the corridor after construction. We will be working through the summer to do just that.”

The transmission project also includes the upgrade of 73 miles of existing lines and substations between Conover and Quinnesec, Mich. Construction to upgrade facilities on the 30-mile segment between Conover and Iron River, Mich. began earlier this month with tree clearing. Anticipated completion date for the upgrade is June 2010.

]]>
http://www.atcllc.com/news/atc-places-new-transmission-line-in-service/feed/ 0
Electricity cost-saving power line is approved by PSC; first of its kind in the Midwest http://www.atcllc.com/news/electricity-cost-saving-power-line-is-approved-by-psc-first-of-its-kind-in-the-midwest/ http://www.atcllc.com/news/electricity-cost-saving-power-line-is-approved-by-psc-first-of-its-kind-in-the-midwest/#comments Fri, 30 May 2008 08:00:40 +0000 http://www.atcllc.com/?p=978 ATC gets approval for high-voltage connection to regional generation sources

MADISON, Wis. – Following a year-long regulatory review, the Public Service Commission of Wisconsin gave American Transmission Co. its verbal approval today to move forward with the construction of the Paddock-Rockdale project, a new high-voltage electric transmission line in south central Wisconsin. The new, 35-mile line, to be built largely on existing right-of-way, will extend an existing connection to Illinois and allow local electric distribution companies access to lower-cost power produced in the region. The savings will be passed on to end-use electricity customers under PSC regulations.

“This is the first transmission line project within the footprint of the Midwest Independent System Operator that is driven by economics,” said Randy Satterfield, ATC vice president of Public Affairs. “Although enhanced reliability will be a by-product of the project, the primary benefit of this transmission line to the south comes from the ability of local electric utilities to benefit economically from the wholesale electricity market. This additional high-voltage connection will remove a significant constraint and enable access to lower-cost power in the region—and that translates to savings for electricity consumers.”

As a net importer of electricity, Wisconsin utilities will gain flexibility in the wholesale market with the construction of the new 345-kilovolt line. “The state’s electricity generators generally produce less power than is used; the balance—about 15 percent on average—is imported from areas around the region. On any given day, it’s not necessarily a matter of generation capacity,” explained Flora Flygt, director of Planning for ATC. “It’s a matter of economics. Sometimes the best price and availability on electricity is outside the state.”

According to Flygt, getting the best deal on power is largely dependent on the transmission system. “Wisconsin utilities have been at a disadvantage compared to neighboring states because of the limited number of transmission line connections to other states,” she said. “As the wholesale market and competition continues to evolve, it becomes even more critical that Wisconsin utilities can get cheap power or power from renewable resources for their customers.”

Justifying the project economically came down to the numbers, explained Satterfield. “Almost without exception, the scenarios and models we evaluated demonstrate cost savings sufficient to cover the $133 million cost of the project,” he said. Except for a slow economic growth scenario, (highly unlikely to persist for the entire 40-year life of the line) the present value potential of the net benefits as a result of constructing the Paddock-Rockdale project ranges from $82 million to $1.8 billion. The aggregate annual benefits available for all scenarios range from $7 million to $133 million.

The line will be built on an existing transmission line right-of-way between the Rockdale Substation in the Town of Christiana in Dane County and the Paddock Substation located in the Town of Beloit in Rock County. The existing transmission lines that extend south out of the Paddock Substation into Illinois create a path for importing power into Wisconsin.

The state’s major utilities including Alliant Energy, Madison Gas & Electric, Wisconsin Public Service Corp., and We Energies, along Wisconsin Public Power Inc., testified in support of the project during PSC hearings earlier this year. “We know those benefits are real, and ATC’s modeling does demonstrate that the project will clearly be economically justified,” said Steve Kraus, MGE spokesperson. “MGE’s ratepayers will benefit if we can increase the number of high-voltage transmission lines linking Wisconsin to our neighboring states.”

Traditional transmission line projects have largely focused on reliability needs and weaknesses on the transmission system. Flygt said the recent restructuring of wholesale electric markets has highlighted the need for economic considerations to be a driving force in transmission planning as well. “An access project like Paddock-Rockdale, by reducing transmission congestion and increasing transfer capacity, will positively enhance wholesale generation competition.”

“Timing is important. Our in-service target is 2010, which coincides with the expiration of some of the federal market protection for Wisconsin utilities that have been in place since the market was introduced in 2005,” explained Flygt.

Over the life of the transmission line, the savings include:

  • Reduced generation costs, including fuel. This gives utilities flexibility when fuel prices fluctuate and allows utilities to choose from a greater array of regional generation options.
  • Reduced energy losses. High-voltage lines are more efficient and experience lower losses compared to lower-voltage lines.
  • Increased market competition. A more competitive market will help control and lower prices compared to a market where power purchase choices are limited.

Note to editors: A map and additional information on the Paddock-Rockdale project is available at www.atc-projects.com

ATC’s other proposal for a 345-kilovolt line between the Rockdale Substation and the West Middleton Substation in the town of Middleton (Rockdale – West Middleton project) is under regulatory review. A decision on the project is expected sometime in 2009.

]]>
http://www.atcllc.com/news/electricity-cost-saving-power-line-is-approved-by-psc-first-of-its-kind-in-the-midwest/feed/ 0
Transmission lines carry green power http://www.atcllc.com/news/transmission-lines-carry-green-power/ http://www.atcllc.com/news/transmission-lines-carry-green-power/#comments Thu, 22 May 2008 08:00:26 +0000 http://www.atcllc.com/?p=976 By Flora Flygt

Recent headlines on renewable sources of electricity include:

  • WPL buys huge wind farm
  • WPS seeks hydro power
  • Wind farms proposed on Lake Michigan
  • Wind turbines start generating power in Fond du Lac
  • US leads world in wind power growth

Demand for renewable electricity is soaring, driven by an awareness of climate change and the resulting state mandates on utilities to produce clean power. To meet this demand, new large-scale renewable generators must often be built in remote locations with site-specific resources, far away from population centers that would use the energy. Electric transmission lines provide a vital link in bringing renewable power into communities and realizing environmental objectives.

Connecting renewable energy projects to the long-distance transmission grid is one significant part of states’ strategies to reduce carbon emissions and fossil fuel use across the electric system. Yet the current interstate transmission network was not sized, sited or designed to accommodate large new injections of intermittent energy from wind, solar or other resources.

Renewable power as a major source of electricity is in its infancy relative to demand. Here in Wisconsin, renewable sources of power produce about four percent of the electricity we consume. Nationally, wind power, one of the more heavily developed renewable resources, supplies one percent of the nation’s electricity. More than 25 states have new renewable energy mandates, and they represent exponential increases in the amount of electricity utilities must produce (or purchase) from renewable sources: from 4 percent of electricity consumed currently to as much as 30 percent in the next 15 years.

To meet these mandates, this power must be deliverable to consumers. And yet the transmission grid does not have the capability, regionally or nationally, to deliver this energy. Transmission bottlenecks are among the largest barriers to wind power and other large-scale renewable energy development. The non-profit group Wind on the Wires, together with the American Wind Energy Association, is advocating the study and elimination of transmission constraints that inhibit or delay wind projects. Although Wisconsin generally has less robust wind resources (with the exception of Lake Michigan) the Upper Midwest as a region is relatively rich: it has five of the top ten states in the country in terms of wind energy potential, according to Wind on the Wires. Tapping this resource requires regional transmission grid building and investment.

Wisconsin has made progress in increasing its renewable power portfolio. New projects have been proposed, approved, built and connected to the transmission grid over the last few years. Despite the lower-quality wind regime in the state, new technologies have enabled developers to better harness Wisconsin’s wind. In fact, American Transmission Co., owner and operator of the transmission grid in the region, is connecting more than 340 megawatts of wind power to the grid this year, enough to power more than 90,000 homes. The 220-mile Arrowhead-Weston transmission line, energized earlier this year, is well situated to help bring in hydro resources from Canada and future wind power from the Dakotas. Yet the goals are high and our progress must continue. If wind is the predominant resource for meeting renewable energy requirements, Wisconsin utilities will need up to 1,800 megawatts of additional capacity, according to Public Service Commission information.

Raising renewable energy from 5 to 10 (or more) percent of the region’s electricity generating portfolio requires large volumes of renewable electricity to be produced, which is accomplished where wind, solar, biomass or hydro resources are abundant. Hydro and wind sources can’t be moved closer to population centers. Good wind areas cover only 6 percent of the lower 48 states’ land mass, and solar costs are lowest in remote areas where local power needs are minimal. Interstate, high-voltage transmission lines can take up to 10 years to plan, permit and construct. Achieving green power objectives in the near term will require a collective acceptance that transmission lines are an integral part of supplying our homes and businesses with renewable electricity.

Flora Flygt is director of planning for American Transmission Company. Pewaukee-based ATC owns, operates and maintains 9,350 miles of transmission lines and 500 substations with a total investment in facilities of $1.7 billion in portions of Wisconsin, Michigan, Minnesota and Illinois. For more information, visit our Web site at www.atcllc.com

]]>
http://www.atcllc.com/news/transmission-lines-carry-green-power/feed/ 0
Newly energized electric transmission line moves power; boosts reliability http://www.atcllc.com/news/newly-energized-electric-transmission-line-moves-power-boosts-reliability/ http://www.atcllc.com/news/newly-energized-electric-transmission-line-moves-power-boosts-reliability/#comments Wed, 21 May 2008 08:00:44 +0000 http://www.atcllc.com/?p=974 ATC’s Saukville-St. Lawrence line supports output from Port Washington Generating Station

PEWAUKEE, WIS. – An existing 138-kilovolt electric transmission line between the Saukville Substation and the St. Lawrence Substation (located northeast of Slinger in the town of Hartford) was returned to service by American Transmission Co. following a year-long upgrade project.

The 19-mile line was energized last week following a year of construction activities to replace 60-year old poles and wires. “This work was done in part to address issues related to the age and condition of the facilities,” said Mary Carpenter, local relations representative. “The upgrade was also necessary to accommodate the additional output from the Port Washington Generating Station when the second of two new units is soon placed in service by We Energies.”

The need for a heaver-weight wire to carry more electricity called for the construction of stronger structures (poles). In general, the new structures were placed in the same position as the old structures. “Moving power from the generation source to where it’s needed was the goal of this project,” explained Carpenter. “This line also will strengthen reliability throughout the area.”

]]>
http://www.atcllc.com/news/newly-energized-electric-transmission-line-moves-power-boosts-reliability/feed/ 0
Delgado named to DOE Electricity Advisory Committee http://www.atcllc.com/news/delgado-named-to-doe-electricity-advisory-committee/ http://www.atcllc.com/news/delgado-named-to-doe-electricity-advisory-committee/#comments Tue, 22 Apr 2008 08:00:23 +0000 http://www.atcllc.com/?p=972 New committee to provide counsel on long-range planning for national electricity infrastructure

PEWAUKEE, WIS. – José M. Delgado, president and CEO of American Transmission Co., is among 30 electric industry leaders selected to serve on the U.S. Department of Energy’s newly established Electricity Advisory Committee.

The new committee – chartered by DOE Secretary Samuel Bodman — is tasked with providing counsel on long-range planning and priorities for the modernization of the nation’s electricity delivery infrastructure. It will work with the DOE’s Office of Electricity Delivery and Energy Reliability, which has responsibility for meeting the requirements of the Energy Policy Act of 2005 and the Energy Independence and Security Act of 2007. The Electricity Advisory Committee also has been asked to share its expertise on the deployment of smart grid technologies, research and development of energy storage technologies, renewable energy resource system integration and new transmission infrastructure to ensure the efficient delivery of electricity.

Since its formation in 2001 as the nation’s first multi-state, transmission-only utility, ATC has invested $1.7 billion in new and upgraded transmission lines and substations to increase the reliability of the grid serving portions of Wisconsin, Michigan, Minnesota and Illinois.

Prior to ATC, Delgado spent 27 years at Wisconsin Electric Power Co. starting as an electrical engineer and ending as vice president of Electric System Operations. He currently serves on the Edison Electric Institute board of directors and is co-chair of the CEO Task Force on Reliability & Infrastructure Protection. He is chairman of the North American Electric Reliability Corp.’s Transmission Owners and Operators Forum. He also serves on the advisory board of the Consortium for Electrical Reliability Technology Solutions.

For a list of all members of the DOE’s Electricity Advisory Committee, go to:
http://www.doe.gov/news/6158.htm

]]>
http://www.atcllc.com/news/delgado-named-to-doe-electricity-advisory-committee/feed/ 0
Arrowhead-Weston transmission line energized http://www.atcllc.com/news/arrowhead-weston-transmission-line-energized/ http://www.atcllc.com/news/arrowhead-weston-transmission-line-energized/#comments Tue, 05 Feb 2008 08:00:38 +0000 http://www.atcllc.com/?p=970 One of the nation’s largest transmission lines completed safely, ahead of schedule, within budget

PEWAUKEE, Wis. – American Transmission Co. energized the completed 220-mile, 345-kilovolt Arrowhead- Weston transmission line linking Wausau, Wis., and Duluth, Minn. First proposed in 1999 (prior to ATC’s formation) by Wisconsin Public Service Corp. and Minnesota Power, Arrowhead-Weston is one of the largest new extra high voltage transmission lines to be placed in service nationally in decades.

“To say that this is an achievement would be an understatement,” said José Delgado, ATC president and CEO. “In 10 years’ time, we have faced public and local government opposition, delays, a reauthorization of the cost estimate, and dozens of regulatory and legal challenges. And yet today we have successfully completed this massive undertaking.”

Pete Holtz, Arrowhead-Weston project manager for ATC, pointed to the companies’ coordinated performance on multiple fronts during the past four years of construction as evidence of the project’s success. “Our project team’s efforts were outstanding. The team displayed a “can-do” attitude on all challenges and we kept each and every commitment. As a result, our performance in completing the construction met a set of high expectations,” said Holtz.

  • Safety — Few recordable incidents.
  • Schedule — Construction completed 7 months early; line energized 4 months early.
  • Budget — Project came in at $439 million, 3.6 percent over estimate but within the 5 percent contingency set by the Public Service Commission of Wisconsin.
  • Fairness — We were able to reach agreement with nearly all of the landowners and even a local opposition leader, Tom Krueger, publicly stated his settlement was fair.
  • Environment — 27 miles of mats used to preserve wetlands and compliance excellent with no major environmental incidents.

Holtz noted several other factors in the companies’ success. “We received outstanding support from local and state public officials, and state regulators worked with us in a cooperative manner to ensure that their concerns were addressed effectively. The state’s utilities also gave us excellent support in coordinating and scheduling the system outages that were needed during construction.”

As a result, Holtz said, significant improvements in electric system reliability have accrued. “First, Arrowhead- Weston improves electric system reliability by reducing the strain on Wisconsin’s single transmission connection to the west, the Eau Claire-Arpin transmission line. Second, this project increases import and transfer capability into Wisconsin, a state that depends on imports to meet its power needs. Third, it provides needed support for WPS Weston 4 power plant and helps all of Central Wisconsin be less vulnerable to outages. Fourth, the Stone Lake Substation provides critical support for Xcel customers in Northwestern Wisconsin, and lastly the line improves access to lower cost, Western energy markets, which is an unanticipated advantage.” The line can carry roughly 600 to 800 megawatts of electricity, enough to power a minimum of 250,000 homes.

Following the project’s completion, Delgado reflected on a number of “lessons learned” in bringing a major new transmission line into service. “Continuous communication is critical. We used a grass-roots political campaign model to overcome initial public opposition. On the management side, we and our utility partners coordinated our work using sophisticated scheduling tools, and established standards for major risk assessment and cost control. If you’re going to manage a project of this magnitude, you have to bring appropriate tools to bear.”

“I extend my sincere thanks to those involved with the project,” Delgado said, adding, “we had many partners in this project, and all of them deserve credit for our success.” In addition to WPS and Minnesota Power, several contractors worked on the project, including:

  • MJ Electric, Inc.
  • Tri-State Drilling, Inc.
  • Northern Clearing, Inc.
  • Natural Resources Consulting
  • Power Engineers
  • PAR Electric, Inc.
  • Kenny Construction, Inc.
  • Thomas and Betts
  • Alcan Corp.
  • Border States
  • STS Consulting
  • Olinick, Inc.
  • Superior Redi Mix
  • County Materials
  • JZ Environmental

With Arrowhead-Weston’s completion long included in its transmission system planning models, ATC’s recent 10-Year Transmission System Assessment calls for a reduced investment of $2.8 billion in the transmission grid in its service area over the next 10 years.

]]>
http://www.atcllc.com/news/arrowhead-weston-transmission-line-energized/feed/ 0
ATC receives PSC approval for power line between Fitchburg and Verona http://www.atcllc.com/news/atc-receives-psc-approval-for-power-line-between-fitchburg-and-verona/ http://www.atcllc.com/news/atc-receives-psc-approval-for-power-line-between-fitchburg-and-verona/#comments Tue, 15 Jan 2008 08:00:48 +0000 http://www.atcllc.com/?p=968 New line will strengthen Dane County’s transmission system, route to follow existing corridor

MADISON, Wis. – The Public Service Commission of Wisconsin today approved a vital improvement to Dane County’s electric transmission system linking a new substation in the City of Fitchburg to an existing substation in Verona. The new 138-kilovolt line will run six miles along an existing right-of-way between the new Oak Ridge Substation in Fitchburg and the Verona Substation.

“We are pleased that the PSC agreed with our assessment for this much-needed transmission line that will improve electric system reliability in the rapidly growing areas of southern Dane County and northern Green County,” said Sarah Justus, ATC local relations representative. “The existing facilities are operating at near- maximum capacity during the peak summer season and may face overloads by next summer,” Justus said. “The transmission system is outdated and needs to be reinforced to prevent future system failures. The new facilities also will strengthen Madison Gas & Electric’s local distribution system.”

In its decision, the PSC selected the route recommended in ATC’s application filed in January 2007. “The route along Adams Road and County Highway M makes use of an existing transmission line corridor,” explains Justus. “The construction along this existing corridor is a cost-effective route that minimizes impacts to the community. The amount of new right-of-way needed is also less on the approved route.”

The project was introduced to the public in 2005 to meet growing demand for electricity in south central Dane County. According to the U.S. Census Bureau, Verona’s population between 2000 and 2005 grew by 44 percent—a rate faster than any other community in the state.

Construction on the new Oak Ridge Substation will begin in the coming months and is expected to be operational by June 2009. The transmission line construction will begin following the substation work, and the line will be operational in June 2010. The estimated cost of the project is $22 million.

ATC’s proposal for a 345-kilovolt transmission line between the towns of Christiana and Middleton is currently under regulatory review. The company expects the PSC to schedule hearings later this year or in early 2009.

]]>
http://www.atcllc.com/news/atc-receives-psc-approval-for-power-line-between-fitchburg-and-verona/feed/ 0
Satterfield promoted to vice president of Public Affairs http://www.atcllc.com/news/satterfield-promoted-to-vice-president-of-public-affairs/ http://www.atcllc.com/news/satterfield-promoted-to-vice-president-of-public-affairs/#comments Mon, 10 Dec 2007 08:00:53 +0000 http://www.atcllc.com/?p=966 He assumes responsibilities of retiring VP Williamson

WAUKESHA, Wis. – The ATC board of directors elected Randy Satterfield vice president of Public Affairs effective Jan. 1, 2008. He is assuming the responsibilities of Mark Williamson, vice president of Major Projects, who announced last week he will retire at the end of 2007. As vice president of Public Affairs, Satterfield will oversee State Regulatory Relations, Real Estate, Environmental, Local Relations and Corporate Communications.

Satterfield has been director of Regulatory and Governmental Relations for ATC since December 2006. He joined ATC in 2003 as director of Communications. Previously, he was senior account manager for Wood Communications Group in Madison. Prior to Wood, Randy served as an assistant director in the Bureau of Consumer Protection at the Federal Trade Commission in Washington D.C. He has extensive experience in communications, advertising, political consulting and international public relations. He holds undergraduate degrees in philosophy and political science from Marquette University.

“Randy has developed a broad knowledge of our business and industry, and the issues impacting us,” said José Delgado, president and chief executive officer. “He has applied strategic thinking, collaboration within and outside our company, and an aptitude to achieve results that have helped ATC be successful. We are pleased to have Randy in this new role within our corporate leadership team.”

]]>
http://www.atcllc.com/news/satterfield-promoted-to-vice-president-of-public-affairs/feed/ 0
Williamson announces retirement from ATC, plans consulting career http://www.atcllc.com/news/williamson-announces-retirement-from-atc-plans-consulting-career/ http://www.atcllc.com/news/williamson-announces-retirement-from-atc-plans-consulting-career/#comments Mon, 03 Dec 2007 08:00:04 +0000 http://www.atcllc.com/?p=964 Will continue active role in Dane County transmission projects

PEWAUKEE, Wis. – Mark Williamson, vice president of Major Projects, has announced he will retire from American Transmission Co. on Jan. 1, 2008, and go into the consulting industry as a partner with the Madison communications firm Putnam Roby (www.putnamroby.com). He will continue his affiliation with ATC in a consulting role and remain active with the company’s proposed projects in Dane County.

Williamson has been associated with ATC since its inception in 2001. He initially served on ATC’s board of directors representing Madison Gas & Electric. During his 16-year career at MGE, Williamson last served as executive vice president and chief strategic officer. In June 2002, Williamson joined ATC as vice president of Major Projects overseeing external relations and the public participation process that includes local relations, environmental, real estate and state regulatory functions. For ATC, he has managed external relations for major transmission infrastructure projects including the 220-mile Arrowhead-Weston transmission line, the 100-mile Gardner Park-Central Wisconsin-Morgan-Werner West project, and the 85-mile Cranberry-Conover-Plains project – all currently under construction. He also has led the public participation process for the proposed transmission line projects in and around Dane County.

“It’s not an easy job to gain acceptance for new transmission lines, but Mark has developed a very successful program for communicating and working with those impacted by our work,” said José Delgado, ATC president and chief executive officer. “His leadership in the company’s proactive communications with landowners, local officials and especially those opposing our work has been the reason we’ve been able to get these critical projects under way in time to maintain the reliability of the electric grid serving people and businesses in communities throughout Wisconsin and Michigan. I have admired and appreciated his ability to address this most significant obstacle to the construction of transmission in this country.”

Williamson said, “I have enjoyed the challenge, and I look forward to continuing to help ATC with the proposed transmission line projects in Dane County in my new consulting capacity.
“This new career also gives me the opportunity to help other companies and communities around the country take a similar open approach in raising awareness and gaining acceptance for their important infrastructure projects,” Williamson said.

]]>
http://www.atcllc.com/news/williamson-announces-retirement-from-atc-plans-consulting-career/feed/ 0
Utilities collaborate to address impact of declining lake levels on electricity supply http://www.atcllc.com/news/utilities-collaborate-to-address-impact-of-declining-lake-levels-on-electricity-supply/ http://www.atcllc.com/news/utilities-collaborate-to-address-impact-of-declining-lake-levels-on-electricity-supply/#comments Mon, 12 Nov 2007 08:00:09 +0000 http://www.atcllc.com/?p=962 SAULT STE. MARIE, MICH. – Edison Sault Electric Company and Cloverland Electric Cooperative have been working with American Transmission Co. to address electricity supply issues caused by declining Lake Superior water levels. Low lake levels have reduced the amount of water that is typically available for hydroelectric generation – a major source of power for the eastern portion of Michigan’s Upper Peninsula.

“Because of the low lake levels, we cannot operate our hydro facilities at the level necessary to effectively serve the needs of our customers and communities,” said Don Sawruk, President of Edison Sault. “We have to rely on the high-voltage electric transmission system to import power into the area.”

ATC, which owns and operates the high-voltage electric transmission system in Michigan’s Upper Peninsula and Wisconsin, has begun reinforcing the transmission system at several locations to offset some of the effects of the declining lake levels. Brett French, senior regional manager of Customer Relations for ATC, says, “The transmission system was never designed to supplant the output of the hydroelectric generating facilities in Sault Ste. Marie. However, upgrades are quickly being made by ATC to bolster the supply of electricity throughout the region with most of the upgrades coming online by the end of 2007.”

“These projects will dramatically improve the reliability and capacity of the grid that serves the Eastern Upper Peninsula,” French said. “Any reduction in hydro generation in this region places a greater demand on ATC’s system, and we were concerned about the risk of disruptions or outages to Edison Sault and Cloverland customers under extreme conditions. Consequently we are investing approximately $6.5 million to manage the short-term risks that are being caused by a reduction in output at the existing hydroelectric plants. We are also working with Edison Sault and Cloverland to address the long-term electrical needs of the region.”

With these improvements, Sawruk says, “Edison Sault will be importing up to 75 percent of its electricity needs through the ATC high-voltage electric transmission system. This is substantially more than at any other point in our history, which dates back to 1892.”

Don Wozniak, General Manager of Cloverland Electric Cooperative, says, “We anticipate the upgrades being made by ATC will help ensure the reliability of the electric system. With the recent approval of a $10 million loan from the U.S. Department of Agriculture’s Rural Development program, Cloverland will be making additional upgrades to its electric distribution system.”

Crews install new electric transmission equipment that will help bring power into the eastern portion of Michigan’s Upper Peninsula, where low lakes levels are dramatically reducing output of the hydroelectric facilities.

Edison Sault Electric Company, a wholly owned subsidiary of Wisconsin Energy Corporation, serves 23,000 customers in the Eastern Upper Peninsula. For more information, visit www.edisonsault.com

Cloverland Electric Cooperative is a member-owned electric utility providing electricity to over 19,000 homes, farms and businesses in the rural areas of Chippewa, Mackinac, Luce and Schoolcraft counties. It was incorporated in 1938 and operates offices in Dafter, DeTour and Newberry. For more information, visit www.cloverland.com

]]>
http://www.atcllc.com/news/utilities-collaborate-to-address-impact-of-declining-lake-levels-on-electricity-supply/feed/ 0
ATC submits regulatory application for Rockdale – West Middleton project to PSC http://www.atcllc.com/news/atc-submits-regulatory-application-for-rockdale-%e2%80%93-west-middleton-project-to-psc/ http://www.atcllc.com/news/atc-submits-regulatory-application-for-rockdale-%e2%80%93-west-middleton-project-to-psc/#comments Mon, 15 Oct 2007 08:00:42 +0000 http://www.atcllc.com/?p=960 Year-long regulatory review includes evaluation of need, alternatives and routes

MADISON, Wis. – ATC today submitted to the Public Service Commission of Wisconsin its application requesting approval of a proposal for a new 345-kilovolt electric transmission line through Dane County between the towns of Middleton and Christiana. The project, with a cost between $213 million and $250 million, is a critical infrastructure improvement that will:

  • reinforce the entire transmission network in Dane County • reduce the threat of future system outages
  • eliminate the need for multiple new, lower voltage transmission lines in the future
  • provide critical power for continued economic development and a growing population
  • benefit the environment by efficiently moving power throughout the county, reducing electricity lost in transit. This results in reduced electricity generation and the fuels needed to produce power.

Over the past two and half years, ATC has worked with local residents, community representatives, elected officials and others to gather input and answer questions about the project. “We appreciate the involvement of the public in helping to shape the decisions related to this project,” said Mark Williamson, vice president of major projects. “We look forward to continued public dialogue on our proposal as the PSC begins its regulatory review.”

According to Williamson, the PSC in its analysis makes two distinct determinations. “The PSC will first study the need for the project, including alternative solutions. Once the need has been established and the project is determined to be the optimal solution, the staff will review the proposed route options and render a decision on the project.”
The final routes included in ATC’s construction application follow two basic east-west corridors. These routes, which were announced in August, include a northern route that generally follows the Beltline Highway and a southern route that traverses mostly rural areas offset from county highways. Some variations to the routes provide alternate connections or paths between the two primary routes. Williamson noted that the company did not designate a preferred route in its application. “All the route options have pros and cons. It will be up to the PSC to determine the route that best represents the public interest.”

“Our filing represents the next step in the public process that will culminate with a PSC decision,” said Williamson. “There will be numerous opportunities for public comment, including a public hearing prior to a PSC order, which we hope to receive in early 2009.”
If approved, the company would begin construction in 2010 and place the line in service in 2013. ATC’s application, Docket No. 137-CE-147 is available for viewing in the Case Management section of the PSC’s web site at http://psc.wi.gov. Copies will also be available late this week at Dane County area libraries, and in each municipal and town clerks’ office.

]]>
http://www.atcllc.com/news/atc-submits-regulatory-application-for-rockdale-%e2%80%93-west-middleton-project-to-psc/feed/ 0
Transmission line right-of-way to be cleared of vegetation http://www.atcllc.com/news/transmission-line-right-of-way-to-be-cleared-of-vegetation/ http://www.atcllc.com/news/transmission-line-right-of-way-to-be-cleared-of-vegetation/#comments Tue, 18 Sep 2007 08:00:02 +0000 http://www.atcllc.com/?p=958 60-year-old poles and wires to be replaced between Saukville and Hartford

WAUKESHA, Wis. – American Transmission Co. crews will be removing trees and clearing woody vegetation within an existing electric transmission line right-of-way between the Saukville Substation and the St. Lawrence Substation (located northeast of Slinger in the town of Hartford). The work, which is scheduled to begin the third week in September, is in advance of a project to replace the old structures and wires along the right-of-way.

“It’s been many years since the right-of-way in some areas has been cleared or maintained,” said Mary Carpenter, local relations representative. “We want adjacent landowners to be aware of the extent of clearing that is needed to prepare for the replacement of the old structures. The appearance of the right-of-way in some locations will be significantly altered, and we want neighbors to know what to expect.”

According to Carpenter, right-of-way maintenance is done primarily for electric reliability reasons. “In this case, the clearing is driven by the upcoming construction work. But the removal of trees and vegetation also will ensure the safe and reliable operation of the new facilities for many years to come,” she said. “We are required to meet certain federal standards for vegetation management on our rights-of-way to prevent electric system outages.”

ATC has notified landowners of the upcoming clearing and tree removal, which will begin on the west end of the line near the St. Lawrence Substation and continue through the end of the year, wrapping up in Saukville. A final notification will be made by the forestry company, Wright Tree Service, who will provide a phone number for property owners who may have questions or concerns.
The construction work to replace the 60-year old poles and wires on the existing 138-kilovolt electric transmission line will begin in mid-October as portions of the right-of-way are cleared. This 19-mile corridor needs upgrading to support the additional output from the Port Washington Generating Station when the second unit is placed in service in 2008. The voltage of the line will remain the same at 138-kilovolts when the new facilities are placed in service in late April 2008.

]]>
http://www.atcllc.com/news/transmission-line-right-of-way-to-be-cleared-of-vegetation/feed/ 0
Public informational meetings set to begin on Dane County transmission project http://www.atcllc.com/news/public-informational-meetings-set-to-begin-on-dane-county-transmission-project/ http://www.atcllc.com/news/public-informational-meetings-set-to-begin-on-dane-county-transmission-project/#comments Tue, 14 Aug 2007 08:00:06 +0000 http://www.atcllc.com/?p=956 ATC to answer questions about Beltline and southern routes for transmission line

MADISON – American Transmission Co. will host a series of public informational open house meetings next week to share information about the proposed Rockdale – West Middleton transmission line project. ATC is encouraging the public to learn more about the two proposed route options that will be included in the regulatory application the company will submit to the Public Service Commission in October.

ATC unveiled the final two route alternatives for the transmission line last week. The northern route alternative generally follows I-90 and the Beltline highway west toward Middleton. The southern route follows a path mostly through rural areas offset from county highways.

“We’re encouraging property owners who are not yet familiar with this critical project to become in engaged in the process so they understand how the project may potentially impact their property and the next steps in the process,” said Mark Williamson, vice president of Major Projects. At the meetings next week, ATC staff also will discuss other aspects of the proposed project including the overall need for a new transmission line, environmental impacts, the regulatory review process, and engineering and construction issues.

Public informational open houses to review the final route alternatives:

Monday, Aug. 20, 4 – 8 p.m.
Alliant Energy Center

Wednesday, Aug. 22, 4 – 8 p.m.
Quality Inn & Suites, Fitchburg

Tuesday, Aug. 21, 4 – 8 p.m.
LakeView Church, Stoughton

Thursday, Aug. 23, 4 – 8 p.m.
The Heights Event Center, Verona

ATC’s public involvement process began more than two years ago when the company first introduced a proposal for a 345-kilovolt electric transmission line between the towns of Middleton and Christiana. More than 17,000 households were invited to attend 18 open houses in the past couple of years and to provide input and feedback. “Our collaborative approach to routing and siting transmission lines involved thousands of people,” explained Williamson. “Our public outreach has been a two-way street that included a meaningful dialogue with property owners, public officials and other stakeholders about the need and possible impacts of the project.”

According to Williamson, the final route options for the transmission line were directly influenced by ATC’s public involvement activities. “The valuable information and input from the public leads to good decision-making, results in a better, more acceptable project, and helps us prepare a regulatory application that can withstand the thorough review of the PSC,” he said.

The year-long regulatory review will begin in October when ATC files its construction application for the project. “We encourage people to continue their involvement as the regulatory process begins and the PSC reviews our proposal,” said Williamson.

]]>
http://www.atcllc.com/news/public-informational-meetings-set-to-begin-on-dane-county-transmission-project/feed/ 0
ATC to start work along Michigan’s Upper Peninsula http://www.atcllc.com/news/atc-to-start-work-along-michigan%e2%80%99s-upper-peninsula/ http://www.atcllc.com/news/atc-to-start-work-along-michigan%e2%80%99s-upper-peninsula/#comments Mon, 30 Jul 2007 08:00:16 +0000 http://www.atcllc.com/?p=954 Laurium Rebuild will improve electric reliability in Houghton County

Kingsford, Mich. – American Transmission Co. will soon begin reconstruction of the existing transmission line that runs between the Atlantic Mine Substation, located in Adams Township, and the Osceola Substation, located in Calumet Township.

“The upgraded transmission line will improve electric reliability in Michigan’s Upper Peninsula,” said Brett French, ATC customer relations. “We will do our best to inform landowners of the impact of our work, while keeping disruptions to a minimum as we complete the project.”

During the project, the existing transmission facilities will be replaced with new steel poles, insulators and wires along and within the existing transmission right-of-way corridor. ATC will also upgrade the substations in this area.

The affected communities include the City of Hancock, and the Townships of Adams, Quincy, Franklin, Osceola and Calumet. All are located in Houghton County. These communities may experience heavy truck traffic from time to time as equipment and materials are mobilized to the area to support this project.

ATC will start the work in August. This project should be complete, and the facilities placed in service by the end of May 2008.

This project, estimated to cost approximately $9 million, is another example of ATC’s ongoing commitment to the Upper Peninsula.

]]>
http://www.atcllc.com/news/atc-to-start-work-along-michigan%e2%80%99s-upper-peninsula/feed/ 0
ATC to start work along Highway 41 in Oshkosh http://www.atcllc.com/news/atc-to-start-work-along-highway-41-in-oshkosh/ http://www.atcllc.com/news/atc-to-start-work-along-highway-41-in-oshkosh/#comments Thu, 19 Jul 2007 08:00:31 +0000 http://www.atcllc.com/?p=952 Ellinwood-Sunset transmission line upgrade will improve electric reliability in Fox Valley

De Pere, Wis. – American Transmission Co. will soon begin work on the existing transmission line that runs alongside US Hwy. 41 between the Sunset Point Substation, located in the town of Oshkosh, and the Ellinwood Substation, located in the City of Oshkosh.

“The upgraded transmission line will improve electric reliability in the Fox Valley,” said David Hovde, ATC local relations. “We will do our best to keep disruptions to a minimum along Hwy. 41 as we complete the project.”

The work consists of replacing six structures with steel poles on concrete foundations, as well as adding another six new steel poles. In addition, we will also be adding a second circuit (i.e, a second set of wires) on the remaining structures on the existing line by replacing the steel “arms” to these structures. This will accommodate the second circuit that will be placed on the 3.8 mile line along Hwy. 41 and across a portion of Lake Butte des Morts. The steel poles need to be replaced to meet newly required height clearances. There will also be some construction activities inside the two substations.

There will be a few periodic lane closures and diversions along Koeller Street. to accommodate the construction vehicles and work taking place during the project. The appropriate traffic control procedures, warning and directional signage, and other safety measures will be in place to alert drivers about any lane closures.

This project should be complete, and the facilities placed in service by mid-December 2007.

]]>
http://www.atcllc.com/news/atc-to-start-work-along-highway-41-in-oshkosh/feed/ 0
ATC gets approval to construct electric transmission line near Waunakee http://www.atcllc.com/news/atc-gets-approval-to-construct-electric-transmission-line-near-waunakee/ http://www.atcllc.com/news/atc-gets-approval-to-construct-electric-transmission-line-near-waunakee/#comments Thu, 12 Jul 2007 08:00:45 +0000 http://www.atcllc.com/?p=950 138-kV line will ensure local electric reliability for existing customers and future growth

MADISON, Wis. – Following a year-long regulatory review, the Public Service Commission of Wisconsin gave ATC its final approval today for construction of a new electric transmission line from Vienna to Westport, known as the North Madison-Huiskamp project. The proposal for the 8-mile, 138-kilovolt line near Waunakee is needed to accommodate the robust growth in recent years and the increase in electric consumption.

“Waunakee is one of the fastest growing communities in Dane County both in terms of population growth and new business,” said Sarah Justus, local relations representative. “This growth has out-paced the capacity of the area’s existing electric system to deliver reliable electric service.”

The PSC selected the preferred route recommended by ATC, which will run along County Highway I and State Highway 113 between the North Madison Substation in Vienna and the Huiskamp Substation located in the town of Westport. ATC gathered feedback from area residents beginning in 2005 on several possible routes for the proposed line. “The input we received was very helpful in identifying the most suitable routes for the line,” said Justus. “It’s always a challenge, and gathering feedback is an essential part of the process.”

During the next several months, ATC will begin land surveying and soil testing to finalize the design details, as well starting on the easement acquisition process. According to Justus, the construction of the line won’t begin until next year, but pre-construction activities will begin right away. “When we get closer to actual construction, we’ll host a pre-construction open house where area residents can learn more about what they can expect to observe during construction.” she said. The project, which is estimated at approximately $15 million, is expected to be placed in service in 2008.

“Approval of this line is good news for the homeowners, businesses and industries that will benefit from a reliable electric system,” said Justus. “We hope that area residents will continue to stay involved as we prepare for construction.”

Note to editors: A map of the approved route is available at www.atcllc.com

]]>
http://www.atcllc.com/news/atc-gets-approval-to-construct-electric-transmission-line-near-waunakee/feed/ 0
Newly energized electric transmission line boosts reliability in Columbia County http://www.atcllc.com/news/newly-energized-electric-transmission-line-boosts-reliability-in-columbia-county/ http://www.atcllc.com/news/newly-energized-electric-transmission-line-boosts-reliability-in-columbia-county/#comments Tue, 10 Jul 2007 08:00:11 +0000 http://www.atcllc.com/?p=946 Columbia-Rio transmission line completed under budget and ahead of schedule

MADISON, Wis. – American Transmission Co. placed in service last week a new 69-kilovolt electric transmission line connecting the Columbia Substation, located in the Town of Pacific, with the Rio Substation, located in the Village of Rio. The new line will also connect to a new Alliant Energy substation – the Wyocena Substation, in the Village of Wyocena.

Construction began last spring on the transmission line, which runs from the Columbia Substation along State Hwy. 16 into the Wyocena Substation. Construction was completed last month, ahead of schedule.

The 10-mile transmission line helps meet local electricity needs and backs up other critical facilities on the electric system. “This new transmission line will help accommodate the increase in electricity usage due to population growth,” said John Garvin, ATC local relations representative. “Completion of this line gives us a solution to past network challenges.”

]]>
http://www.atcllc.com/news/newly-energized-electric-transmission-line-boosts-reliability-in-columbia-county/feed/ 0
New electric transmission line energized in Oneida and Forest counties http://www.atcllc.com/news/new-electric-transmission-line-energized-in-oneida-and-forest-counties/ http://www.atcllc.com/news/new-electric-transmission-line-energized-in-oneida-and-forest-counties/#comments Mon, 09 Jul 2007 08:00:58 +0000 http://www.atcllc.com/?p=948 Venus-Metonga transmission line completed on schedule

De Pere, Wis. – American Transmission Co. placed in service last week a new 115-kilovolt electric transmission line connecting the Venus Substation, located in the Town of Monico, with a new Wisconsin Public Service Corp. substation, named the Metonga Substation, in Crandon.

Construction began in late fall 2006 on the 13-mile line. It runs along Old Hwy. 26 south and east along Hwy. 8, down Rosa Road to the Metonga Substation. Construction wrapped up last week, on schedule.

The new transmission line helps improve electric reliability in the area and serves as a backup to other critical facilities on the electric system.

“Completion of this project resolves further loading problems caused by population growth in the area,” said Lee Meyerhofer, ATC local relations representative.

]]>
http://www.atcllc.com/news/new-electric-transmission-line-energized-in-oneida-and-forest-counties/feed/ 0
PSC begins formal review of ATC’s application for Paddock – Rockdale Project http://www.atcllc.com/news/psc-begins-formal-review-of-atc%e2%80%99s-application-for-paddock-%e2%80%93-rockdale-project/ http://www.atcllc.com/news/psc-begins-formal-review-of-atc%e2%80%99s-application-for-paddock-%e2%80%93-rockdale-project/#comments Tue, 26 Jun 2007 08:00:12 +0000 http://www.atcllc.com/?p=944 180-day regulatory analysis of electric transmission access proposal begins

MADISON, Wis.—American Transmission Co.’s application seeking approval to construct a new 345 kilovolt electric transmission line in south central Wisconsin was declared complete last week by the Public Service Commission of Wisconsin. The determination marks the beginning of the roughly six-month regulatory review of the proposal, which will include engineering and environmental scrutiny and a public hearing.

This application, which was filed with the PSC in May, is the first transmission line proposal within the service area of the Midwest Independent System Operator (MISO) that is justified on economics. ATC’s projects in recent years largely have been constructed to address weaknesses on its transmission system and resolve reliability issues. “Although area reliability will be enhanced, the primary benefit of this high-voltage transmission line to the south comes from the ability of utilities to access and purchase cheaper power in the region for their customers,” explained Flora Flygt director of Planning for ATC. The proposed power line, called Paddock-Rockdale, will add a connection between the Rockdale Substation in the Town of Christiana in Dane County and the Paddock Substation located in the Town of Beloit in Rock County.

Although the PSC staff has requested a few additional pieces of information from ATC, a “completeness determination” by the PSC means the staff is confident that the information and data contained in ATC’s Paddock – Rockdale proposal will allow the agency to perform a comprehensive analysis of the proposal. “We hope to have a decision later this year or early next year,” said Flygt. “This regulatory review follows two years of analysis by our planners. If approved, this project will complete a connection to Illinois that will allow local distribution companies access to lower-cost power produced in the region.”

Wisconsin has limited transmission line connections to other states, which reduces access to wind energy and lower-cost sources of electricity from other regions. According to Flygt, six of seven scenarios studied by ATC showed that the project would pay for itself over its lifetime. “The new line could yield a 40-year net savings on the low end of $100 million and almost $1 billion on the high end. On an annual basis, the savings could be between $7 million and $125 million. The cost of the project is about $133 million,” she said.

“Timing is important and we’re encouraged by the PSC’s timetable for review. Our in-service target is 2010, which coincides with the expiration of some of the federal market protection for our service area. Supporting a more competitive market for utilities will translate to savings to consumers,” said Flygt. The regulatory application includes two possible locations for the new 345-kV circuit, and both make use of existing transmission line corridors. If the project is approved, the PSC will select one route for construction as part of its decision.

]]>
http://www.atcllc.com/news/psc-begins-formal-review-of-atc%e2%80%99s-application-for-paddock-%e2%80%93-rockdale-project/feed/ 0
Underground power line study leads to route options off Beltline highway, through neighborhoods http://www.atcllc.com/news/underground-power-line-study-leads-to-route-options-off-beltline-highway-through-neighborhoods/ http://www.atcllc.com/news/underground-power-line-study-leads-to-route-options-off-beltline-highway-through-neighborhoods/#comments Wed, 30 May 2007 08:00:49 +0000 http://www.atcllc.com/?p=942 ATC will not propose underground construction for proposed Rockdale-West Middleton project

MADISON, Wis.—The conclusion of a study on constructing the proposed Rockdale – West Middleton high voltage transmission line underground is that Madison’s Beltline highway is not a suitable location for underground facilities.

The locations identified as the most feasible include routes off the Beltline on city streets and frontage roads. “Although we assumed the Beltline might offer undergrounding possibilities, the routes we found the most feasible from a construction standpoint deviate from the Beltline between Verona Rd. and west to the West Middleton Substation,” said Mark Williamson, vice president of Major Projects. “The routing guidelines are different for underground facilities. Portions of the Beltline were found to be unsuitable for underground construction because of access issues from private property, volume and speed of traffic and steep slope conditions along the edge of the Beltline right-of-way. All combine to make this type of construction along the Beltline impractical.”

ATC conducted the underground study—the first to be conducted by the company for a 345-kilovolt line—in response to requests from the Public Service Commission of Wisconsin and several local governments to evaluate options for undergrounding the proposed transmission line near the Beltline and in parts of Fitchburg. According to Williamson, the company will not be recommending underground construction because of operational and cost concerns. “It is simply imprudent to construct underground lines at a cost many times greater than overhead lines knowing the trade-off is greater operational limitations,” he said. “It’s like paying a premium for a high-end coffee maker that makes worse coffee than a more economical model.”

Williamson explained that Wisconsin currently doesn’t have any power lines of this voltage underground. “The findings will be useful for future 345-kV proposals. The results we have now offer a comprehensive analysis of underground routing and construction feasibility for a line at this voltage. More detailed studies on the reliability of the specific underground line proposals are ongoing and results will be provided as part of ATC’s filing with the PSC.”

In its application to the PSC, ATC will provide the study’s final results including cost, route and feasibility analyses on a segment by segment basis. The analysis was performed in segments to allow state regulators the option of designating that certain segments be constructed underground while constructing others overhead. One such segment is the area between South Towne Dr. and Verona Rd., which has been the focus of many questions from adjoining landowners. The analysis of this six-mile segment shows the cost to construct the line overhead is estimated to be $20 million, while the cost to construct the same route underground is estimated to be $128 million, or almost 6 times more costly.

Among those who have a stake in the study results are property owners along the newly identified underground routes. “Most of these property owners have not been previously involved in the two-year public process leading up this point,” said Williamson. “It is our obligation to notify these landowners of the possible impact an underground line could have on their property and their neighborhoods if the PSC were to require portions to be placed underground.”

ATC will host open house meetings on June 11, 12, and 13 to discuss the underground line route proposals. “We want to introduce the overall project to people who are new to this process and give them an opportunity to ask questions,” explained Williamson. “Since it ultimately will be up to the PSC to determine if and where the line is built—and whether or not it should go overhead or underground it is prudent to make sure the public is aware of all the possibilities.”

The company expects to announce its final overhead routes for the transmission line project in late July of this year and file for the necessary approvals from state regulators in October.

]]>
http://www.atcllc.com/news/underground-power-line-study-leads-to-route-options-off-beltline-highway-through-neighborhoods/feed/ 0
ATC to rebuild power lines in Marinette County http://www.atcllc.com/news/atc-to-rebuild-power-lines-in-marinette-county/ http://www.atcllc.com/news/atc-to-rebuild-power-lines-in-marinette-county/#comments Fri, 25 May 2007 08:00:38 +0000 http://www.atcllc.com/?p=940 Original line built in 1910

DE PERE, Wis. – American Transmission Co., has received approval from the Public Service Commission of Wisconsin to rebuild a 13-mile power line between the Crivitz and High Falls substations in Marinette County. The original line was built in 1910 to deliver energy generated at hydro-electric plants along the Upper Peshtigo River to the city of Green Bay.

“The line needs to be upgraded and its capacity increased to meet reliability needs and provide additional operating flexibility under certain conditions,” explains David Hovde, local relations representative for ATC. Voltage of the double-circuit line will remain 69,000 volts, but larger conductors (wires) will be used to increase the line’s capacity.

Estimated cost of the project is $23.4 million. Construction is expected to begin in summer 2008. Landowners along the right-of-way have been informed of the project and will continue to be kept apprised as the project proceeds.

]]>
http://www.atcllc.com/news/atc-to-rebuild-power-lines-in-marinette-county/feed/ 0
Natural Resources Foundation awards grants to nonprofit conservation initiatives http://www.atcllc.com/news/natural-resources-foundation-awards-grants-to-nonprofit-conservation-initiatives/ http://www.atcllc.com/news/natural-resources-foundation-awards-grants-to-nonprofit-conservation-initiatives/#comments Thu, 12 Apr 2007 08:00:02 +0000 http://www.atcllc.com/?p=938 ATC Stewardship Fund is part of Green Tier agreement with WDNR

MADISON, Wis. – The Natural Resources Foundation of Wisconsin is supporting nearly a dozen nonprofit conservation groups and programs throughout the state with funding from American Transmission Co.’s Environmental Stewardship Fund, maintained by the Foundation. The ATC fund is part of the company’s commitment through its Green Tier agreement with the Wisconsin Department of Natural Resources.

Diverse projects were chosen by a selection process overseen by the Foundation’s Environmental Stewardship Fund committee. The committee, made up of conservation professionals from the nonprofit and public sector, reviewed proposals from nonprofit organizations and agencies for projects involving

  • endangered species protection,
  • habitat restoration and management,
  • community-based conservation,
  • environmental education and outreach.

Projects deemed to have the highest conservation importance are recommended to the Natural Resources Foundation board of directors for approval. Grants for 2007 are being disbursed beginning this month.

“ATC’s commitment of $300,000 in annual funding is the kind of partnership that is critical in supporting a wide variety of environmental stewardship programs and land conservation efforts across the state,” explains Charlie Luthin, executive director of the Natural Resources Foundation of Wisconsin. “The Green Tier program requires companies to achieve, document and maintain a level of environmental performance that is above and beyond what is required by law. The ATC Environmental Stewardship Fund is part of that commitment.”

“We are happy to support the work of statewide and local conservation groups,” says Rita Hayen, manager of ATC’s environmental department. “When we can, we try to avoid impacts and minimize our presence in construction, operation and maintenance of transmission lines. The fund is another way we demonstrate our commitment to environmental protection.”

Following is a sample of some initiatives selected by the NRF to receive funds in 2007:

Gathering Waters Conservancy is a statewide umbrella group for land trusts. In 2006, the organization received a $30,000 grant to support a public outreach initiative in support of the Knowles-Nelson Stewardship Fund. Named after a former governor and former senator renowned as conservation leaders, the program is designed to preserve valuable natural areas and wildlife habitat, protect water quality and fisheries, and expand opportunities for outdoor recreation. “We organized a ‘parade of preserves’ to show state residents what the Knowles-Nelson Fund has done in their backyards,” explains Vicki Elkin, stewardship campaign director. “The grant allowed us to organize field trips to six natural areas around the state that have been protected with Stewardship Fund support.” Gathering Waters has received a 2007 grant to develop and implement a statewide communication plan about the value of the Stewardship Fund, including a publication, “Stories of Stewardship: Tales from Wisconsin’s Big Backyard.”

Mequon Nature Preserve is a 438-acre natural area within the city limits of Mequon, which officials are preserving as “a premier environmental education and recreation facility,” according to Mayor Christine Nuernberg. A master plan was completed for the preserve in 2006, and a grant from the fund is being used to develop a comprehensive trail system, scheduled to be completed in Summer 2007.

C.D. Besadny Conservation Grants Program funds projects that encourage conservation activities to promote the responsible stewardship of Wisconsin’s natural resources at the local level. The matching grants program, named after a former DNR Secretary who championed environmental education, support community groups with projects ranging from habitat restoration, accessibility, environmental education and control of invasive species. The ATC fund has supported about 38 community projects in the past two years.

James Madison Memorial High School in Madison received a 2006 Besadny grant to conduct a State Natural Areas study and field trip project. “The students were very impressed with the quality of our State Natural Areas,” says Nancy Piraino, science teacher at Memorial. “Any exposure to natural areas will hopefully heighten student interest and help them learn to appreciate the value of these sites for their protection and preservation.”

Endangered species programs also are being supported by grants from the ATC fund, including those designed to protect the following:

  • Wood turtle (statewide)
  • Karner blue butterfly (Burnett, Jackson, Monroe, Wood, Juneau, Adams, Waushara, Waupaca, Green Lake, Portage, Monroe counties
  • Kirtland’s warbler (Jackson, Douglas, Washburn, Vilas, Marinette, Oconto counties)
  • American Marten (Ashland, Bayfield, Sawyer counties)

The Natural Resources Foundation of Wisconsin is a nonprofit organization that creates opportunities for individuals and organizations who care about Wisconsin’s lands, waters and wildlife to: deepen their understanding and appreciation for these resources; support state and local conservation programs; and create conservation endowments. For more information on the Natural Resources Foundation or the Wisconsin Conservation endowment, visit www.wisconservation.org

]]>
http://www.atcllc.com/news/natural-resources-foundation-awards-grants-to-nonprofit-conservation-initiatives/feed/ 0
Rockdale- West Middleton Electric Transmission Line Project http://www.atcllc.com/news/rockdale-west-middleton-electric-transmission-line-project/ http://www.atcllc.com/news/rockdale-west-middleton-electric-transmission-line-project/#comments Tue, 10 Apr 2007 08:00:26 +0000 http://www.atcllc.com/?p=936 ATC adjusting project timetable: more detailed study needed on undergrounding, environmental impacts and route options

(MADISON) – American Transmission Co. is modifying its filing date to the Public Service Commission of Wisconsin by at least three months for the Rockdale-West Middleton 345-kilovolt transmission line project. Originally, ATC planned to file its construction application with the PSC in June, but will now target October 2007.

“We are being responsive and responsible to the people of Dane County,” said Mark Williamson, vice president of Major Projects. “We have a critical need here, but taking some additional time to address concerns and issues is a reasonable and prudent compromise.”

ATC unveiled three general route options last summer for connecting the Rockdale and West Middleton electric substations in Dane County and expected to be ready to announce the final routes this month. “During the past year, residents, stakeholders and elected officials have actively engaged in the process, made recommendations to us, and asked appropriate questions,” said Williamson. “Among them is the feasibility of placing high-voltage transmission lines underground along portions of the routes.”

In addition to undergrounding, questions about electric usage forecasts, environmental impacts and the recent Department of Transportation concerns about the Beltline route have added work to the preparation of the company’s application to the PSC. Williamson reiterated the crucial need for this project. “We’re eager to get this project in the hands of the regulators, but we want to fully explore these issues without compromising our ability to keep the lights on. Today, we’re looking at an in-service date in 2013, rather than in 2012.”

According to Williamson, the preliminary evaluation of underground construction suggests that it is not a feasible option for the 345,000-volt project. “The significant added cost is only one factor. We continue to have serious concerns about the construction, reliability and environmental impact of placing power lines of this voltage underground,” he explained. “However, we’ve agreed to perform a more comprehensive analysis and develop detailed underground transmission line options for project at the request of the PSC and the public. This analysis will be included in our application to the PSC.”

Dane County is one of the fastest growing counties in Wisconsin and few significant improvements have been made to the transmission infrastructure in nearly 30 years. The county is mainly served by a network of 69- and 138-kilovolt transmission lines. The expected growth in the coming years cannot be served by the existing system. A new 345-kilovolt line will allow power to flow in from other areas to efficiently serve Dane County and boost the reliability of the entire network.

The regulatory review process, which will begin after the PSC receives ATC’s application this fall, will likely continue through most of 2008—during which time the public will have an opportunity to participate in public hearings on the project.

To monitor project developments including the timeline and current route maps, visit ATC’s web site at www.atcllc.com

]]>
http://www.atcllc.com/news/rockdale-west-middleton-electric-transmission-line-project/feed/ 0
New electric transmission line energized on east side of Dane County http://www.atcllc.com/news/new-electric-transmission-line-energized-on-east-side-of-dane-county/ http://www.atcllc.com/news/new-electric-transmission-line-energized-on-east-side-of-dane-county/#comments Tue, 20 Feb 2007 08:00:32 +0000 http://www.atcllc.com/?p=934 Femrite – Sprecher transmission line completed under budget and ahead of schedule

MADISON, Wis. – American Transmission Co. placed in service last week a new 138-kilovolt electric transmission line connecting the Sprecher Substation, located near the Sprecher Road / CTH BB intersection, with the Femrite Substation, located on Femrite Drive near the I-90 /USH 12/18 interchange.

Construction began last spring on the underground portion of the line, running along Buckeye Road east of the Interstate 90 and north on Sprecher Road to the substation on Cottage Grove Road. Construction on the overhead portion from the Femrite Substation to I 90 and Buckeye Road began last summer and wrapped up last week—several months ahead of schedule and under budget.

The four-mile transmission line helps support local electricity needs and back up other critical facilities on the system. “It also will help to strengthen the reliability of the transmission system serving the east side of Madison and neighboring communities,” said Mark Williamson, ATC vice president of major projects. “The electrical path that has been completed around the city with this line provides an alternate path for electricity to flow in the event of an outage on another line.”

This project is one among several needed to reinforce the electric system in and around Dane County. “This project is one of our critical short-term upgrades to Dane County’s transmission network,” Williamson said. “It gives us a solution and helps buy us a bit of time to work on our larger projects.”

ATC expects to reach milestones in 2007 on several other projects in Dane County.

  • Final proposed routes will be announced in later this year for the 345-kilovolt Rockdale-West Middleton project.
  • A decision is expected this summer on the 138-kilovolt line proposed for the Waunakee area.
  • The 138-kilovolt proposed line between Verona and Fitchburg is being reviewed by the Public Service Commission with public hearings expected this summer.
]]>
http://www.atcllc.com/news/new-electric-transmission-line-energized-on-east-side-of-dane-county/feed/ 0
ATC awards major construction contract http://www.atcllc.com/news/atc-awards-major-construction-contract/ http://www.atcllc.com/news/atc-awards-major-construction-contract/#comments Tue, 13 Feb 2007 08:00:32 +0000 http://www.atcllc.com/?p=932 The Boldt Company to furnish services in southern Wisconsin

PEWAUKEE, Wis. – American Transmission Co. has selected The Boldt Company as general contractor to provide transmission line and substation construction services for projects in southeastern and south central Wisconsin.

“This is the latest in a series of long-term agreements we have signed with premier construction companies,” explains Mike Rowe, ATC vice president for construction. “This three-year contract with Boldt will enable us to proceed with our ambitious plan to maintain and improve electric reliability across the southern third of Wisconsin.”

“The Boldt Company is very excited to be part of the ATC team to implement this construction program,” states Jim Lee, Boldt’s group president, Northern Operations. “ATC has Boldt’s commitment to uphold high standards in safety and to provide cost-effective, value-added construction services.”

Under the agreement, Boldt will provide all construction resources, including labor, equipment and management strategies, for projects managed by ATC offices in Pewaukee and Madison.

ATC’s most recent 10-year plan calls for $3 billion in construction and maintenance projects across its four major portfolios of assets. Long-term agreements help manage construction costs by leveraging resources, equipment and services across a broader base of assets. Working relationships also are established that contribute to common goals for safety and environmental stewardship.

ATC recently signed a three-year agreement with MJ Electric, LLC, an InfraSource Co., for general construction services for its northern portfolio. A contract was signed with Kenny Construction for services to ATC’s central portfolio in 2005.

“These agreements fulfill our strategy of securing high quality construction service partners to help us execute our capital construction program,” Rowe says.

]]>
http://www.atcllc.com/news/atc-awards-major-construction-contract/feed/ 0
Delgado elected chair of new national electric reliability forum http://www.atcllc.com/news/delgado-elected-chair-of-new-national-electric-reliability-forum/ http://www.atcllc.com/news/delgado-elected-chair-of-new-national-electric-reliability-forum/#comments Thu, 01 Feb 2007 08:00:47 +0000 http://www.atcllc.com/?p=928 Group to focus on enhancing transmission grid operations and reliability

MADISON, Wis. – Thirty representatives from many of the largest electric transmission owners and operators in the U.S. and Canada elected José M. Delgado, president and CEO of American Transmission Co. as chairman of the North American Electric Reliability Corporation’s (NERC) newly established Transmission Owners and Operators Forum. W. Terry Boston, the Tennessee Valley Authority’s executive vice president of power system operations was elected its vice-chairman.

The TOO forum is a new effort by members of NERC to provide a transmission-specific venue for enhancing grid operations; it is open to both large and small, publicly owned and privately held participants.

NERC oversees the reliability and security of the bulk power system in North America (US, Canada and parts of Mexico) and is responsible for developing and enforcing reliability standards and assessing the reliability of the system and the readiness of its operators.

The goal of the new TOO forum is to improve the reliability of the electricity grids through the identification and sharing of best practices in transmission system operations. It provides an opportunity for transmission owning and operating utilities to assist each other through the exchange of information on all aspects of transmission operations.

Delgado was also recently appointed to a two-year term as Co-Chairman of the Edison Electric Institute’s CEO task force on electric system reliability which focuses on regulatory policy.

]]>
http://www.atcllc.com/news/delgado-elected-chair-of-new-national-electric-reliability-forum/feed/ 0
ATC awards construction contract http://www.atcllc.com/news/atc-awards-construction-contract/ http://www.atcllc.com/news/atc-awards-construction-contract/#comments Thu, 01 Feb 2007 08:00:42 +0000 http://www.atcllc.com/?p=930 Iron Mountain, Mich. firm to provide services

DE PERE, Wis. – American Transmission Co. has selected MJ Electric LLC, an InfraSource Co., as general contractor to provide construction services for transmission line and substation projects in northeastern Wisconsin and Michigan’s Upper Peninsula.

“MJ Electric has a demonstrated track record of providing superior construction services in a ‘safety-first’ atmosphere,” said Mike Rowe, ATC vice president for construction. “This three-year alliance with MJE will meet our goal to establish a long-term, reliable source of construction services that meets our cost, schedule and project requirements. MJE’s work practices also are consistent with our environmental goals.”

“Obviously, we are very excited about this opportunity to partner with ATC on future projects,” stated Stephen J. Reiten, president of MJE. “This is a very significant event for us and we are pleased that ATC is demonstrating confidence in our capabilities with this alliance. We look forward to the opportunity of contributing to ATC’s future success.”

Under the agreement, MJE will provide all construction resources, including labor, equipment and management strategies, to safely and cost-effectively implement ATC’s construction projects in the company’s northern portfolio. ATC’s 10-year plan calls for nearly $3 billion in construction and maintenance activities to ensure electric reliability. ATC’s investment in the northern portfolio, which is managed by offices in De Pere and Kingsford, Mich., is estimated to be more than $500 million over the next 10 years.

]]>
http://www.atcllc.com/news/atc-awards-construction-contract/feed/ 0
Application for power line between Fitchburg and Verona deemed complete by PSC http://www.atcllc.com/news/application-for-power-line-between-fitchburg-and-verona-deemed-complete-by-psc/ http://www.atcllc.com/news/application-for-power-line-between-fitchburg-and-verona-deemed-complete-by-psc/#comments Tue, 30 Jan 2007 08:00:49 +0000 http://www.atcllc.com/?p=926 Regulatory review process begins on ATC’s proposal

MADISON, Wis. – American Transmission Co.’s application seeking approval to construct a new electric transmission substation (called the Oak Ridge Substation) in the City of Fitchburg and a new transmission line that would connect to the existing Verona substation was declared complete Monday by the Public Service Commission. This decision marks the beginning of the roughly six-month regulatory review process, which will include engineering and environmental scrutiny and a public hearing.

“Although the PSC staff has requested a few additional pieces of information from ATC, their completeness determination means they have the information and documentation needed to begin a thorough review and evaluation of the project,” explained Sarah Justus, ATC local relations representative. “We hope to have a decision on the project from the PSC next summer.”

The PSC staff analyzes the transmission line application for need and potential impacts, alternative solutions, engineering, economics, safety and also reviews the route options recommended by ATC.

ATC’s application, which was filed in December, proposes to construct the Oak Ridge substation near the intersection of Fish Hatchery Road and Irish Lane in the City of Fitchburg. The proposed 6-mile, 138-kilovolt transmission line would connect the new Oak Ridge substation with the existing Verona substation. The total estimated cost of these improvements is approximately $19 million.

South central Dane County has experienced dramatic growth in recent years and the electric system needs to be reinforced to accommodate the increased electrical usage. This project will strengthen both ATC’s transmission system and Madison Gas & Electric’s local distribution system to ensure safe and reliable electric service.

ATC’s proposal for a 345-kilovolt transmission line between the towns of Christiana and Middleton is still under route review. The company expects to finalize the routes options that will be included in its application this spring and submit the application in June.

]]>
http://www.atcllc.com/news/application-for-power-line-between-fitchburg-and-verona-deemed-complete-by-psc/feed/ 0
ATC helps make Gilda’s Club the real winner in Raise the Roof event http://www.atcllc.com/news/atc-helps-make-gilda%e2%80%99s-club-the-real-winner-in-raise-the-roof-event/ http://www.atcllc.com/news/atc-helps-make-gilda%e2%80%99s-club-the-real-winner-in-raise-the-roof-event/#comments Mon, 29 Jan 2007 08:00:40 +0000 http://www.atcllc.com/?p=922 Company donates 25 cents per fan attending UW Women’s Basketball game; matches Coach Stone’s gift

Madison, Wis. – Yesterday’s Badger win in the face off between the women’s basketball teams from UW-Madison and the University of Minnesota also was a win for Gilda’s Club of Madison. The sell-out crowd at the Kohl Center meant the cancer support organization, Gilda’s Club, will receive $4,285 from American Transmission Co.

“We teamed up with the Badgers and their fans to raise money for Gilda’s Club,” said Sarah Justus. “We pledged 25 cents to the organization for every fan who attended yesterday’s game, matching Coach Stone’s donation of 25 cents per fan.”

As part of ATC’s sponsorship and support of the Raise the Roof event, the company purchased 500 tickets and donated more than 400 of the tickets to community and youth groups. The remaining tickets were distributed to company employees. “Our company and its employees are part of this community, and we’re privileged to support worthy causes and organizations,” explained Justus.

]]>
http://www.atcllc.com/news/atc-helps-make-gilda%e2%80%99s-club-the-real-winner-in-raise-the-roof-event/feed/ 0
ATC near completion of year-long analysis of underground construction alternatives for proposed Rockdale – West Middleton power line http://www.atcllc.com/news/atc-near-completion-of-year-long-analysis-of-underground-construction-alternatives-for-proposed-rockdale-west-middleton-power-line/ http://www.atcllc.com/news/atc-near-completion-of-year-long-analysis-of-underground-construction-alternatives-for-proposed-rockdale-west-middleton-power-line/#comments Tue, 23 Jan 2007 08:00:27 +0000 http://www.atcllc.com/?p=918 Overhead power lines remain the most affordable, practical industry standard

Madison, Wis. – The findings of American Transmission Company’s year-long analysis of burying portions of its proposed Rockdale – West Middleton transmission line will be made available to the Public Service Commission of Wisconsin. However, the company won’t be proposing underground lines or asking the PSC to approve them when its application is submitted for regulatory review next June. “Our analysis shows that overhead facilities are the better option,” said Mark Williamson, vice president of Major Projects.

Although ATC has not yet finalized its proposed route options for the proposed Rockdale – West Middleton line, there are concerns among local elected officials about placing overhead facilities along the Beltline. City of Madison officials have asked the PSC to give “serious consideration to undergrounding the line.”

“As a matter of practice, our project proposals for electric transmission lines always include an analysis of alternatives,” explains Williamson. “During the past year, we’ve been studying the costs and feasibility of placing portions of the Rockdale – West Middleton line underground. Our analysis overwhelmingly shows there’s no adequate justification for undergrounding the line within a mature commercial, controlled access highway corridor like the Beltline.”

Williamson acknowledged that advances are being made in the technology for burying transmission lines, but argued it’s still too costly and environmentally invasive. “The Beltline is not a justifiable candidate for undergrounding due to higher costs, increased environmental intrusion, and heightened electric system operational risks,” he said. “Underground construction adds between $9 million and $15 million per mile to the cost of these facilities compared to overhead lines. To bury the 15-mile portion between Stoughton Road and Middleton translates to between $135 million and $225 million in additional costs—more than doubling the total cost of the 35-mile project compared to building it entirely on overhead structures.”

Because the costs associated with major utility projects are spread among all electricity customers in ATC’s service area, Williamson said ATC is concerned about the precedent that would be created if lines were buried along the Beltline. “We have hundreds of communities throughout our service area that could make the same argument for burying lines,” he said. “Burying transmission lines in all the communities in which we are working would result in huge cost increases for industrial, commercial and residential customers.”

According to a 2006 report published by the Edison Electric Institute, studies of statewide undergrounding initiatives in Florida and North Carolina suggest undergrounding would require rate increases ranging from 80 percent to 125 percent from current rates. A Virginia study calculates the annual cost of a statewide undergrounding initiative at approximately $3,500 per customer.

]]>
http://www.atcllc.com/news/atc-near-completion-of-year-long-analysis-of-underground-construction-alternatives-for-proposed-rockdale-west-middleton-power-line/feed/ 0
Public Service Commission begins review of Fitchburg – Verona Electric Upgrade http://www.atcllc.com/news/public-service-commission-begins-review-of-fitchburg-%e2%80%93-verona-electric-upgrade/ http://www.atcllc.com/news/public-service-commission-begins-review-of-fitchburg-%e2%80%93-verona-electric-upgrade/#comments Thu, 28 Dec 2006 08:00:14 +0000 http://www.atcllc.com/?p=916 New line is needed to meet growing demand in South Central Dane County

MADISON, Wis. – The formal regulatory review is underway for a new substation in the City of Fitchburg and a new transmission line connecting the proposed Oak Ridge Substation with an existing substation in the City of Verona. American Transmission Co. today filed its application for the Fitchburg – Verona project with the Wisconsin Public Service Commission.

ATC is proposing to construct the Oak Ridge substation near the intersection of Fish Hatchery Road and Irish Lane in the City of Fitchburg. The proposed 6-mile, 138-kilovolt transmission line would connect the new Oak Ridge substation with the existing Verona substation. The total estimated cost of these improvements is approximately $19 million.

The project is needed to meet growing demand for electricity in south central Dane County. “This part of the county has seen dramatic growth and the electric system has not kept pace,” explains Sarah Justus, ATC local relations. “The existing facilities are projected to become overloaded by the summer of 2009. This project will strengthen both ATC’s transmission system and Madison Gas & Electric’s local distribution system to ensure safe and reliable electric service.”

Over the last 18 months, ATC has worked with local residents, elected officials and others to gather input and answer questions about the project. “We appreciate the involvement of the public in this project to date and look forward to continued public input as this project moves to the regulatory stage” says Justus. During the regulatory review the Public Service Commission will review the need for the project and the proposed routes. The PSC will also work with the Department of Natural Resources to conduct an environmental review.

]]>
http://www.atcllc.com/news/public-service-commission-begins-review-of-fitchburg-%e2%80%93-verona-electric-upgrade/feed/ 0
PSC approves transmission line project in Dodge County http://www.atcllc.com/news/psc-approves-transmission-line-project-in-dodge-county/ http://www.atcllc.com/news/psc-approves-transmission-line-project-in-dodge-county/#comments Fri, 15 Dec 2006 08:00:07 +0000 http://www.atcllc.com/?p=914 138-kV lines needed to ensure reliability for electricity customers

MADISON, Wis. – After months of public input and regulatory review, the Public Service Commission of Wisconsin gave its final approval for construction of a $17 million power line proposed by American Transmission Co.

ATC will build a new 13-mile, 138-kilovolt line to connect a new substation to be located near Horicon with an existing substation located south of Neosho. The PSC approved ATC’s recommended route, which runs parallel and just east of County Road TW through the Town of Hubbard and the Town of Hustisford.

Population in Dodge County has increased 25 percent since 1970. Electricity usage is increasing 3 percent annually in most areas of the county. No significant new electric infrastructure has been built in the past 20 years, and the transmission system is operating at its limits. The transmission line will address electric system instability and will accommodate a new electric substation in the Village of Hustisford as well.

“Approval of this project is good news for homeowners, businesses and industries that enjoy all the benefits of a reliable electric system,” said John Garvin, ATC local relations. “We hope that landowners will continue to stay involved as we prepare for construction.”

ATC first introduced the project to area residents in summer 2004 and submitted its regulatory application in late 2005. Construction is expected to begin in April 2007, and the project is anticipated to be completed in May 2008.

Note to editors: Additional background information, including maps, is available at www.atcllc.com.

]]>
http://www.atcllc.com/news/psc-approves-transmission-line-project-in-dodge-county/feed/ 0
ATC names directors to new positions http://www.atcllc.com/news/atc-names-directors-to-new-positions/ http://www.atcllc.com/news/atc-names-directors-to-new-positions/#comments Thu, 07 Dec 2006 08:00:26 +0000 http://www.atcllc.com/?p=912 PEWAUKEE, Wis. – American Transmission Co. has named Flora Flygt director of Planning, and Randy Satterfield director of Regulatory, Government Affairs and Communications. In addition, Mike Hofbauer was named Corporate Controller, and Tom Finco, director of Real Estate, has additional responsibilities for local relations and environmental.

Flygt, director of Planning, has been in the utility business for more than 25 years. She joined ATC in 2005 to work on business development. She previously was employed by Alliant Energy and Madison Gas & Electric in the areas of long-term forecasting, demand-side planning, integrated resource planning, environmental planning, market research, strategic planning and business development. She has a bachelor’s degree in economics from the University of Michigan and a master’s of science degree in land resources, energy analysis and policy from the University of Wisconsin.

Satterfield, director of Regulatory, Governmental Affairs and Corporate Communications, joined ATC in 2003 as director of Communications. Previously, Satterfield was senior account manager for Wood Communications Group in Madison. Prior to Wood, Satterfield served as an assistant director in the Bureau of Consumer Protection at the Federal Trade Commission in Washington D.C. He has extensive experience in communications, advertising, political consulting and international public relations. He holds undergraduate degrees in philosophy and political science from Marquette University.

Mike Hofbauer has been named Corporate Controller and will be responsible for accounting, financial reporting, taxes and budgets. Hofbauer joined ATC in 2000 as director of Accounting. Prior to ATC, Hofbauer was senior manager with Arthur Andersen LLP in Illinois, where he managed multi-million dollar consulting projects for various industries and governmental entities. Prior to joining Arthur Andersen, Hofbauer was a corporate accounting manager with Midway Airlines. He is a certified public accountant with a bachelor’s degree in business administration from the University of Notre Dame and a master’s degree in business administration from the University of Chicago.

Tom Finco, director of Real Estate, now also will oversee ATC’s Environmental and Local Relations groups. Finco joined ATC in 2000 as manager of Real Estate. Prior to ATC, Finco spent 11 years at Alliant Energy in various leadership positions in the real estate area. He has a bachelor’s degree in geography information systems from the University of Wisconsin-Stevens Point and a master’s of business administration from the University of Wisconsin-Madison. He is a licensed real estate broker in the state of Wisconsin and a licensed surveyor in Wisconsin and Iowa.

]]>
http://www.atcllc.com/news/atc-names-directors-to-new-positions/feed/ 0
Critical segment of Arrowhead-Weston transmission line successfully energized http://www.atcllc.com/news/critical-segment-of-arrowhead-weston-transmission-line-successfully-energized/ http://www.atcllc.com/news/critical-segment-of-arrowhead-weston-transmission-line-successfully-energized/#comments Wed, 06 Dec 2006 08:00:03 +0000 http://www.atcllc.com/?p=910 345-kilovolt line more than 70 percent complete, on schedule for 2008 completion

WAUSAU, WIS. – American Transmission Co. has completed the second week of successful tests on a 143-mile segment of the Arrowhead-Weston transmission line between Weston Power Plant and Stone Lake Substation in Sawyer County. The line is now in service, though carrying less than its full capacity, and will reinforce the existing transmission system in northwest Wisconsin. It will carry the full 345-kilovolt load when the line is completed in 2008.

“This is a giant step forward for the residents and businesses of northwest Wisconsin and throughout the Midwest. With Arrowhead-Weston becoming a reality, electric system reliability will be greatly improved,” said Pete Holtz, ATC project manager of the Arrowhead-Weston line. “Cooperation from residents along the line has been a critical component in getting this important public works project nearer to completion.”

Testing of the line began Nov. 16, according to Holtz, without any major problems and was placed in service Nov. 30. The Weston to Stone Lake segment will reinforce the area between Wausau and Hayward so construction can continue north to Douglas County and the City of Superior. The energized line will supply needed power as the existing lines are taken out of service and rebuilt on the new 345-kV structures.

“We still have 66 miles to go, but our engineering and construction crews deserve a tremendous amount of credit for the superb work they’ve done on this project,” said Dave Valine, Wisconsin Public Service Corp. construction coordinator. “This is a major accomplishment, the benefits of which Wisconsin residents will soon reap.”

Construction on the Arrowhead-Weston project currently is focused in Douglas and Washburn counties. Completion of the 210-mile transmission line project is scheduled before May 2008. The project is entering its ninth year of planning, development, approval and construction.

ATC will own and operate the line upon completion. WPS has been in charge of construction activities and coordinating those activities with Minnesota Power, which has already completed the 12-mile segment in Minnesota.

]]>
http://www.atcllc.com/news/critical-segment-of-arrowhead-weston-transmission-line-successfully-energized/feed/ 0
Chinn named COO of American Transmission Co. http://www.atcllc.com/news/chinn-named-coo-of-american-transmission-co/ http://www.atcllc.com/news/chinn-named-coo-of-american-transmission-co/#comments Tue, 05 Dec 2006 08:00:23 +0000 http://www.atcllc.com/?p=908 PEWAUKEE, Wis. – American Transmission Co. has named Carol Chinn as ATC’s chief operating officer. Chinn will join ATC on Dec. 18, 2006, in this newly created position, and oversee ATC’s construction, maintenance and system operations areas. Chinn currently is with the Federal Energy Regulatory Commission in the Division of Reliability.

Prior to FERC, Chinn was president and chief executive officer of Georgia Transmission Corp., an electric transmission utility with more than $1 billion in assets. Previously, she spent 18 years at Florida Power & Light in various planning, engineering, construction and operations management positions in transmission and distribution, along with corporate strategy and quality leadership roles.

“ATC is known as an industry leader and the successful model for a stand-alone transmission company,” said Chinn. “I am energized about joining the ATC team and contributing to its future success in asset delivery, asset management and system operations.”

In its first five years, ATC has invested more than $1 billion in the transmission grid serving most of Wisconsin and Michigan’s Upper Peninsula. The company is planning another $3 billion in investment over the next 10 years.

Chinn will report to José Delgado, president and chief executive officer, who said, “Carol brings to ATC proven experience in utility operations, strategic planning and organizational leadership. We are looking forward to her oversight and coordination of our system operations, maintenance and construction plan.”

Chinn earned a bachelor’s degree in environmental engineering from the University of Florida at Gainesville, a bachelor’s degree in electrical engineering from the University of Miami, and a master’s of business administration from the University of Florida at Gainesville.

]]>
http://www.atcllc.com/news/chinn-named-coo-of-american-transmission-co/feed/ 0
PSCW approves transmission line project in northern Wisconsin and Upper Michigan http://www.atcllc.com/news/pscw-approves-transmission-line-project-in-northern-wisconsin-and-upper-michigan/ http://www.atcllc.com/news/pscw-approves-transmission-line-project-in-northern-wisconsin-and-upper-michigan/#comments Wed, 22 Nov 2006 08:00:17 +0000 http://www.atcllc.com/?p=906 138-kV lines needed to ensure reliability for electricity customers

MADISON, Wis. – After many months of public input and regulatory review, the Public Service Commission of Wisconsin gave its final approval to a power line project proposed by American Transmission Co.

The Cranberry-Conover-Plains project is needed because significant growth in the Rhinelander and Eagle River areas has resulted in an overloaded electric system that is vulnerable and subject to blackouts under certain conditions. The new and improved line will significantly improve reliability in the region long-term and improve ATC’s ability to move power in and around northeastern Wisconsin and Michigan’s Upper Peninsula.

ATC will build a new 138-kilovolt, 16 mile line between Eagle River and Conover, and convert about 73 miles of existing lines between Conover and Quinnesec, Mich., from 69 kilovolts to 138 kilovolts. The cost of the project is estimated at $116.4 million.

“The transmission lines to the east of Eagle River that connect northern Wisconsin to the Upper Peninsula are some of the most severely constrained in the ATC system,” states Franc Fennessy, ATC manager of local relations. “Approval of this project is good news for homeowners, businesses and industries that enjoy all the benefits of a reliable electric system.”

ATC first introduced the project to area residents in Summer 2004 and submitted its regulatory application in late 2005. Construction is expected to begin during the 3rd Quarter of 2007, and the project is anticipated to be completed in late 2009.

Note to editors: Additional background information, including maps, is available at the www.atcllc.com Web site.

]]>
http://www.atcllc.com/news/pscw-approves-transmission-line-project-in-northern-wisconsin-and-upper-michigan/feed/ 0
Updated study of transmission system needs shows slight decrease in costs http://www.atcllc.com/news/updated-study-of-transmission-system-needs-shows-slight-decrease-in-costs/ http://www.atcllc.com/news/updated-study-of-transmission-system-needs-shows-slight-decrease-in-costs/#comments Mon, 13 Nov 2006 08:00:57 +0000 http://www.atcllc.com/?p=904 $1 billion in work is paying off; investment of $3.1 billion is still needed over next 10 years

WAUKESHA, Wis. – In American Transmission Co.’s annual 10-Year Transmission System Assessment report (www.atc10yearplan.com), ATC identifies an estimated $3.1 billion in work needed over the next 10 years to ensure that the transmission grid can reliably meet the electric needs of people and businesses throughout most of Wisconsin and Michigan’s Upper Peninsula.

This is the first time in six years that ATC’s estimated dollar amount for the 10-year plan has gone down and it’s due to a decrease in the number of projects needed to improve reliability and modernize aging equipment. “Our past and current investments are paying off,” said Mark Williamson, ATC vice president of major projects. “In our first five years we’ve been tremendously successful in making improvements, and we are no longer operating the system in crisis mode.”

But Williamson cautioned against believing that the job of upgrading the state’s transmission grid is done. “We cannot make up for 20 to 30 years of minimal investments in transmission in five years’ time. Not only are we just starting to tackle the more embedded constraints on the system, but we face continued growth in population, a surge in the use of automation and electrically powered technologies, and a region-wide disadvantage in the new Midwest energy markets,” he said.

ATC’s service area is designated as constrained by the Midwest Independent System Operator. “Those constraints will continue to cost consumers until we can place our major projects in service,” said Williamson. Transmission costs are the smallest component of a consumer’s electric bill at roughly six percent.

Of the $3.1 billion needed, approximately $1.7 billion would be for adding new equipment, including:

  • constructing 360 miles of new lines,
  • upgrading more than 840 miles of existing lines,
  • installing more than 35 new transformers and
  • installing more than 35 capacitor banks.

Some $1.4 billion would be for improving existing facilities including:

  • maintenance on aging equipment,
  • connections to power plants,
  • infrastructure replacements and relocations, and
  • small network reliability improvements.

Williamson identified southwestern Wisconsin as the portion of ATC’s service area with the greatest need for system upgrades and expansions because low voltages and overloaded facilities threaten the future reliability of the electric system. Low voltages can cause lights to dim or harm to computers or industrial processes. New infrastructure also is needed to accommodate load growth, particularly in and around fast-growing Dane County. ATC is nearing completion of $110 million in short-term improvements begun in 2001 in Dane County to prevent reliability problems. Longer-term upgrades of approximately $300 million through 2015 are in the planning and public outreach stages there.

“In assessing our system,” Williamson says, “we look out 10 years – and now even 20 years – because it can take up to eight years to plan, propose, get approvals and build additions or enhancements to the transmission system. We do not have the luxury of waiting until