|
Pole Replacement in Fox River Presents
Challenges
Pole replacements are generally routine, but a recent project
near DePere presented a unique challenge because the pole was
located in the Fox River and had distribution underbuild.
A routine maintenance inspection revealed that the structure
on a line between Highway V and Nicolet Substations had a
rotten pole and cross-arm. The project involved replacing the
H-frame
structure
in its
entirety during a planning outage. In order to replace the
pole, ATC arranged for a crane on a barge. However, the water
level at that point in the river was only 18"
deep at low tide, so careful planning was needed to transport
the crane and materials at the appropriate times of
the day when the water was at its highest level. Crews
shuttled to the barge in power boats. The poles could not be
transported on the barge due to their weight, and instead
were floated in the river and towed to the work site.
 
In preparation for the work, ATC issued press releases to
the local newspapers and a local fishing internet site. Notification
signs were posted at three boat launches in the vicinity of
the structure and ATC Environmental notified the applicable
permitting agencies of the work, even though no permits were
required.
ATC collaborated with WPS to obtain an outage on the distribution
underbuild line and to coordinate parts procurement and construction
crews to replace old insulators on the distribution line.
The project was completed in two days. ATC Project Manager
Jon Thoresen commented, "The project presented several unique
challenges. In addition to the pole being in the middle of
the Fox River, the shallow water and barge displacement dictated
construction to start early in the year during the high-water
season. To accommodate the local fisherman, ATC waited until
after the spring walleye spawning run to begin construction."
|