|
May 2003 marked the cutover of all transmission lines associated
with the Forest Junction Project. The project is a of a new,
13-acre 345kV/138kV transmission substation in the Town of Brillion,
that involved rebuilding a 75-year-old, 20.2-mile transmission
line from the new Forest Junction Substation to the WPS Hwy
V Substation in Bellevue, the addition of a new transmission
line from the new Forest Junction Substation to the Lost Dauphin
Substation in the Town of Lawrence (Brown County), and demolition
of existing facitilies.
The Forest Junction Project addresses the growing demand for
electricity in the greater Fox River Valley and Green Bay areas,
expands the limited facilities in the region, reduces the potential
for existing facilities to overload, and accommodates future
growth. This results in improved reliability for the area and
increased transfer capability.
From construction kickoff in September 2001, the project maintained
an aggressive schedule. The first 12 miles of the rebuild was
completed in March 2002, and the construction of the new substation
was completed in December 2002. The new transmission line was
placed in service in January 2003 with the complete cut-over
of all lines done in May 2003. All that remains is the demolition
of the existing station. That work is targeted to be finished
in August 2003.
ATC Project Manager Al Bayer is pleased with the progress of
the project. "This very significant system improvement
was completed on schedule and substantially below budget. Our
success is directly attributable to the skill of the construction
contractors used and the terrific support provided by We Energies'
Appleton area electricians, relay technicians and start-up personnel."
|