AMERICAN TRANSMISSION COMPANY   |   ISSUE TWO  

 

 

 

 

Ideas Wanted!
We are eager to hear your ideas, feedback, and suggestions for Connections. Submit articles or ideas you would like to see in an upcoming issue.

 

 

In response to the flooding in Michigan's Upper Peninsula in mid-May, ATC initiated the National Capacitor Bank Project. It was designed to allow 50 Mw of load to be used at the mine after the Presque Isle Power Plant began generation again.

The project consisted of moving an out-of-service 138kV capacitor bank from Forest Junction to the National Substation in Ishpeming. From groundbreaking to in-service, and despite six days of soaking rains, the project took only 16 days. The capacitor bank was energized on June 13, 2003.

The project's original purpose was to assist moving electricity to the mine, but other benefits now have become apparent. The permanent installation of the capacitor bank will contribute to the stabilization of the area, offer more operator control, and reduce the potential for a voltage collapse in the U.P.

Ken Jauquet, ATC project manager, comented that "commendations are due all around for a great job. Great teamwork and dedicated effort on the part of ATC staff, Black and Veatch, MJ Electric, Coleman Engineering, and We Energies made completion of this project in an extremely short timeframe possible."

 

 
privacy policy
Your privacy is important to us. View our full Privacy Policy.
Copyright © 2007 by ATC LLC All rights reserved.