|
Columbia Substation equipment
installation increases reliability
In Fall 2001, ATC’s Transmission
Planning Group identified improvements that needed to be made
at the Columbia substation in order to improve reliability.
In Spring 2002, ATC installed a breaker and one-half configuration
at the Columbia 345 kV substation that provided increased reliability
for one of the three lines that exit the substation. In total,
approximately $2.6 million will be spent to improve the reliability
on all of the three lines by the end of the project in April
2003.
 |
PHASE 1
- Install a 345kV breaker to keep Columbia--North
Madison in service in case one breaker failed
and to upgrade the relay system
PHASE 2
- Install an additional 345kV breaker and upgrade
the relay system on the Columbia -- South Fond
du Lac and Columbia -- Rockdale lines
|
|
ATC and Alliant employees teamed up to complete the first phase
of the project in a very short, eight-month time frame. These
crews went "the extra mile" to complete the project.
Matt Weber, ATC Project Manager, complimented the crews. He
said, "without the combined efforts of these individuals,
the benefits of this work would not have been realized."
The benefit of this work was soon realized. On February 9,
2003, a failure of one of the two breakers on the Columbia to
North Madison line occurred. It took ten days to repair the
breaker; however, the work that was done to install the new
breaker at Columbia avoided costly redispatch and allowed construction
work to continue on other important transmission lines. The
potential impact of this outage would have cost ATC customers
almost $3 million.
ATC Transmission Reliability Administrator Bill Hoesly offered,
"from this one event, it is evident that the breaker addition
at Columbia was critical to system reliability."
|